Resolved
That Council be recommended to approve the Mablethorpe depot refurbishment project be included as part of the previously agreed capital allocation for ‘capitalised repairs and maintenance.
Executive Board approved this item on Tuesday 23 April 2013. Below is the council's own wording, with the papers it was decided on.
Resolved
That Council be recommended to approve the Mablethorpe depot refurbishment project be included as part of the previously agreed capital allocation for ‘capitalised repairs and maintenance.
East Lindsey District Council Refurbishment of Depot Mablethorpe 08-Apr-13
Target Cost 4
Remove Existing Fencing £ 741.00
Install New Palisade Fencing £ 9,100.00
2nr. Pairs of Gates £ 1,500.00
Single Access Gate £ 350.00
General Site Clearance £ 1,690.00
Remove & Dispose Oil Tank £ 350.00
Remove Steel Structure Included
Strip Existing Cladding and £ 45,620.00 Install New Cladding & bird spikes
Remove Existing Roller Shutter Door Included
Install New Galvanise Roller Shutter Door Included
Remove Door & Frame Included
Install New Steel Door & Frame Included
Remove Timber Door & Frame & Infill with Blockwork £ 175.00
Ditto to Window £ 155.00
Break Out & Install New Yard Gully, make up of £ 1,676.00 a brick structure & hinged grating
Break Out & Install New Dished Channel Included
Install New Push Walls with Sleepers & Steels £ 8,311.00
Excavate & Lay New Concrete Hardstanding Area £ 5,227.00
White Lining Works £ 500.00
Paint Exposed Steelwork to Open Part of Canopy £ 755.00
Electrical works £ 2,850.00
Water service £ 615.00
Additional Concrete Area to Bins £ 1,140.00
Pothole Repairs £ 705.00
Additional Fencing to Front Boundary £ 2,316.92
Sub Total £ 83,776.92
Contract Prelims £ 3,400.00
Planning Application & Fee £ 500.00
Provision for Bond £ 475.00
Provision for CDMC £ 1,000.00
Provisional Sums
New Electrical Service £ 3,000.00
New Water Service £ 2,000.00
Signage £ 1,000.00
Internal Fitout Works £ 5,000.00
Contingency Sum £ 8,000.00
Sub Total £ 108,151.92
Profit & Overheads 9.75% £ 10,544.81
Sub Total £ 118,696.73
EMPA Fee 0.95% £ 1,127.62
Target Cost £ 119,824.35
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Mablethorpe Depot: Final Cost Estimates: AppAReport | 2 pages | DownloadRead as text |
PDF |
Mablethorpe Depot: Photos: AppBReport | 6 pages | Download |
PDF |
Mablethorpe Depot:Report | 6 pages | Download |
Follow Executive Board at East Lindsey and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 23 Sep 2026 | East Lindsey Investment Fund Update ReportThat the un-committed spend of ELIF 1 in para 2.3 and for ELIF 2 in para 2.5 be noted. 2. That the proposed activitie... | Noted | Open |
| 23 Sep 2026 | Acceptance of Ministry of Housing, Communities and Local Government (MHCLG) Playground Fund GrantThat the signed Memorandum of Understanding between East Lindsey District Council and MHCLG for the Playground Fund b... | Noted | Open |
| 23 Sep 2026 | Vehicle parking improvements to the Waste Depot, Fairfield Industrial Estate, LouthThat the addition of £500,000 to the 2026/27 Capital Programme to fund the improvements to vehicle parking provision ... | Approved | Open |
| 23 Sep 2026 | 2026/27 Quarter 1 Finance Update1) That the General Fund forecast revenue outturn position for 2026/27 being an underspend of £56k as detailed in Tab... | Noted | Open |
| 23 Sep 2026 | Quarter 1 26/27 Performance and Risk ReportThat the performance and risk information contained within the report and appendices be noted. 2. That the risk appet... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.