That the performance and governance information contained within the report be noted by Executive Board; That the three supplementary estimates referenced within Appendix A, Section 2.2 – Revenue Budget, be approved; That the use of the Technology Reserve to fund the iTrent payroll/HR system costs totalling £75k as referred in Appendix A be approved; That the procurement exemptions referenced within Appendix A, Section 2.8 be approved.
Word for word from the decision East Lindsey published for this meeting.Source: democracy.e-lindsey.gov.uk
1. That Executive Board considers any further action in respect of the performance and governance information contained within the report;
2. That Executive Board approves the three supplementary estimates referenced within Appendix A (Section 2.2, page 63).
3. That Executive Board approves the use of the Technology Reserve to fund the iTrent payroll/HR system costs totalling £75K (Appendix A, Section 2.2, page 63)
4. That Executive Board approves the procurement exemptions referenced within Appendix A (Section 2.8, page 70)
REASON: To achieve performance and governance objectives
This report has been prepared by: John Medler - Tel: 01507 613072 e-mail: [email protected]
This report was prepared after consultation with: Management Team
This report is number 3 in a series of 4.
This report has been signed off by: Management Team
The following policies form a context to this report:
This report is not a key decision included in the Forward Plan. LIST OF BACKGROUND PAPERS AS REQUIRED BY LAW (papers relied on to write the report which are published but do not contain exempt information) 1. None
OTHER HELPFUL PAPERS (papers which the report author considers might be helpful – this might include published material) 1. Corporate Strategy 2014 to 2018, East Lindsey District Council
Local Government (Access to Information Act) 1985 Is the report Exempt – No Please contact the person who has written this report or Andrew Wright Tel. No. 01507 613071 e-mail: [email protected], if you want more information about this report or the background papers.
1.0INTRODUCTION 1.1. The report attached as Appendix A brings together information relating to the Council’s Performance and Governance Framework.
1.2The underlying themes behind the report are effective performance and risk management, strong financial management, capturing and acting upon resident and customer feedback, sound governance and effective deployment and management of staff resources. The report includes a short Executive Summary containing the key headlines with further detailed information provided in the following sections:
Section 1 - Performance
1.3The report provides a summary of performance against the Council’s key performance indicators.
Section 2 – Finance
1.4This section includes key financial issues, developments and financial recommendations. Information and updates relating to the revenue and capital budgets, treasury management, insurance, debt collection, business rates and council tax collection are also provided.
Section 3 - Risk management and audit
1.5The report gives an overview of the audit and risk frameworks including the current version of the Council’s Strategic Risk Register. Section 4 - Customer engagement and feedback
1.6This section looks at the methods of engagement used by customers, volumes of formal complaints / compliments and requests made under the Freedom of Information Act 2000, Environmental Information Regulations 2004 and Data Protection Act 1998.
Section 5 – Workforce
1.7The report provides information from the annual staff survey and updates on delivery of the Council’s People Strategy 2016-18.
2.0BACKGROUND 2.1. N/A
3.0SUBJECT INFORMATION AND ISSUES/FACTS AND FIGURES 3.1. Detailed subject information, issues/facts and figures are included in Appendix A and Appendix B.
4.0SUPPLEMENTARY FACTS 4.1. N/A
5.0COUNCILLOR COMMENTS 5.1. None
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
2026/27 Quarter 1 Finance Update1) That the General Fund forecast revenue outturn position for 2026/27 being an underspend of £56k as detailed in Tab...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.