Resolved
That the transfer of the internal audit function to Lincolnshire County Council be approved by Executive Board.
Executive Board approved this item on Wednesday 13 November 2019. Below is the council's own wording, with the papers it was decided on.
Resolved
That the transfer of the internal audit function to Lincolnshire County Council be approved by Executive Board.
The Council’s Internal Audit service has been provided ‘in-house’ since 2013. The requirement for an Internal Audit service is set within the Accounts and Audit Regulations 2015 which states that:
‘A relevant authority must undertake an effective internal audit to evaluate the effectiveness of its risk management, control and governance processes, taking into account public sector internal auditing standards or guidance’
Current Internal Audit capacity
Internal Audit forms part of the wider Internal Audit and Information Governance service which is incorporated into the Corporate Governance service area. The resource within the service is:
Internal Audit and Information Governance Service Manager (50% of role) (0.8 FTE) Principal Auditor 1 FTE Senior Auditor 06. FTE
The Internal Audit plan currently comprises 200 audit days plus 25 days Housing Subsidy testing undertaken on behalf of External Audit.
Reason for Review
Internal Audit is specialist service and requires appropriately skilled and qualified staff in order to maintain conformity with the professional standards. Resilience presents a significant risk to the service, it has become increasingly difficult to recruit skilled auditors and the loss of any member of the team would significantly impact the ability to deliver the function. Previously resource shortages have been filled with the use of agency staff, however this has been with mixed results and isn’t a cost effective method of acquiring resource. Concerns around resilience have also been raised repeatedly by Audit and Governance Committee Members.
East Lindsey has acted as a partner in the Assurance Lincolnshire Collaborative Partnership since 2009, the partnership consists of ELDC, City of Lincoln Council, Nottingham County Council and Lincolnshire County Council (LCC) acting as the lead partner. The partnership has been highly successful over the period and has produced a large number of examples of successful joint working. The partnership provides Assurance services to most of the Councils in Lincolnshire, in addition to a number outside the County, Academies and Lincoln University.
Due to the ongoing difficulties around resilience highlighted above in addition to a lack of specific fraud and ICT audit expertise at East Lindsey we are proposing transferring the Internal Audit service to Lincolnshire County Council. The Council will continue to benefit from the Assurance Lincolnshire Partnership, but as part of a much larger and more diverse team, resilience risks will be greatly reduced. The proposal is for a contract for the provision of audit services for a period of five years with an option to terminate on either side giving a notice period of twelve months. It is not currently proposed to make any changes to the level of audit days however as the risk environment changes these considerations may be taken at a later date. Appendix A
Costs and Impact
Current and proposed costs are as follows:
Current costs and income (based on 2019/20 budget)
Expenditure £124,333
Income £ 25,975 (SHDC & MV)
Net Current Cost £ 98,358
Proposed Cost £ 66,375 (225 days @ £295 per day)
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Business Case: IA v3Report | 2 pages | DownloadRead as text |
PDF |
Future Delivery Model of the Internal Audit Function:Report | 5 pages | Download |
Follow Executive Board at East Lindsey and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 23 Sep 2026 | East Lindsey Investment Fund Update ReportThat the un-committed spend of ELIF 1 in para 2.3 and for ELIF 2 in para 2.5 be noted. 2. That the proposed activitie... | Noted | Open |
| 23 Sep 2026 | Acceptance of Ministry of Housing, Communities and Local Government (MHCLG) Playground Fund GrantThat the signed Memorandum of Understanding between East Lindsey District Council and MHCLG for the Playground Fund b... | Noted | Open |
| 23 Sep 2026 | Vehicle parking improvements to the Waste Depot, Fairfield Industrial Estate, LouthThat the addition of £500,000 to the 2026/27 Capital Programme to fund the improvements to vehicle parking provision ... | Approved | Open |
| 23 Sep 2026 | 2026/27 Quarter 1 Finance Update1) That the General Fund forecast revenue outturn position for 2026/27 being an underspend of £56k as detailed in Tab... | Noted | Open |
| 23 Sep 2026 | Quarter 1 26/27 Performance and Risk ReportThat the performance and risk information contained within the report and appendices be noted. 2. That the risk appet... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.