East Lindsey District Council
Executive Board, Tuesday 17 July 2018 at 6.00pm

Capital Programme Update

Approved Executive 1 paper

Executive Board approved this item on Tuesday 17 July 2018. Below is the council's own wording, with the papers it was decided on.

Item19

Resolved

That the changes recommended to the 2018/19 Capital Programme relating to Tedder Hall Plant Room, Skegness Embassy Theatre, Kingfisher Caravan Park and Electrical Vehicle Charging Points and the associated funding requirements be approved. That approval of the changes to the 2018/19 Capital Programme which are in excess of £300,000, relating to Skegness Town Hall and Disabled Facilities Grants be recommended to Council. This would result in a revised Capital Programme for 2018/19 of £28.602m being agreed.
Word for word from the decision East Lindsey published for this meeting. Source: democracy.e-lindsey.gov.uk

Follow this further

Built from East Lindsey's papers

What the report saysPro

Report to Executive Board, 9 pages

Summary

This report considers amendments to the 2018/19 Capital Programme. These changes have arisen for the following reasons: 1. Tedder Hall Plant Room Refurbishment, £106k increase in costs to be funded from Capital Reserve. 2. Skegness Embassy Theatre, £45k increase in costs to be funded from Service Transformation Reserve 3. Kingfisher Caravan Park Electrical Infrastructure Works, new scheme for £55k to be funded from Capital Reserve. 4. Skegness Town Hall Refurbishment, £1.653m to be removed from programme. 5. Disabled Facilities Grants, £362k increase funded from additional grant, of which £103k received in 2018/19 with £259k from previous years. 6. Electric Vehicle Charge Points, £110k with £100k funded from grants and £10k to be funded from Capital Reserve.

The inclusion of these schemes will reduce the 2018/19 programme to £28.602m.

Further details are provided below and at the Financial Appendix A.

Recommendations

Cont. 1. That Executive Board approves the changes recommended to the 2018/19 Capital Programme relating to Tedder Hall Plant Room, Skegness Embassy Theatre, Kingfisher Caravan Park and Electrical Vehicle Charging Points and the associated funding requirements.

2. That Executive Board recommends to Council to approve the changes to the 2018/19 Capital Programme which are in excess of £300,000, relating to Skegness Town Hall and Disabled Facilities Grants. This would result in a revised Capital Programme for 2018/19 of £28.602m being agreed.

REASON:

To enable capital projects to be progressed during 2018/19 in line with the Council’s Financial Procedure rules.

This report has been prepared by:

George Gustard, Assistant Business Partner, Compass Point Business Services - Tel: 01507 613256 - e-mail: [email removed]

This report was prepared after consultation with:

Robert Barlow Cllr R Fry

This report is number 1 in a series of 1.

This report has been signed off by:

Robert Barlow

The following policies form a context to this report:

Budget and Policy Framework Financial Procedure Rules

This report is not a key decision included in the Forward Plan. LIST OF BACKGROUND PAPERS AS REQUIRED BY LAW (papers relied on to write the report which are published but do not contain exempt information)

1. N/A

OTHER HELPFUL PAPERS (papers which the report author considers might be helpful – this might include published material)

1. N/A

Local Government (Access to Information Act) 1985

Is the report Exempt –No

Please contact the person who has written this report or Sally Topham Tel. No. 01507 613254 e-mail: [email removed] if you want more information about this report or the background papers.

1.0INTRODUCTION 1.1. The Council’s Financial Procedure Rules requires all changes to the Capital Programme up to £300,000 be approved by Executive Board. Above that level, all changes must be approved by full Council. Details are provided at section 2 and Appendix A.

2.0BACKGROUND 2.1. TEDDER HALL PLANT ROOM REFURBISHMENT – The existing Capital Programme contains an allocation of £42k within the Capitalised Enhancements budget for a boiler upgrade. This is a long standing provision which was included a number of years ago. There is now a requirement for a full refurbishment of the plant including pipework, valves, electrical distribution and control panels which were not previously incorporated into the historic budget provision. After a tender process and review it is requested that an additional £106k to complete the scheme. Without the works there are risks around Council operations and business continuity in the winter seasons ahead.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Programme Update:Report 9 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at East Lindsey

Search all
  1. Capital Programme UpdateThis decision
  2. Annual Budget Report 2026/27, Medium Term Financial Strategy, Capital Programme and Capital Strategy Treasury Management Policy/Strategy, and Annual Delivery PlanApproved
  3. Annual Budget Report 2025/26, Medium Term Financial Strategy, Capital Programme and Capital Strategy, Treasury Management Policy/Strategy and Annual Delivery PlanNoted
  4. Annual Budget Report 24/25 Medium Term Financial Strategy, Capital Programme and Capital Strategy, Treasury Management Strategy and Annual Delivery PlanApproved
  5. Annual Budget Report 2023/24, Medium Term Financial Strategy, Capital Programme and Capital Strategy, Treasury Management Strategy, Pay Policy Statement and Annual Delivery PlanApproved
  6. Capital Programme Update: IT InvestmentApproved

More from East Lindsey Executive Board

All decisions
MeetingDecisionOutcome
23 Sep 2026 East Lindsey Investment Fund Update ReportThat the un-committed spend of ELIF 1 in para 2.3 and for ELIF 2 in para 2.5 be noted. 2. That the proposed activitie... Noted Open
23 Sep 2026 Acceptance of Ministry of Housing, Communities and Local Government (MHCLG) Playground Fund GrantThat the signed Memorandum of Understanding between East Lindsey District Council and MHCLG for the Playground Fund b... Noted Open
23 Sep 2026 Vehicle parking improvements to the Waste Depot, Fairfield Industrial Estate, LouthThat the addition of £500,000 to the 2026/27 Capital Programme to fund the improvements to vehicle parking provision ... Approved Open
23 Sep 2026 2026/27 Quarter 1 Finance Update1) That the General Fund forecast revenue outturn position for 2026/27 being an underspend of £56k as detailed in Tab... Noted Open
23 Sep 2026 Quarter 1 26/27 Performance and Risk ReportThat the performance and risk information contained within the report and appendices be noted. 2. That the risk appet... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies