3/14/1812/FP – Erection of generator compound at Rye Meads Sewage Treatment Works, Stanstead Abbotts, Ware, Hertfordshire, SG12 8JY for Peakgen Power Ltd

Decided Committee 3 papers

Development Management Committee decided this item on Wednesday 27 May 2015. Below is the council's own wording, with the papers it was decided on.

Item37

Resolved

RESOLVED – that in respect of application 3/14/1812/FP, planning permission be granted subject to the conditions detailed in the report now submitted.
Word for word from the decision East Hertfordshire published for this meeting. Source: democracy.eastherts.gov.uk

Follow this further

Built from East Hertfordshire's papers

What the report saysPro

Report to Development Management Committee, 6 pages

Recommendation

That planning permission be GRANTED subject to the following conditions:

1. Three year time limit (1T121)

2. Approved plans (2E103)

3. Landscape Design proposals (4P12) (a, e, f, i, k and l)

4. Landscape Works Implementation (4P13)

5. Prior to the commencement of the development hereby approved, details of all boundary acoustic fences or other means of enclosure shall be submitted to and approved in writing by the Local Planning Authority and thereafter shall be erected and retained in accordance with the approved details.

Reason: In the interests of good design, in accordance with policy ENV1 of the East Herts Local Plan Second Review April 2007.

6. The development hereby permitted shall be undertaken in accordance with the approved Flood Risk Assessment, unless otherwise agreed in writing by the Local Planning Authority.

Reason: In the interest of flood risk and in accordance with Policy ENV19 of the East Herts Local Plan Second Review April 2007 and the National Planning Policy Framework.

Summary of Reasons for Decision

East Herts Council has considered the applicant's proposal in a positive and proactive manner with regard to the policies of the Development Plan (Minerals Local Plan, Waste Core Strategy and Development Management Policies DPD 2012 and the 'saved' policies of the East Herts Local Plan Second Review April 2007); the National Planning Policy Framework and in accordance with the Town and Country Planning (Development Management 3/14/1812/FP

Procedure) (England) Order 2015. The balance of the considerations having regard to those policies and lpa 3/14/0768/FP is that permission should be granted. 181214FP.LP)

Background

1.1The application site is shown on the attached OS extract. It comprises a roughly rectangular parcel of land that measures 120 x 30 metres, with a narrower element to allow access measuring 35 x 10 metres . The site is within the Thames Water Rye Meads Treatment Works, located some 1000 metres to the north east of the residential properties on Rye Road, Hoddesdon. Vehicular access can also be taken via the B181 to the north east and along the toll road. The location is within the Green Belt. A large part of the sewage treatment works to the south of this site is identified as a Major Developed Site in the Green Belt. This application site lies outside of that designation.

1.2The proposal includes 10 generator containers (12.2 x 2.4 metres in footprint to a height of 4.5 metres), 5 transformers (3.4 x 3.4 metres in footprint with a maximum height of 3.7 metres), 5 fuel tanks (5.4 x 1.9 metres in footprint to a height of 2.0 metres) and 2 switchgear structures. 40 solar panels will also be installed on the structures. The proposal is enclosed by acoustic fencing. The installation is proposed to operate as a Short Term Operating Reserve (STOR) and provide stand by or back up electricity generating capacity to deal with periods of stress on the national network.

1.3Planning permission for an identical generator compound was approved under lpa 3/14/0768/FP. It is understood that, for reasons to do with ownership and permission from landowners, the earlier permission cannot now be implemented. The development is therefore now proposed to this different site area. A Unilateral Undertaking has been submitted which details that if that earlier consent is implemented then the current proposal will not be developed and vice versa. This will ensure that the 2 proposals cannot both be implemented.

1.4It is the requirement for the Legal Agreement that results in this report being submitted to the Committee.

2.0Site History

2.1Planning permission was granted last year for the same generator compound proposal but on a site some 25 metres to the north east. (3/14/0768/FP). 3/14/1812/FP

3.0Consultation Responses

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
3/14/1812/FP: Erection of generator compound at Rye Meads Sewage Treatment Works, Stanstead Abbotts, Ware, Hertfordshire, SG12 8JY for Peakgen Power LtdReport 6 pages DownloadRead as text
PDF
3141812FP 1-10000Report 1 MB Download
PDF
3141812FP 1-2500Report 1 pages Download

At this meeting

Whole meeting

More from East Hertfordshire Development Management Committee

All decisions
MeetingDecisionOutcome
12 Aug 2026 3/25/1986/FUL - Erection of 4 x industrial units (use classes E[g], B2 and B8) with associated parking and external works at Buntingford Business Park, Baldock Road, BuntingfordRESOLVED - in accordance with paragraph 6.5.6 of the constitution, Fergus Alexander be permitted to address the Commi... Decided Open
12 Aug 2026 Items for Reporting and NotingRESOLVED – that the following reports be noted: (A) Appeals against refusal of planning permission / non-determinatio... Noted Open
15 Jul 2026 Appointment of Vice-Chair for the 2026/27 civic yearRESOLVED – that Councillor J Thomas be appointed Vice-Chair of the Development Management Committee for the 2026/27 c... Decided Open
15 Jul 2026 Minutes - 15 April 2026RESOLVED – that the Minutes of the meeting held on 15 April 2026, be confirmed as a correct record and signed by the ... Decided Open
15 Apr 2026 Minutes - 11 March 2026RESOLVED – that the Minutes of the meeting held on 11 March 2026, be confirmed as a correct record and signed by the ... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies