East Lindsey District Council
Executive Board, Wednesday 22 September 2021 at 6.15pm

3G Football Pitch Project

Agreed Executive 2 papers

Executive Board agreed this item on Wednesday 22 September 2021. Below is the council's own wording, with the papers it was decided on.

Item39

Resolved

That agreement be given for the Wood Lane facility in Louth as the preferred site to progress the 3G pitch project; 2. That the 3G pitch project’s current funding position be noted; 3. That the merits of adding the refurbishment of the Wood Lane Multi-Use Games Area into the 3G project in Louth be supported, subject to the necessary external funding being identified.
Word for word from the decision East Lindsey published for this meeting. Source: democracy.e-lindsey.gov.uk

Follow this further

Built from East Lindsey's papers

What the report saysPro

Report to Executive Board, 5 pages

REPORT TO: EXECUTIVE BOARD

DATE: 22 SEPTEMBER 2021

SUBJECT: 3G FOOTBALL PITCH PROJECT

KEY DECISION: NO PORTFOLIO HOLDER: PORTFOLIO HOLDER FOR PARTNERSHIPS, COUNCILLOR GRAHAM MARSH

REPORT AUTHOR: ASSISTANT DIRECTOR – SUPPORT SERVICES AND PARTNERSHIPS, PHIL PERRY LOUTH WARD(S) AFFECTED:

EXEMPT REPORT? NO

SUMMARY A report previously went before the 17 February 2021 Executive Board, where it was agreed to provide capital funding of £170k as a contribution towards new 3G football facilities in Louth, subject to obtaining the necessary external funding. This report details the progress of the 3G football pitch project and the potential for the refurbishment of the existing Five-a-Side pitch on the Wood Lane site to become a Multi-Use Games Area.

RECOMMENDATIONS 1. That Executive Board agrees the Wood Lane facility in Louth as the preferred site to progress the 3G pitch project. 2. That Executive Board notes the 3G pitch project’s current funding position. 3. That Executive Board considers the merits of adding the refurbishment of the Wood Lane Multi-Use Games Area into the 3G project in Louth, subject to the necessary external funding being identified.

REASONS FOR RECOMMENDATIONS To further improve the leisure, health and wellbeing offer in East Lindsey, in line with the Council’s Corporate Strategy.

OTHER OPTIONS CONSIDERED 3G pitch To seek an alternative location in Louth to that proposed for the 3G Pitch. This isn’t recommended as the site identified is considered the most suitable due to proximity to existing leisure provision. Refurbishment of Multi Use Games Area To not explore the further refurbishment of this facility. This isn’t recommended as it could be an opportunity, subject to external funding, to dovetail two projects and achieve greater value for money.

REPORT 1.0 3G FOOTBALL PITCH PROJECT POSITION - LOUTH

1.1In the previous report concerning a 3G pitch option that went to the Executive Board on 17 February 2021, it was reported that the project to construct would be developed with an estimated cost in the region of £825k and that there is an opportunity to secure Football Foundation funding at 70%-75% (£577k to £625k). This remains the position at this time and the Football Foundation are starting a desktop and site survey on the Wood Lane site to determine a more accurate site-specific estimate of cost for the project.

1.2Whilst a number of sites in Louth were explored for the 3G pitch, including London Road and Louth Academy, Wood Lane was determined to be the most appropriate location for a number of reasons. A plan of the site, with an outline of a 3G pitch added, is attached for reference (Appendix 1). The reasons for choosing Wood Lane include the dedicated changing facilities adjacent to where the pitch would be located; the site is fully accessible and can be available to the community 7 days a week; the benefit of the Meridian Leisure Centre facilities and professional onsite staffing to support the ongoing management and maintenance; there is security and infrastructure already in place, as well as car parking provision that meets the standard required to be accessible for all users. 1.3 Representatives from the Council and Magna Vitae (MV) met with representatives from the Lincolnshire FA and the Football Foundation most recently on 11 August to scope out the project and discuss any implications concerning the site, a prospective planning permission and its current usage. Council Officers and MV have agreed to provide historic documentation to inform assessments being undertaken by the Football Foundation.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
3G Football Pitch Project:Report 5 pages DownloadRead as text
PDF
Appendix 1Appendix 1 1 pages Download

More from East Lindsey Executive Board

All decisions
MeetingDecisionOutcome
23 Sep 2026 East Lindsey Investment Fund Update ReportThat the un-committed spend of ELIF 1 in para 2.3 and for ELIF 2 in para 2.5 be noted. 2. That the proposed activitie... Noted Open
23 Sep 2026 Acceptance of Ministry of Housing, Communities and Local Government (MHCLG) Playground Fund GrantThat the signed Memorandum of Understanding between East Lindsey District Council and MHCLG for the Playground Fund b... Noted Open
23 Sep 2026 Vehicle parking improvements to the Waste Depot, Fairfield Industrial Estate, LouthThat the addition of £500,000 to the 2026/27 Capital Programme to fund the improvements to vehicle parking provision ... Approved Open
23 Sep 2026 2026/27 Quarter 1 Finance Update1) That the General Fund forecast revenue outturn position for 2026/27 being an underspend of £56k as detailed in Tab... Noted Open
23 Sep 2026 Quarter 1 26/27 Performance and Risk ReportThat the performance and risk information contained within the report and appendices be noted. 2. That the risk appet... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies