East Lindsey District Council
Executive Board, Tuesday 23 April 2013 at 10.00am

Mablethorpe Depot

Approved Executive 3 papers

Executive Board approved this item on Tuesday 23 April 2013. Below is the council's own wording, with the papers it was decided on.

Item76

Resolved

That Council be recommended to approve the Mablethorpe depot refurbishment project be included as part of the previously agreed capital allocation for ‘capitalised repairs and maintenance.
Word for word from the decision East Lindsey published for this meeting. Source: democracy.e-lindsey.gov.uk

Follow this further

Built from East Lindsey's papers

What the report saysPro

Report to Executive Board, 2 pages

East Lindsey District Council Refurbishment of Depot Mablethorpe 08-Apr-13

Target Cost 4

Remove Existing Fencing £ 741.00

Install New Palisade Fencing £ 9,100.00

2nr. Pairs of Gates £ 1,500.00

Single Access Gate £ 350.00

General Site Clearance £ 1,690.00

Remove & Dispose Oil Tank £ 350.00

Remove Steel Structure Included

Strip Existing Cladding and £ 45,620.00 Install New Cladding & bird spikes

Remove Existing Roller Shutter Door Included

Install New Galvanise Roller Shutter Door Included

Remove Door & Frame Included

Install New Steel Door & Frame Included

Remove Timber Door & Frame & Infill with Blockwork £ 175.00

Ditto to Window £ 155.00

Break Out & Install New Yard Gully, make up of £ 1,676.00 a brick structure & hinged grating

Break Out & Install New Dished Channel Included

Install New Push Walls with Sleepers & Steels £ 8,311.00

Excavate & Lay New Concrete Hardstanding Area £ 5,227.00

White Lining Works £ 500.00

Paint Exposed Steelwork to Open Part of Canopy £ 755.00

Electrical works £ 2,850.00

Water service £ 615.00

Additional Concrete Area to Bins £ 1,140.00

Pothole Repairs £ 705.00

Additional Fencing to Front Boundary £ 2,316.92

Sub Total £ 83,776.92

Contract Prelims £ 3,400.00

Planning Application & Fee £ 500.00

Provision for Bond £ 475.00

Provision for CDMC £ 1,000.00

Provisional Sums

New Electrical Service £ 3,000.00

New Water Service £ 2,000.00

Signage £ 1,000.00

Internal Fitout Works £ 5,000.00

Contingency Sum £ 8,000.00

Sub Total £ 108,151.92

Profit & Overheads 9.75% £ 10,544.81

Sub Total £ 118,696.73

EMPA Fee 0.95% £ 1,127.62

Target Cost £ 119,824.35

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Mablethorpe Depot: Final Cost Estimates: AppAReport 2 pages DownloadRead as text
PDF
Mablethorpe Depot: Photos: AppBReport 6 pages Download
PDF
Mablethorpe Depot:Report 6 pages Download

At this meeting

Whole meeting

On this subject at East Lindsey

Search all
  1. Mablethorpe DepotThis decision
  2. Mablethorpe DepotAgreed

More from East Lindsey Executive Board

All decisions
MeetingDecisionOutcome
23 Sep 2026 East Lindsey Investment Fund Update ReportThat the un-committed spend of ELIF 1 in para 2.3 and for ELIF 2 in para 2.5 be noted. 2. That the proposed activitie... Noted Open
23 Sep 2026 Acceptance of Ministry of Housing, Communities and Local Government (MHCLG) Playground Fund GrantThat the signed Memorandum of Understanding between East Lindsey District Council and MHCLG for the Playground Fund b... Noted Open
23 Sep 2026 Vehicle parking improvements to the Waste Depot, Fairfield Industrial Estate, LouthThat the addition of £500,000 to the 2026/27 Capital Programme to fund the improvements to vehicle parking provision ... Approved Open
23 Sep 2026 2026/27 Quarter 1 Finance Update1) That the General Fund forecast revenue outturn position for 2026/27 being an underspend of £56k as detailed in Tab... Noted Open
23 Sep 2026 Quarter 1 26/27 Performance and Risk ReportThat the performance and risk information contained within the report and appendices be noted. 2. That the risk appet... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies