1) That a recommendation be forwarded to Council for the Capital Programme to be amended to enable the allocation of a further £315,540.00 from the Capital Reserve for the delivery of the Local Broadband Plan; 2) That further clarity be sought regarding ‘not spots’ in the East Lindsey area and the future funding required to address this provision (taking into consideration any commercial confidentiality); 3) That Online Lincolnshire be invited to provide a briefing session to East Lindsey District Council Members prior to consideration of the matter at full Council and that future broadband progress in East Lindsey is effectively communicated.
Word for word from the decision East Lindsey published for this meeting.Source: democracy.e-lindsey.gov.uk
On 8th July 2011 Lincolnshire County Council submitted the Lincolnshire Broadband Delivery Plan to BDUK (Broadband Delivery UK), the government’s rural broadband delivery arm.
This submission secured an allocation of £14.3 million to implement Broadband roll out across the county with the objective of securing 90% coverage, with remaining properties having access to at least 2mbps connection.
Whilst this £14.3 million allocation was less than requested, it was the fifth largest allocation nationally.
Following the County Council’s commitment of £10 million, all District/Borough/City Councils in Lincolnshire committed to this Broadband partnership and agreed to meet the funding gap of £4 million. The specific Council contributions at that time were not finalised as they would be dependant upon the success of other external funding bids, primarily to Europe. As a consequence, the East Lindsey contribution was defined as being within a range between £887.990 and £1,315,540 (with the top end figure being a maximum).
In light of this uncertainty (but with the requisite need to make a commitment to BDUK) this Council took a mid-range figure of £1,000,000 for purposes of making allocation within the Capital Programme (2012).
The County Council has now requested the signing of a formal funding agreement incorporating a contribution from ELDC of £1,315,540. Clearly this funding agreement cannot currently be signed as the required amount exceeds the amount previously incorporated in the Capital programme. Any decision to amend the Capital Programme is a matter for Full Council.
Recommendations
1. Executive Board recommends that Council amends the Capital Programme to enable the allocation of a further £315,540 from the Capital Reserve for the delivery of the Local Broadband Plan. REASON: To enable the Council to contribute its proportion of funding for the successful completion of Broadband roll out across the District.
The following policies form a context to this report: n/a
The contents of this report will be a key decision for Council and is incorporated in the Forward Plan.
LIST OF BACKGROUND PAPERS (papers relied on to write the report but which are not published and do not contain exempt information)
OTHER HELPFUL PAPERS (papers which the report author considers might be helpful – this might include published material)
Lincolnshire Local Broadband Plan
Local Government (Access to Information Act) 1985
Is the report Exempt? – No
Please contact the person who has written this report Tel. No. 01507 601111
e-mail: [email protected], if you want more information about this report or the background papers. 1.0. INTRODUCTION
On 8th July 2011 Lincolnshire County Council submitted the Lincolnshire Broadband Delivery Plan to BDUK (Broadband Delivery UK), the government’s rural broadband delivery arm.
This submission secured an allocation of £14.3 million to implement Broadband roll out across the county with the objective of securing 90% coverage, with remaining properties having access to at least 2mbps connection.
The remaining funding would be met by a combination of public and private sector contributions including a requirement for Lincolnshire’s District/Borough/City Councils to meet a funding gap of (up to) £4 million.
Background
As below
3.0SUBJECT INFORMATION AND ISSUES/FACTS AND FIGURES
As outlined earlier, the submission of the Lincolnshire Broadband Delivery Plan to BDUK in 2011 was successful in securing a £14.3 million allocation to support the implementation of the scheme across the county.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
2026/27 Quarter 1 Finance Update1) That the General Fund forecast revenue outturn position for 2026/27 being an underspend of £56k as detailed in Tab...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.