Feasibility Study

Noted Planning 2 papers

Planning Policy Committee noted this item on Thursday 5 March 2009. Below is the council's own wording, with the papers it was decided on.

Item36

Resolved

RESOLVED 1) That the contents of the report be noted. 2) That the methodology proposed, as detailed at Appendix A to the report presented, be used on each of the long listed growth and development options listed at paragraph 2.1 on the report presented, as part of the Feasibility Study, to inform the Local Development Framework subject to the following amendments: i) Archaeology – That the title be amended to read ‘Archaeology and Ancient Monuments’. ii) Flood Risk – That the title be amended to read ‘Flood Risk and Surface and Foul Water’. iii) Regeneration Opportunities – That a section titled ‘Regeneration Opportunities be inserted, to include Tourism and funding options. iv) Community Facilities – That the title be amended to read ‘Community Facilities and new Community Centres’. 3) That the Methodology be completed prior to the consultation process being undertaken. 4) That a Sustainability Appraisal be undertaken using the 13 objectives identified in the scoping report. (Councillor K.D. Sharpe left the Meeting at 3.55 p.m.)
Word for word from the decision East Lindsey published for this meeting. Source: democracy.e-lindsey.gov.uk

Follow this further

Built from East Lindsey's papers

What the report saysPro

Report to Planning Policy Committee, 8 pages

Appendix A DRAFT

LOUTH DESKTOP STUDY

DEMOGRAPHICS

Population

The population of Louth as cited in the 2001 census was 15930 made up from 6871 households.

Projects from the ONS mid year estimates show that the population of the District as a whole will continue to increase.

1 Employment

From information from the 2001 Census in the seven Louth Wards there were 6894 economically active persons between the ages of 16 and 74 of those 714 were self-employed.

To be populated from information from the Employment Land Review

INFRASTRUCTURE

In March 2008 the Council commissioned a provisional appraisal of baseline environmental issues for five earmarked sites for future employment land in Louth. However this study also provided useful information on the condition of the existing infrastructure in and around Louth.

2 Electricity supply – although there would appear to sufficient power in the current 33kV primary network, any new large user (high-end data processing and/or industrial user within Louth or simultaneous major residential growth would potentially lead to a shortfall in spare capacity. Reinforcement of the primary network from the nearest bulk supply substation would cost approximately £13500k with a new 20m x 30m land allocation to support a new primary substation.

Foul water – Anglian Water Services have stated that there is insufficient capacity in the foul sewerage network within Louth to accommodate any new or extended employment land, it would therefore be a fair assumption that this would also apply to any substantial residential growth. This problem is alleged to be so bad that the town- centre sewers frequently surcharge and occasionally flood during storm conditions. Anglian Water Services have advised that network reinforcement might cost in the region of £3m and this is assuming that no further reinforcement work is required at the sewage treatment works itself.

National Grid Gas – If there was a substantial amount of residential growth accompanied by an increase in employment land then the National Grid modelling indicates that network reinforcement would be required.

OTHER POTENTIAL DEVELOPMENT CONSTRAINTS

Archaeology

Louth developed as a town in the Anglo-Saxon period, evidence of Romano-British activity is limited to a few isolated find spots. A substantial cemetery of some 400 cremation urns was excavated at South Elkington and in Louth itself there have been some Saxon finds.

3 The town continued to expand during the Medieval period and given a boost by the completion of the Louth Canal in 1770 which allowed access to the sea at Tetney Lock. This led to the development of the Riverhead suburb at the east of the town.

Flood risk

The river Lud runs through Louth west to east and has its fluvial flood plain, whilst much historic development lies within this flood plain to the east of the town the river runs out of the built up urban area and into the open countryside. The river area is covered by the Draft Louth Coastal Catchment Flood Management Plan. That document states that crucial to managing flood risk new development should be minimised in areas of flood risk such as the fluvial flood plain.

Landscape Designations

Within the Landscape Character Appraisal the area around Louth and Louth itself falls within two landscape character types; G1 – Wolds Farmland, Binbrook to Tetney Wolds Farmland, the landscape sensitivity is considered to be moderate to high; and I1 Holton le Clay to Great Steeping Middle Marsh, the landscape is considered moderate to high. To the west of Louth and almost butting up with the urban built environment lies the Wolds Area of Outstanding Natural Beauty. Development would be constrained by the AONB if it impacted on the character or visual amenity of the AONB.

Green Infrastructure

Will require further input from the Green Infrastructure Plan.

Retail Vitality

In March 2007 the Council commissioned a retail capacity study for Louth. The shopping survey undertaken for

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Feasibility Study: AppAReport 8 pages DownloadRead as text
PDF
Feasibility Study:Report 4 pages Download

At this meeting

Whole meeting

More from East Lindsey Planning Policy Committee

All decisions
MeetingDecisionOutcome
20 May 2026 Election of Vice ChairmanThat Councillor Terry Aldridge be elected Vice-Chairman of the Planning Policy Committee for the Council year 2026/27. Decided Open
14 May 2026 Conservation Area AppraisalsRESOLVED That the Committee noted and endorsed the conservation area appraisals and South East Lincolnshire Tradition... Noted Open
21 May 2025 Election of Vice-ChairmanThat Councillor Terry Aldridge be elected Vice-Chairman of the Planning Policy Committee for the Council year 2025/26. Decided Open
17 Oct 2024 ActionsIt was agreed that the Actions would be deferred to the next Committee Meeting. Agreed Open
22 May 2024 Election of Vice-ChairmanThat Councillor Terry Aldridge be elected Vice-Chairman of the Planning Policy Committee for the Council year 2024/25. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies