CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
East Lindsey District Council
Executive Board, Wednesday 15 February 2017 at 6.00pm

Neighbourhood Services Depot Provision, Princes Parade, Skegness

Approved Executive 1 paper

Executive Board approved this item on Wednesday 15 February 2017. Below is the council's own wording, with the papers it was decided on.

Item70

Resolved

That the closure of the Princes Parade public toilets and their removal from the asset review of public toilets be approved; That the consolidation of depot provision for the Neighbourhood Service to Princes Parade as detailed in the report and for officers to progress contractor/works procurement be approved; That an amendment to the Capital Programme be recommended to Full Council by making an allocation from the Capital Reserve of £115,000 (One Hundred and Fifteen Thousand Pounds) for the enhancement works to the Princes Parade Depot, Skegness.
Word for word from the decision East Lindsey published for this meeting. Source: democracy.e-lindsey.gov.uk

Follow this further

Built from East Lindsey's papers

What the report saysPro

Report to Executive Board, 9 pages

Summary

This report considers the future depot provision for the Neighbourhood Services service in the Skegness area of the district.

Recommendations

That : 1. Executive Board approves the closure of the Princes Parade public toilets and their removal from the asset review of public toilets.

2. Executive Board approves the consolidation of depot provision for the Neighbourhood Service to Princes Parade as detailed in the report and for officers to progress contractor/works procurement.

3. Executive Board recommend to Full Council an amendment to the Capital Programme by making an allocation from the Capital Reserve of £115,000 (One Hundred and Fifteen Thousand Pounds) for the enhancement works to the Princes Parade Depot, skegness.

REASON: To allow a continuous and cost effective delivery of service.

This report has been prepared by:

Malcolm Abbott - Tel: 01507 613031 - e-mail: [email protected]

This report was prepared after consultation with:

Cont. Management Team Portfolio Holder for Operational Support Portfolio Holder for Coastal Economy

This report is number 1 in a series of 1.

This report has been signed off by:

Gary Sargeant

The following policies form a context to this report:

N/A

This report is not a key decision included in the Forward Plan.

LIST OF BACKGROUND PAPERS AS REQUIRED BY LAW (papers relied on to write the report which are published but do not contain exempt information)

1. N/a

OTHER HELPFUL PAPERS (papers which the report author considers might be helpful – this might include published material)

1. N/a

Local Government (Access to Information Act) 1985

Is the report Exempt – No

Please contact the person who has written this report, if you want more information about this report.

1.0INTRODUCTION

1.1As part of the Transformation Programme and continued development of Neighbourhood Services, officers have been tasked with reviewing the viability of working accommodation and providing an effective and economic way forward for the service. 2.0. BACKGROUND 2.1. Neighbourhood Services currently occupy two depot sites in Skegness. Princes Parade which is freehold and part occupation of Burgh Road which is leasehold.

Property and Technical Services shared the Burgh Road depot up until 2015 in delivering the summer illuminations. In 2015 the summer illuminations were contracted out and it is the responsibility of the contractor to source their own storage facility. As a result this part of the rented premises is surplus to requirements.

The tenancy of the Burgh Road depot is coming to an end in August 2017.

3.0SUBJECT INFORMATION AND ISSUES/FACTS AND FIGURES

3.1In moving out of Burgh Road there would be a yearly saving on rent and business rates. For the purpose of this report revenue costs are not included because these costs will still be needed at Princes Parade.

Moving out of Burgh Road will incur expenditure to fulfil requirements agreed with the owner under termination of the lease agreement. These are dilapidations as a result of the occupation of the premises over a number of years. The cost of these dilapidation works are estimated to be £5k and these can be contained within the current revenue repairs and maintenance budgets.

3.2Property and Technical Services have discussed the service requirements with Neighbourhood Services and identified works deemed essential to provide an effective continued delivery of the service out of Princes Parade. The cost of these works is estimated at £115,000, subject to competitive tender.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Neighbourhood Services Depot Provision, Princes Parade, Skegness:Report 9 pages DownloadRead as text

At this meeting

Whole meeting

More from East Lindsey Executive Board

All decisions
MeetingDecisionOutcome
23 Sep 2026 East Lindsey Investment Fund Update ReportThat the un-committed spend of ELIF 1 in para 2.3 and for ELIF 2 in para 2.5 be noted. 2. That the proposed activitie... Noted Open
23 Sep 2026 Acceptance of Ministry of Housing, Communities and Local Government (MHCLG) Playground Fund GrantThat the signed Memorandum of Understanding between East Lindsey District Council and MHCLG for the Playground Fund b... Noted Open
23 Sep 2026 Vehicle parking improvements to the Waste Depot, Fairfield Industrial Estate, LouthThat the addition of £500,000 to the 2026/27 Capital Programme to fund the improvements to vehicle parking provision ... Approved Open
23 Sep 2026 2026/27 Quarter 1 Finance Update1) That the General Fund forecast revenue outturn position for 2026/27 being an underspend of £56k as detailed in Tab... Noted Open
23 Sep 2026 Quarter 1 26/27 Performance and Risk ReportThat the performance and risk information contained within the report and appendices be noted. 2. That the risk appet... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies