RESOLVED That full planning permission be approved, subject to the following conditions: 1. The development must be begun not later than the expiration of three years beginning with the date of this permission. 2. The development hereby permitted shall be carried out in accordance with the following approved plans; Plan no: 002 Received by the LPA on the 09/01/2017. Plan no: 003 Received by the LPA on the 09/01/2017. 3. Before the commencement of the development hereby permitted a schedule of external materials of construction of buildings and hard surfaced areas shall be submitted to and approved in writing by the Local Planning Authority. Samples shall be provided as may be required by the Local Planning Authority of the materials in the schedule and the use of such samples shall be approved in writing by the Local Planning Authority. The development shall be constructed in accordance with the schedule and samples so approved. 4. Before the commencement of the development hereby granted, full details of the proposed means of foul and surface water disposal to separate systems shall be submitted to and approved in writing by the Local Planning Authority and the details so approved shall be implemented in full before there are any flows into the receiving systems 5. The development hereby approved must be undertaken in accordance with the recommendations set out in the protected species report submitted to the Local Planning Authority on the 14 th February 2016, unless otherwise agreed in writing by the Local Planning Authority. 6. The holiday accommodation hereby approved must be occupied for holiday purposes only and shall not be occupied as a person’s sole or main place of residence. The owners/operators of the site ... view the full minutes text for item 161.
Word for word from the decision East Lindsey published for this meeting.Source: democracy.e-lindsey.gov.uk
PROPOSAL: Planning Permission - Change of use, conversion of, extension and alterations to existing barn to provide 3no. holiday bedrooms each with en suites to serve the Three Horseshoes Inn. LOCATION: THREE HORSESHOES, SHOE LANE, GOULCEBY, LOUTH, LN11 9WA
1.0REASONS FOR COMMITTEE CONSIDERATION
1.1The application has been referred to the Planning Committee by the Planning Team Leader due to the high level of public interest.
2.0THE SITE AND SURROUNDINGS
2.1The site lies on the edge of the village of Goulceby. The village and the site are within the Wolds Area of Outstanding Natural Beauty. The site is comprised of the Three Horseshoes public house and two parcels of land to the rear. The public house is located to the front of the site, with access to the rear along the southern side.
2.2The members of the Committee considered an initial application at the January Committee meeting and approved it. A further application is currently being considered at the site – N/060/02449/16, which proposes to site 2 glamping pods and 2 arctic huts and to use the land for a mix of touring caravans and tents.
2.3There is a marquee permanently erected to the rear of the public house with an internal link into it from the public house. Beyond the marquee to the west lies a grassed area which will contain the manager’s accommodation and the amenity block. This is currently used for touring caravans.
2.4Further to the west beyond the first field lies the second field, which is the location for the approved touring caravan and camping pitches. This second field is separated from the first, and the public house, by a mature hedge row.
3.0DESCRIPTION OF THE PROPOSAL
3.1The proposal seeks permission to convert a brick and tile barn to the front of the site into holiday accommodation. The proposal involves an extension to the side of the building. The completed building would provide 3 bedrooms each with en-suite facilities. 4.0 CONSULTATION
4.1Set out below are the consultation responses that have been received on this application. These responses may be summarised and full copies are available for inspection separately. Some of the comments made may not constitute material planning considerations.
Publicity
4.2The application was advertised by way of a site notice, displayed at the entrance to the site. Where relevant, neighbouring properties sharing a common boundary were notified by letter.
Consultees
4.3ASTERBY AND GOULCEBY PARISH COUNCIL – No comments received.
4.4LINCOLNSHIRE COUNTY COUNCIL AS HIGHWAYS AUTHORITY AND LEAD LOCAL FLOOD AUTHORITY – Requests further information as to where parking will be provided.
4.5ENVIRONMENTAL SERVICES (Noise/Odour) - No comments to make.
4.6ENVIRONMENTAL SERVICES (Contamination) - No comments received.
4.7ENVIRONMENTAL SERVICES (Drainage) - No comments received.
4.8ENVIRONMENT AGENCY – Low environmental risk.
4.9LINCOLNSHIRE WOLDS COUNTRYSIDE SERVICE – No response received.
4.10NATURAL ENGLAND – No objection - NB. Natural England does not assess protected species surveys.
4.11WITHAM 3RD DRAINAGE BOARD – Details of soakaways required.
4.12LINDSEY MARSH DRAINAGE BOARD – No response received.
Neighbours
4.13Comments are summarised below. Full comments are available on the file.
4.14All addresses are in Goulceby unless otherwise stated.
Object
Addresses:
i) Cliff Lodge, Butt Lane; ii) Which Way, Ford Lane; iii) 1x no address given; iv) Holly House, Watery Lane; v) Ford Way; vi) 2x via email; vii) Viking Cottage, Church Lane.
Summary of reasons:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.