Planning Committee, Thursday 12 March 2009 at 2.00pm

Proposed Construction of an Offshore Wind Farm

Decided Planning 2 papers

Planning Committee decided this item on Thursday 12 March 2009. Below is the council's own wording, with the papers it was decided on.

Item101

Resolved

RESOLVED That the proposal of an offshore Wind Farm at Race Bank, 16 miles off Chapel St. Leonards be supported by the Planning Committee.
Word for word from the decision East Lindsey published for this meeting. Source: democracy.e-lindsey.gov.uk

Follow this further

Built from East Lindsey's papers

What the report saysPro

Report to Planning Committee, 6 pages

EAST LINDSEY DISTRICT COUNCIL REPORT COMMITTEE: PLANNING COMMITTEE

DATE: 12TH MARCH 2009

SUBJECT: PROPOSED CONSTRUCTION OF AN OFFSHORE WIND FARM

PORTFOLIO HOLDER Councillor Brian Burnett

Ward(s) affected: N/A

Brief description of report content and the decision being asked for:

Summary: This report is to advise the Planning Committee members of a proposal to construct a Wind farm at Race Bank some 16 miles off Chapel St. Leonards.

Recommendations: That the Planning Committee support the proposal of an offshore wind farm in this location.

This report has been prepared by:

[name removed]: 01507 601 111 e-mail: [email protected]

This report was prepared after consultation with:

Simon Machen

This report is number 1 in a series of 1

This report has been signed off by:

Simon Machen – Business Manager

The following policies form a context to this report:-

None applicable for offshore wind farms. LIST OF BACKGROUND PAPERS AS REQUIRED BY LAW (papers relied on to write the report but which are not published and do not contain exempt information)

None required.

OTHER HELPFUL PAPERS (papers which the report author considers might be helpful – this might include published material)

1. Copy of Environmental Statement dated January 2009 for Race Bank offshore wind farm.

Local Government (Access to Information Act) 1985

Is the report Exempt –No

1.0INTRODUCTION 1.1. The Department of Energy and Climate Change have requested comments from this council on applications made by Centrica for various consents relating to the installation and operation of a wind farm at Race Bank in the Wash; some 16 miles off the coast of Chapel St. Leonards and the North Norfolk coast. A location plan is attached to this report.

1.2The council is one of a number of consultees who have been consulted on the scheme and have been supplied with an Environmental Statement.

2.0SUBJECT INFORMATION & FACTS & FIGURES 2.1. The proposed Race Bank site is located within the Greater Wash Strategy area, which is one of three areas designated by Government in 2002 for future development of offshore wind farms.

2.2Centrica already owns the 2 completed and built offshore wind farms, which comprise 54 turbines some 3 miles offshore. Consent has also been granted in October 2008 for some 70 turbines at the Lincs offshore wind farm, which is just east of the two existing wind farms at Inner Dowsing and Lynn. The Committee will recall at the last meeting there was support in principle for a further wind farm at Docking Shoal, just south of the Race Bank site.

2.3The proposed Race Bank wind farm would have between 88 and 206 bladed wind turbines depending on the size of the turbines chosen. The maximum height to above high water level to blade tip would be 180m (591 feet), the maximum hub height would be 110m (361 feet) with a minimum spacing between turbines of 630m. The site would cover an area of some 29 square miles, would have a capacity of 620MW and would meet the domestic requirements of around 420,000 homes annually. On land the works would include buried cables and an extension to the existing substation at Walpole in Norfolk, forming the connection to the National Grid.

2.4A key part of the overall project has been the assessment of all potential locations and key criteria in the choice of location include:- results of surveys from the Greater Wash Strategy area, available wind resource, water depth, seabed obstructions, geology, construction limitations, operation and maintenance requirements, grid connection and stakeholder consultations.

2.5As part of the EIA process the identification and assessment of the key impacts has been considered and these are as follows with a summary position:-

a) Coastal Processes

During construction there would be some disturbance of seabed sediment, but this would be re-deposited quickly in the local area. During operation the overall effect would be minimal and in any event any effect is limited to within the wind farm site.

b) Marine Ecology

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Location Plan: Offshore WindfarmPlan 1 pages Download
PDF
Proposed Construction of an Offshore Wind Farm:Report 6 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at East Lindsey

Search all
  1. Proposed Construction of an Offshore Wind FarmThis decision
  2. Proposed Construction of an Offshore Wind FarmDecided
  3. Mablethorpe Public Realm - Proposed Improvements to Sea View Car Park and Construction of New Skate Boarding FacilityApproved

More from East Lindsey Planning Committee

All decisions
MeetingDecisionOutcome
2 Sep 2026 Tree Preservation Order: 137, Eastgate, Louth (105.36)That 137 Eastgate, Louth (105.36) Tree Preservation Order be confirmed (made permanent). Decided Open
2 Sep 2026 Tree Preservation Order: Land adjacent 116C Horncastle Road, Roughton Moor (215.31)That land adjacent to 116C Horncastle Road, Roughton Moor (215.31) Tree Preservation Order be confirmed (made permane... Decided Open
2 Sep 2026 00489/26/fulThat the application be approved. Approved Open
2 Jul 2026 03860/25/fulThat this Council resolve to grant planning permission with the application being referred to the Secretary of State ... Decided Open
20 May 2026 Election of ChairmanThat Councillor Stephen Eyre be elected Chairman of the Planning Committee for the Council year 2026/27. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies