Lincs Building Consultancy Executive Board, Monday 26 January 2009 at 9.30am

Financial Monitoring & Position Statement Report

Agreed Executive 2 papers

Lincs Building Consultancy Executive Board agreed this item on Monday 26 January 2009. Below is the council's own wording, with the papers it was decided on.

Item57

Resolved

It was agreed that an Extraordinary Meeting would be held on 9 February 2009, and that a report would be considered regarding all aspects of the LBC service in particular the risks of DS On Call and to consider ‘Street Naming’ issues also raised at the Meeting. RESOLVED That an Extraordinary Meeting of Lincs Building Consultancy Executive Board be held on 9 February 2009 at the Knoll, Knoll Street, Cleethorpes at 9:30am. That a report be presented to the Extraordinary Meeting of Lincs Building Consultancy Executive Board to be held on 9 February 2009 covering all aspects of the LBC service in particular the risks of DS On Call and Street Naming.
Word for word from the decision East Lindsey published for this meeting. Source: democracy.e-lindsey.gov.uk

Follow this further

Built from East Lindsey's papers

What the report saysPro

Report to Lincs Building Consultancy Executive Board, 4 pages

Recommendation

The Board is recommended to:-

1) Note the financial performance of the partnership against budgets; 2) Support a review of the way the Non Fee Earning work is financed by both partner Councils.

Reasons for recommendation

Monitoring and information.

OTHER OPTIONS FOR CONSIDERATION

None.

Financial implications

It can be seen from Appendix A attached that the Partnership is currently showing a loss of £86k as at 31st December 2008. This is mainly due to a reduction in application fee income.

IMPLICATIONS HIGH MEDIUM LOW NONE FINANCIAL x ENVIRONMENTAL x PERSONNEL x CRIME & DISORDER x HUMAN RIGHTS x DATA PROTECTION x RISK x 1.0. RISK

1.1Failure to monitor and maintain performance and financial targets will adversely affect customers and the financial viability of the partnership.

2.0REPORT/INTRODUCTION

2.1The partnership has faced a considerable downturn in applications and income over the last 9 months. As previously reported the partnership has made strenuous efforts to reduce its operating costs in the face of the current recession. The partnership has:- a) Implemented a restructure.

b) Undertaken preparation of plans in connection with disabled grants.

c) Providing Clark of the Works for both Councils.

d) Developed a risk assessment inspection policy.

e) Tender for Building Control work outside of the district.

f) Increase the Building Control charges.

2.2When the downturn in the workload was first identified in October 2007, Lincs Building Consultancy in conjunction with both Councils reacted swiftly to identify the course of action necessary to meet the challenges. Nobody at that time could have predicted the enormity of the challenges we now face. Lincs Building Consultancy’s management team have reacted swiftly and decisively since that time to restructure the service. This restructure will be completed by March 2009, and will have seen a reduction of 6.5 full time employees which is approximately 20%.

2.3Although application numbers and income have shown a sharp decline over the past 12 months the income from fees is still allowing the service to breakeven on its core Building Control Fee Earning work. The number of hours recorded for Fee Earning work between 1st January 2008, and 31st December 2008 is 36,382 and the hours booked to Non Fee Earning are 13,191. The grant/budgetary allocation paid for this Non Fee Earning work equates to an hourly rate paid of approximately £17.90 per hour. This means it is impossible for the partnership to recover its costs when undertaking this work. This is in comparison to the £45 per hour, which is paid for the work we undertake under the agreed Service Level Agreements e.g. Dangerous Structures.

2.4When the budgetary allocation was agreed in 2006, the number of Non Fee Earning applications which both Councils received was approximately 3,000 per year whereas it now stands at 15,000 per year. As the government has expanded the Competent Persons Scheme the cost of processing these applications has increase due to their number. The drive for energy 2 conservation has also driven up the numbers of cavity wall applications. This has also increased the pressure on the Fee Earning income to subsidise the processing of Non Fee Earning applications.

2.5The partnership has also seen a rise in Non-Fee Earning applications connected with disabled applications. The loss of income for undertaking this work is approximately £13k since January 2008. This is another area that needs to be addressed by the introduction of Service Level Agreements with both Councils.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Financial Monitoring & Position Statement Report:Report 4 pages DownloadRead as text
PDF
Financial Monitoring: AppAReport 1 pages Download

At this meeting

Whole meeting

On this subject at East Lindsey

Search all
  1. Financial Monitoring & Position Statement ReportThis decision
  2. Financial Performance Monitoring ReportNoted
  3. Financial & Performance monitoring reportNoted
  4. Revenue and Capital Budget Monitoring, Quarter 3 Financial UpdateNoted
  5. Financial and Performance Monitoring Report 2009/10Noted
  6. Performance and Financial Monitoring ReportNoted

More from East Lindsey Lincs Building Consultancy Executive Board

All decisions
MeetingDecisionOutcome
27 Jun 2011 Election of ChairmanRESOLVED That Councillor A. Wallace be elected Chairman of the Lincs Building Consultancy for the 2011/12 Council year. Decided Open
27 Jun 2011 Election of Vice-ChairmanRESOLVED That Councillor N.D. Cooper be elected as Vice-Chairman of the Lincs Building Consultancy for this Meeting o... Decided Open
27 Jun 2011 Director's End of Year Report 2010-11RESOLVED That the draft 2010/11 end of year financial report be approved and the annual return signed off by the Chai... Approved Open
27 Jun 2011 Financial Performance Monitoring ReportRESOLVED That the progress on the partnership be noted. Noted Open
27 Jun 2011 To consider proposed meeting dates for 2011/12It was agreed to circulate proposed Meeting dates for the 2011/12 Council year, following the Meeting. Agreed Open