That the role of Accountable Body, for the purposes of the Coastal Revival Fund, be adopted by East Lindsey District Council in regard to the successful bid for the Tower Gardens Pavilion made by the Skegness Partnership. The value of the grant award being £50,000.
Word for word from the decision East Lindsey published for this meeting.Source: democracy.e-lindsey.gov.uk
On 11th December 2015, the Government announced the successful applicants for the 2015/16 Coastal Revival Fund.
This included a successful bid from the Skegness Partnership to support investigative work for the vacant Tower Gardens Pavilion which is in the ownership of East Lindsey District Council.
The purpose of this Fund is to help kick-start the revival of at-risk coastal heritage sites that have potential to create opportunities for new businesses and jobs.
Whilst the bid was made by the Skegness Partnership, it is a condition of funding that the Local Authority acts as the Accountable Body. The purpose of this report is to confirm the Council’s willingness to act in this capacity.
Recommendations
1. Executive Board agrees that East Lindsey District Council adopts the role of Accountable Body, for the purposes of the Coastal Revival Fund, in regard to the successful bid for the Tower Gardens Pavilion made by the Skegness Partnership. The value of the grant award being £50,000.
REASON: To enable the grant to be accepted and for the Skegness Partnership to utilise the award for purposes for which it has been granted.
The attached report has been prepared by: Stuart Davy, Chief Executive e-mail: [email protected]
The attached report has been signed off by: n/a
The following policies form a context to this report: n/a LIST OF BACKGROUND PAPERS (papers relied on to write the report but which are not published and do not contain exempt information)
OTHER HELPFUL PAPERS (papers which the report author considers might be helpful – this might include published material)
Local Government (Access to Information Act) 1985
Is the report Exempt? – No
Please contact the person who has written this report Tel. No. 01507 601111
e-mail: [email protected], if you want more information about this report or the background papers.
1.0INTRODUCTION 1.1. On 11th December 2015 the Government announced the successful applicants for the Coastal Revival Fund. The national budget for this fund was some £3million of which £50,000 was allocated to fund investigative work at the Tower Gardens Pavilion, Skegness.
1.2Whilst only being confirmed on 11th December 2015, the budget must be utilised before the end of March 2016.
2.0BACKGROUND 2.1. The Tower Gardens Pavilion has been vacant for several years and is facing an uncertain future due to its ongoing deterioration in the absence of investment and external interest for development.
2.2The District Council has previously considered that in the absence of external interest in the building, and the likely cost of renovation, then the only option that would be available, albeit reluctantly, is demolition.
2.3This has raised concerns locally in Skegness where there has been a level of community support for its retention. A local community group has formed with the intention of saving the building, securing resources for its refurbishment and establishing a sustainable use. 2.4. In support of this aspiration, the Skegness Partnership submitted an application to the Government’s Coastal Revival Fund in 2015. Notification of the success of the bid was issued on 11th December 2015.
3.0SUBJECT INFORMATION AND ISSUES/FACTS AND FIGURES 3.1. On 11th December 2015, the Government announced the successful applicants for the 2015/16 Coastal Revival Fund.
3.2This included a successful bid from the Skegness Partnership to support investigative work for the vacant Tower Gardens Pavilion which is in the ownership of East Lindsey District Council.
3.3The purpose of this Fund is to help kick-start the revival of at-risk coastal heritage sites that have potential to create opportunities for new businesses and jobs.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
2026/27 Quarter 1 Finance Update1) That the General Fund forecast revenue outturn position for 2026/27 being an underspend of £56k as detailed in Tab...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.