East Lindsey District Council
Executive Board, Wednesday 25 September 2019 at 6.00pm

Gibraltar Road, Mablethorpe - Partial Wall Collaspe

Decided Executive 2 papers

Executive Board decided this item on Wednesday 25 September 2019. Below is the council's own wording, with the papers it was decided on.

Item34

Resolved

1) That a programme of engineering works be developed and implemented by officers in conjunction with engineers from Lindum Construction Group at the above location using recommendations contained within the consulting engineers report, (Appendix B) that was commissioned following the partial wall collapse at the above location; 2) That the most appropriate and cost-effective engineering solution to matters that have presented at this location be sought by Officers; 3) That a spend of up to £200K to facilitate these works be supported by Executive Board; 4) That the costs associated with this project be drawn from the councils capital reserves.
Word for word from the decision East Lindsey published for this meeting. Source: democracy.e-lindsey.gov.uk

Follow this further

Built from East Lindsey's papers

What the report saysPro

Report to Executive Board, 8 pages

Summary

This report considers matters relating to the partial collapse of wall at Gibraltar Road, Mablethorpe and the remedial actions required to ensure ongoing structural stability of the sand dunes embankment and wall at this location with a recommendation in respect of maximum capital project costs.

Recommendations

That officers in conjunction with engineers from Lindum Construction Group develop and implement a program of engineering works at the above location using recommendations contained within the consulting engineers report (Appendix B) that was commissioned following the partial wall collapse at the above location.

Officers will seek to deliver the most appropriate and cost-effective engineering solution to matters that have presented at this location. It is recommended that members support a spend of up to £200K to facilitate these works.

The costs associated with this project are to be drawn from the councils capital reserves.

REASON: To ensure the structural integrity of the dunes embankment and retaining wall at the above location is preserved and to ensure that public asccess to the highway at the above location is maintained. This is particulary important at this location as the area of highway is immediately to the rear of the RNLI building at Mablethorpe and provides emergency parking for the RNLI lifeboat crew when being called out in emergency situations.

This report has been prepared by:

Cont. Duncan Hollingworth - Tel: 01507 613558 - e-mail: [email protected]

This report was prepared after consultation with:

The Environment Agency Lincolnshire County Council

This report is number 1 in a series of 1.

This report has been signed off by:

Neil Cucksey

This report is not a key decision included in the Forward Plan.

LIST OF BACKGROUND PAPERS AS REQUIRED BY LAW

1. None

OTHER HELPFUL PAPERS

1. Appendix B (AECOM Report dated 18th July 2019)

Local Government (Access to Information Act) 1985

Is the report Exempt. No

Please contact the person who has written this report or Neil Cucksey Tel. No. 613223 e-mail: [email protected] if you want more information about this report or the background papers.

1.0INTRODUCTION 1.1. This report informs members of the circumstances surrounding a partial wall collapse at Gibraltar Road Mablethorpe that occurred following heavy rain overnight on 10th June 2019 and seeks member approval to initiate and implement an engineering solution to address the issues that have been identified following a engineering survey of the wall at Gibralter Road, Mablethorpe

2.0BACKGROUND 2.1. Gibraltar Road is located on the south eastern side of Mablethorpe town centre and runs north-south alongside the sand embankment which forms a secondary part of the flood defences along this section of the coast to the elevated promenade some 20m to the seaward side. The embankment appears to be predominately made up of sea shore sand and has been present since the 1953 floods of the east coast according to historic maps.

2.2Currently a 10m section of wall has partially collapsed onto the road that is located towards the south eastern end of Gibraltar Road.

2.3The embankment is predominately made up of sand that is retained by a cement mortared non structural load bearing wall. Over time a number of differing species of trees, shrubs, flowers and grasses have established themselves on the surface of the embankment.

2.4This wall and sand dune is in the ownership of East Lindsey District Council and as such this council has an obligation to maintain and repair land and structures at this location.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
ELDC Maplethorpe Gibralter Rd Visual Inspection of Partial Failure of Retaining Wall 190925Appendix B 31 pages Download
PDF
Gibraltar Road, Mablethorpe: Partial Wall Collaspe:Report 8 pages DownloadRead as text

At this meeting

Whole meeting

More from East Lindsey Executive Board

All decisions
MeetingDecisionOutcome
23 Sep 2026 East Lindsey Investment Fund Update ReportThat the un-committed spend of ELIF 1 in para 2.3 and for ELIF 2 in para 2.5 be noted. 2. That the proposed activitie... Noted Open
23 Sep 2026 Acceptance of Ministry of Housing, Communities and Local Government (MHCLG) Playground Fund GrantThat the signed Memorandum of Understanding between East Lindsey District Council and MHCLG for the Playground Fund b... Noted Open
23 Sep 2026 Vehicle parking improvements to the Waste Depot, Fairfield Industrial Estate, LouthThat the addition of £500,000 to the 2026/27 Capital Programme to fund the improvements to vehicle parking provision ... Approved Open
23 Sep 2026 2026/27 Quarter 1 Finance Update1) That the General Fund forecast revenue outturn position for 2026/27 being an underspend of £56k as detailed in Tab... Noted Open
23 Sep 2026 Quarter 1 26/27 Performance and Risk ReportThat the performance and risk information contained within the report and appendices be noted. 2. That the risk appet... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies