Resolved

RESOLVED 1) That the Settlement Hierarchy detailed at Appendix 2 to the report presented be approved and for it to be used to formulate the East Lindsey Local Development Framework subject to the following amendment: Page 66 - Points System Agreed for Ranking of Community Facilities - ‘Church’ should be amended to read ‘A Place of Worship’. 2) That a copy of the ‘Scoring Sheet’ be circulated to Members of the Planning Policy Committee.
Word for word from the decision East Lindsey published for this meeting. Source: democracy.e-lindsey.gov.uk

Follow this further

Built from East Lindsey's papers

What the report saysPro

Report to Planning Policy Committee, 4 pages

Summary

This report considers the future Settlement Hierarchy for East Lindsey to be used as a basis for developing policies in the East Lindsey Local Development Framework (LDF). The hierarchy is based on a methodology agreed by Planning Policy Committee on 4th September 2008. The methodology set the thresholds for services and facilities required within a settlement for each tier in the hierarchy and is attached as Appendix 1 to this report. The resulting recommended hierarchy is set out in Appendix 2 to this report.

Recommendations

That the Settlement Hierarchy set out in Appendix 2 of this report be approved by Members to be used in drawing up the East Lindsey Local Development Framework

This report has been prepared by: Kay Turton

Tel: 01507 601111 ext 323 e-mail: [email protected]

This report was prepared after consultation with:

Planning Policy Committee (4th September 2008)

This report is number 1 in a series of 1.

This report has been signed off by:

Simon Machen

The following policies form a context to this report: National Planning Policy Guidance and Planning Policy Statements

This report is a key decision included in the Forward Plan.

LIST OF BACKGROUND PAPERS AS REQUIRED BY LAW (papers relied on to write the report but which are not published and do not contain exempt information)

1. Minutes of the Planning Policy Committee (04.09.08)

OTHER HELPFUL PAPERS (papers which the report author considers might be helpful – this might include published material)

1. N/A

Local Government (Access to Information Act) 1985

Is the report Exempt –No

Please contact the person who has written this report or Anne Shorland Tel. No. 01507 60111 ext 318 e-mail: [email protected], if you want more information about this report or the background papers.

1.0INTRODUCTION

1.1Members will recall that, following consideration of the Core Strategy Issues and Options paper, the Planning Policy Committee resolved to pursue a spatial settlement strategy based on an urban-focussed settlement hierarchy allowing for urban extensions and rural restraint but also taking account of development needs in the more sustainable villages.

1.2At the meeting of this Committee on 4th September 2008, Members discussed and approved a methodology for determining this hierarchy. The methodology set the thresholds for services and facilities for each tier in the hierarchy and is attached as Appendix 1 to this report.

1.3Following this meeting, Parish Council’s, and elected members, were sent a survey form to establish the level of facilities in each village. In addition, for those villages being surveyed as part of the Strategic Housing Land Availability Assessment (SHLAA), officers have completed a survey form when they have been out surveying sites. For those settlements where no return has been provided (and which do not form part of the SHLAA) previous data has been used, updated where we have information available.

1.4The available data has been matched against the agreed methodology and entered into a spreadsheet, leading to the proposed Settlement Hierarchy recommended for agreement today. This is attached at Appendix 2.

2.0OTHER OPTIONS FOR CONSIDERATION (drawn from previous sections) 2.1. The hierarchy set out in Appendix 2 has evolved from the methodology agreed by this committee on 4th September 2008. If Members wish to make any amendments to this hierarchy, the factors used to adjust the hierarchy will have to be applied equally across all settlements and will require a future report being brought back to this Committee.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
East Lindsey Local Development Framework Settlement Hierarchy:Report 4 pages DownloadRead as text
PDF
Settlement Hierarchy: Appendix 1Appendix 2 pages Download
PDF
Settlement Hierarchy: Appendix 2Appendix 2 pages Download

At this meeting

Whole meeting

On this subject at East Lindsey

Search all
  1. East Lindsey Local Development Framework Settlement HierarchyThis decision
  2. East Lindsey Investment Fund Update ReportNoted
  3. East Lindsey Investment Plan UpdateNoted
  4. East Lindsey Age-friendly AssessmentNoted
  5. Supporting East Lindsey businesses with energy decisions and investmentsApproved
  6. East Lindsey Investment Fund and Capital ReservesApproved

More from East Lindsey Planning Policy Committee

All decisions
MeetingDecisionOutcome
20 May 2026 Election of Vice ChairmanThat Councillor Terry Aldridge be elected Vice-Chairman of the Planning Policy Committee for the Council year 2026/27. Decided Open
14 May 2026 Conservation Area AppraisalsRESOLVED That the Committee noted and endorsed the conservation area appraisals and South East Lincolnshire Tradition... Noted Open
21 May 2025 Election of Vice-ChairmanThat Councillor Terry Aldridge be elected Vice-Chairman of the Planning Policy Committee for the Council year 2025/26. Decided Open
17 Oct 2024 ActionsIt was agreed that the Actions would be deferred to the next Committee Meeting. Agreed Open
22 May 2024 Election of Vice-ChairmanThat Councillor Terry Aldridge be elected Vice-Chairman of the Planning Policy Committee for the Council year 2024/25. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies