That the budget setting report and associated financial strategies 2020/21 to 2024/25, this includes the Minimum Revenue Provision (MRP) Policy be recommended to Council for approval; 2. That the Council Tax for a Band D property in 2020/21 is set at £146.79 be recommended to Council for approval; 3. That the creation of an Investments Volatility Reserve and the authorisation of the transfer of £1m (previously set aside for this purpose) with immediate effect from the Council’s General Fund reserve to this reserve be recommended to Council for approval.
Word for word from the decision East Lindsey published for this meeting.Source: democracy.e-lindsey.gov.uk
Attached to this report is the detail of the 2020/21 budget, the 5 year Medium Term Financial Strategy (MTFS) from 2020/21 to 2024/25 and various other associated financial strategies. The report also includes the recommended level of Council Tax for 2020/21.
The draft budget, MTFS and associated strategies were considered by the Audit and Governance committee. The draft budget documents have also been through a consultation process.
Executive Board are asked to consider the attached budget and strategies, to consider feedback and comments from the consultation process and to make their recommendations to Council.
RECOMMENDATION 1. That Council approves the budget setting report and associated financial strategies 2020/21 to 2024/25, this includes the Minimum Revenue Provision (MRP) Policy;
2. That Council approves that the Council Tax for a Band D property in 2020/21 is set at £146.79;
3. That Council approves the creation of an Investments Volatility Reserve and authorises the transfer of £1m (previously set aside for this purpose) with immediate effect from the Council’s General Fund reserve to this reserve.
REASON:
To comply with the budgetary and policy framework.
1. BACKGROUND TO REPORT
1.1The attached Budget Report and Financial Policies set out the Council’s Revenue and Capital Budgets for 2020/21, the MTFS to 2024/25 and associated financial strategies
1.2The preparation of the budget for 2020/21 has been a detailed process involving officer working groups, Management Team, member meetings, Overview Committee, Audit and Governance, Executive Board and public consultation.
1.3When the Council originally made the decision to widen its investment portfolio, £1m was put aside into the Council’s general fund to cover any fluctuations in the fair value of the assets invested in and to negate any impact on the Council’s revenue account. It is now proposed to move this amount into a specific earmarked reserve which is solely for this purpose
1.4The attached report and appendices detail the following:
The Government’s finance settlement for 2020/21 and the estimated government funding over the MTFS period. The estimated total resources and expenditure over the MTFS period. The budget assumptions that have been used in developing the 2020/21 budget and Medium Term Financial Strategy. The estimated budget pressures that the Council must address over the medium term. The anticipated position with the Council’s reserves over the medium term. The anticipated savings targets for future years and the ongoing delivery of these savings via organisational development plans. Risks associated with the budget and medium term financial strategy. The proposed capital programme and Capital Strategy. The proposed Treasury Management Strategy. 1.5 Executive Board are asked to consider the Consultation responses (Appendix 8 to the budget to follow once the consultation has closed), review the budget proposals and to make its recommendations to Council on 4 March 2020
2. OTHER OPTIONS CONSIDERED
2.1No alternative budget proposals are presented. Executive Board are asked to make any amendments to the budget proposals before recommendation to Council
3. RESOURCE IMPLICATIONS
3.1These are contained in appendix 1.
4. RISK AND MITIGATION
Contained in section 8 of appendix 1.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
2026/27 Quarter 1 Finance Update1) That the General Fund forecast revenue outturn position for 2026/27 being an underspend of £56k as detailed in Tab...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.