Executive Board, Tuesday 15 January 2008 at 4.00pm

Mablethorpe Public Realm - Proposed Improvements to Sea View Car Park and Construction of New Skate Boarding Facility

Approved Executive 1 paper

Executive Board approved this item on Tuesday 15 January 2008. Below is the council's own wording, with the papers it was decided on.

Item79

Resolved

RESOLVED That subject to all external funding being confirmed and following consultation with the local Members, that the following be approved by the Executive Board: i) To allocate funding of £105K (£55K General Economic Provision/£50K CAZ) for improvements to Sea View Car Park and the construction of a new skate boarding facility in Mablethorpe as a contribution to the overall projected scheme cost of £360K (the remainder to be funded by other external bodies as identified and the Portfolio Holder in consultation with the Chief Executive be authorised to amend the scheme to reflect the views of local Members). ii) To grant an exception to the Council's Contract Procedure Rules under '14.2 - Contracts above £50,000' and approve the use of the Council's existing Measured Term Contracts for procuring the proposed works. Subject to the above: iii) Recommend to Council the promotion of the scheme from pre commitment to invest to commitment to invest and amend the Capital Programme for 2007/08 to 2009/10 as follows: 2007/2008 Council 19/12/2007 Revised 2007/ 2008 2008/ 2009 2009/ 2010 Total £’000 £’000 £’000 £’000 £’000 Current Programme 10,631 10,631 13,263 3,900 27,794 Current Commitment to Invest 5,042 5,147 9,917 3,434 18,498 Mablethorpe Public Realm – Expenditure – Funding 148 212 -255 360 -255 Revised Commitment to invest 5,042 5,295 9,874 3,434 18,603 Grant Aided Schemes 1,899 1,899 838 466 3,203 Current Pre Commitment to Invest 3,690 3,585 2,508 6,093 CAZ Funding General ED Provision -50 -55 -50 -55 Revised Pre Commitment to Invest 3,690 3,480 2,508 0 5,988 Revised Programme 10,631 10,674 13,220 3,900 27,794 Reasons for the Decision - i) The Mablethorpe Public Realm Strategy (Draft) has identified that Sea View Car Park is an area in need of considerable refurbishment/ enhancement and the proposals will support a number of objectives including the Council's Corporate Strategy for 2007-2012 with the following ambitions for East Lindsey: · Improve our economic prosperity · Nurture our distinctive and vibrant communities · Reduce inequality to improve quality of life. ii) By using existing contracts already in place it will allow improvements to be delivered early in 2008 with a start on site in February and phased completions prior to the Easter holiday period and May Day bank ... view the full minutes text for item 79.
Word for word from the decision East Lindsey published for this meeting. Source: democracy.e-lindsey.gov.uk

Follow this further

Built from East Lindsey's papers

What the report saysPro

Report to Executive Board, 7 pages

Recommendation

It is recommended that, subject to all external funding being confirmed and consultation with the Chief Executive, that Executive Board should approve the following:

i) To allocate funding of £105K (£55K General Economic Provision/£50K CAZ) for improvements to Sea View Car Park and the construction of a new skate boarding facility in Mablethorpe as a contribution to the overall projected scheme cost of £360K (remainder to be funded by other external bodies as identified);

ii) To grant an exception to the Council's Contract Procedure Rules under '14.2 - Contracts above £50,000' and approve the use of the Council's existing Measured Term Contracts for procuring the proposed works.

Subject to the above:

iii) Recommend to Council the promotion of the scheme from pre commitment to invest to commitment to invest and amend the Capital Programme for 2007/08 to 2009/10 as follows: 2007/2008 Revised 2008/ 2009/ Total Council 2007/ 2009 2010 19/12/2007 2008 £’000 £’000 £’000 £’000 £’000 Current Programme 10,631 10,631 13,263 3,900 27,794

Current Commitment to Invest 5,042 5,147 9,917 3,434 18,498 Mablethorpe Public Realm – Expenditure 148 212 360 -- Funding -255 -255 Revised Commitment to invest 5,042 5,295 9,874 3,434 18,603

Grant Aided Schemes 1,899 1,899 838 466 3,203

Current Pre Commitment to Invest 3,690 3,585 2,508 6,093 CAZ Funding -50 -50 General ED Provision -55 -55 Revised Pre Commitment to Invest 3,690 3,480 2,508 0 5,988

Revised Programme 10,631 10,674 13,220 3,900 27,794

Reasons for recommendation

i) The Mablethorpe Public Realm Strategy (Draft) has identified that Sea View Car Park is an area in need of considerable refurbishment/ enhancement and the proposals will support a number of objectives including the Council's Corporate Strategy for 2007-2012 with the following ambitions for East Lindsey:

• Improve our economic prosperity • Nurture our distinctive and vibrant communities • Reduce inequality to improve quality of life.

ii) By using existing contracts already in place it will allow improvements to be delivered early in 2008 with a start on site in February and phased completions prior to the Easter holiday period and May Day bank holiday. This will avoid any unnecessary disruption to visitors and allow a number of ‘quick wins’ to be facilitated at an early stage.

OTHER OPTIONS FOR CONSIDERATION

To not approve the scheme and risk loss of momentum with the Public Realm Strategy. FINANCIAL IMPLICATIONS

Within the Council’s Current approved Capital Programme there is in the pre commitment to invest section provision of £150K for CAZ Contribution and £3.262M General Economic Development Provision from which the Council’s total contribution of £105k can be funded.

The proposals are for a £360K scheme that will be funded as follows:

Description Funding £ East Lindsey District Council 105,000 Lincolnshire County Council 65,000 EMDA 185,000 Private Sector 5,000 TOTAL £360,000

There will be no overall change in the value of the Capital Programme and as such there will be no impact on the prudential indicators.

RISK MANAGEMENT IMPLICATIONS

IMPLICATIONS HIGH MEDIUM LOW NONE FINANCIAL X ENVIRONMENTAL X PERSONNEL X CRIME & DISORDER X HUMAN RIGHTS X DATA PROTECTION X FREEDOM OF INFO X RISK X LEGAL X EQUALITIES & DIVERSITIES X

1.0REPORT/INTRODUCTION

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Mablethorpe Public Realm: Proposed Improvements to Sea View Car Park and Construction of New Skate Boarding Facility:Report 7 pages DownloadRead as text

At this meeting

Whole meeting

More from East Lindsey Executive Board

All decisions
MeetingDecisionOutcome
23 Sep 2026 East Lindsey Investment Fund Update ReportThat the un-committed spend of ELIF 1 in para 2.3 and for ELIF 2 in para 2.5 be noted. 2. That the proposed activitie... Noted Open
23 Sep 2026 Acceptance of Ministry of Housing, Communities and Local Government (MHCLG) Playground Fund GrantThat the signed Memorandum of Understanding between East Lindsey District Council and MHCLG for the Playground Fund b... Noted Open
23 Sep 2026 Vehicle parking improvements to the Waste Depot, Fairfield Industrial Estate, LouthThat the addition of £500,000 to the 2026/27 Capital Programme to fund the improvements to vehicle parking provision ... Approved Open
23 Sep 2026 2026/27 Quarter 1 Finance Update1) That the General Fund forecast revenue outturn position for 2026/27 being an underspend of £56k as detailed in Tab... Noted Open
23 Sep 2026 Quarter 1 26/27 Performance and Risk ReportThat the performance and risk information contained within the report and appendices be noted. 2. That the risk appet... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies