CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
East Lindsey District Council
Executive Board, Tuesday 17 January 2012 at 10.00am

Refurbishment of public conveniences

Agreed Executive 2 papers

Executive Board agreed this item on Tuesday 17 January 2012. Below is the council's own wording, with the papers it was decided on.

Item57

Resolved

RESOLVED 1. That the scheme proposals set out below and in Appendix A, be agreed, and a further report seeking authority to extend the capital programme allocation in 2013/14 be brought forward if necessary; 2. That the programme for 2011/12 and 2012/13 be commenced; 3. That delegated authority be granted to the Portfolio Holder for the Environment to agree the detail and final costs for each of the individual schemes within the framework at Appendix A, in accordance with the agreed capital programme; 4. That the Portfolio Holder’s agreement to close the facility at Roman Bank, Skegness be confirmed, and 5. That the Portfolio Holder’s recommendation to withdraw the current charging arrangements be agreed. Reason To enable improvement works to commence immediately to ensure the 2011/12 and 2012/13 programmes are completed in a timely manner ahead of the 2012 season; and to determine the programme of improvements for the remaining facilities across the district. Other Options for Consideration To look to complete the refurbishment programme over a three to four year period rather than the current five year programmed capital allocation through an acceleration of budget availability from the capital programme. To consider the continuation of the charging regime for a number of the Skegness facilities which would require the purchase of replacement change machines and the introduction of new cash management measures to sustain the current charging arrangements.
Word for word from the decision East Lindsey published for this meeting. Source: democracy.e-lindsey.gov.uk

Follow this further

Built from East Lindsey's papers

What the report saysPro

Report to Executive Board, 1 pages

Estimated Costs for Public Convenience Improvement/Refurbishment Works Version 1.2 - 30th December 2011 UPRN Location Comments Total Cost Timeline Major Refurbishments 3328 Mablethorpe - Seacroft Road PC's To include a Changing Places facility £92,400 2011/12 3331 Mablethorpe - Central Promenade PC's £78,111 2012/13 3322 Louth - Eastgate PC's £64,570 2012/13 Sub-total £235,081 Improvement Schemes 3341 Skegness - Briar Way PC's Last refurbished in 2001 £20,621 2013/14 3302 Anderby Creek - Pullover PC's Last refurbished in 2007 £3,105 2013/14 3304 Burgh le Marsh - Market Place PC's Last refurbished in 1998 £21,068 2013/14 3313 Horncastle - St. Lawrence Street PC's Last refurbished in 2001 £32,297 2013/14 3332 Mablethorpe - Dunes PC's £41,900 2013/14 3337 Skegness - North Parade PC's £29,672 2013/14 3351 Sutton on Sea - Roman Bank PC's £7,354 2013/14 3360 Wragby - Market Place PC's £22,693 2013/14 3321 Louth - Bus Station PC's £33,342 2014/15 3330 Mablethorpe - Queens Park PC's £31,918 2014/15 3347 Skegness - Lumley Square PC's £10,776 2014/15 3338 Skegness - Tower Esplanade PC's New build in 2002 £28,935 2014/15 3345 Skegness - Princes Parade PC's £25,093 2014/15 3353 Sutton on Sea - York Road PC's £23,706 2014/15 3357 Wainfleet - Brooks Walk PC's £17,776 2014/15 3311 Coningsby - Castle Lane PC's £19,111 2015/16 3350 Spilsby - High Street PC's New build in 2003 £19,935 2015/16 3358 Woodhall Spa - Spa Road PC's Refurbished in 2002 £23,989 2015/16 3344 Skegness - Tower Gardens PC's No works required - Refurbished in 2011 £0 N/a Sub-total £413,291 Other 3314 Huttoft Bank - PC's Review after the introduction of the 'Structures on the Edge' observatory. 2012/13 3346 Skegness - Roman Bank PC's Permenantly close £11,824 2011/12 Sub-total £11,824 TOTAL ESTIMATED COST £660,196 NOTES:

The current cost estimates show that the programme can be completed to line 19 inclusive within the capital allocation. The estimate costs for the full scheme (including lines 20-27) equate to a further £160k of capital expenditure. The programme will be tightly managed and costs reviewed as the programme progresses with a view to revisiting the capital required to complete the programme from 2013/14.

Individual estimates for each location have been based on data contained within the following price guides: Spon's Architects' and Builders' Price Book 2011; BCIS Building Maintenance Price Book 2011 Edition (BCIS is the Building Cost Information Service of RICS).

Where 'major refurbishment' has been identified this may involve structural alterations and a complete refit of the entire facility in accordance with the agreed specification.

Where an 'improvement scheme' has been identified this will involve the upgrading of the facility where necessary to include the installation of new toilet cubicles, white vitreous china sanitary ware, thermostatic mixer valves, automatic sensing basin taps, assisted passive ventilation system, presence sensing lighting, new glazed wall tiling and decorations etc.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Refurbishment of Public Conveniences: AppAReport 1 pages DownloadRead as text
PDF
Refurbishment of public conveniences:Report 11 pages Download

At this meeting

Whole meeting

More from East Lindsey Executive Board

All decisions
MeetingDecisionOutcome
23 Sep 2026 East Lindsey Investment Fund Update ReportThat the un-committed spend of ELIF 1 in para 2.3 and for ELIF 2 in para 2.5 be noted. 2. That the proposed activitie... Noted Open
23 Sep 2026 Acceptance of Ministry of Housing, Communities and Local Government (MHCLG) Playground Fund GrantThat the signed Memorandum of Understanding between East Lindsey District Council and MHCLG for the Playground Fund b... Noted Open
23 Sep 2026 Vehicle parking improvements to the Waste Depot, Fairfield Industrial Estate, LouthThat the addition of £500,000 to the 2026/27 Capital Programme to fund the improvements to vehicle parking provision ... Approved Open
23 Sep 2026 2026/27 Quarter 1 Finance Update1) That the General Fund forecast revenue outturn position for 2026/27 being an underspend of £56k as detailed in Tab... Noted Open
23 Sep 2026 Quarter 1 26/27 Performance and Risk ReportThat the performance and risk information contained within the report and appendices be noted. 2. That the risk appet... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies