Pride in Place Programme (Skegness)

Approved Executive 3 papers

AI summaryEast Lindsey Executive Board approves submission of Skegness ten-year Regeneration Plan and four-year investment profile worth up to £20m of Pride in Place grant funding to UK Government by 28 November 2025.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedTen-year vision and four-year plan to be sent to UK Government
MoneyUp to £20 million over ten yearsGrant from UK Government's Pride in Place Programme
What happens nextSubmit to UK Government by 28 November 2025Via online Delta portal by midday
Who it affectsSkegness residents, businesses and visitorsTown centre, public realm, skills, culture and safety

What was decided

The Executive Board approved submission of the ten-year Regeneration Plan and Vision for Skegness, attached at Appendix 2 of the report. [D]

The Board approved the proposed four-year investment plan profile for Skegness set out in Sections 3 and 4 of the report. [D]

Authority was delegated to the Director of Economic Development, in consultation with the Chair of the Skegness Neighbourhood Board, Section 151 Officer and Coastal Economy Portfolio Holder, to agree further amendments during submission and assessment with UK Government. [D]

Why

Skegness has been allocated up to £20 million of new grant funding over a ten-year period from April 2026 as one of 75 towns in Phase One of the Pride in Place Programme. [1.1] Report 1.1

All activities must support at least one of three core objectives: creating thriving places, building stronger communities, and helping communities take back control. [1.2] Report 1.2

Over 1,100 community responses gathered through surveys, workshops and events have shaped priorities around year-round Skegness, business, connectivity, leisure and culture, and natural environment. [2.6] Report 2.6

What happens next

The Plan and investment profile must be submitted via the Delta portal by midday on 28 November 2025. [5.2] Report 5.2

Once the funding offer is confirmed, a future report will be brought to the Executive Board to consider the terms of the Memorandum of Understanding, accept the funding into the Council's budget and agree delegation. [5.3] Report 5.3

The Investment Plan is a live document and is likely to be updated annually, with progress reported regularly to the Executive Board. [3.5] Report 3.5

The money

  • up to £20million Pride in Place grant funding over ten years from April 2026 for Skegness Report 1.1
  • £5,306,000 Total capital grant allocation across years 1 to 4 Report P25
  • £1,432,000 Total revenue grant allocation across years 1 to 4 Report P25
  • £2,000,000 Total capital for Business workspace or incubator feasibility, site options and business case Report P25
  • £1,306,250 Total capital for detailed design and delivery of interventions at Bus Station, Arrival and High Street market area Report P25
  • £750,000 Total capital for improvements to existing green and open spaces Report P25
  • £640,000 Total revenue for Town Centre Rangers and ASB and crime reporting Report P25
  • £650,000 Total revenue for Cultural Capacity Fund, events and outreach Report P25
  • £240,000 Shared permanent staffing: 0.5 FTE Programme Manager and 0.5 FTE Programme Officer contribution with Mablethorpe Report P25
  • £370,00 Indicative future uncommitted revenue capacity fund balance (excluding the £80,000 already committed for street cleaning operatives) Report 4.5

Options considered

  • Chosen: Approve submission of the ten-year Regeneration Plan, four-year investment plan and delegate authority for submission and amendments. Required to release the allocated Pride in Place funding and meet the UK Government deadline of 28 November 2025 Report P1, 5.2
  • Rejected: Do not participate in the Pride in Place Programme for Skegness Report P3
  • Rejected: Seek an alternative accountable body structure to deliver the funding programme Report P3

Implications

  • Legal: The Council acts as the accountable body and must comply with the Nolan Principles, Managing Public Money, the Subsidy Control Act 2022, and public contract regulations. [2.3, P35, P36, P37, P38] Report 2.3, P35, P36, P37, P38
  • Financial: 75% of funding across the delivery period must be spent on capital projects and funding cannot replace existing expenditure on core or statutory Council functions. [4.3, 4.5] Report 4.3, 4.5
  • Financial: Annual grant allocations and the capital and revenue split are fixed, with no inflation adjustments, and unspent funds can be rolled forward only within the programme. [4.2, 4.1] Report 4.1
  • Staffing: Additional project management resource is secured; capacity implications of regeneration plan actions will need ongoing monitoring. [P33, P34] Report P33, P34
  • Risk: Key risks include capacity to deliver, inclusive engagement, partnership working, deliverability of the plan, and accountability compliance. [P40] Report P40
  • Other: The programme is expected to enhance the Council's reputation through joint working with local stakeholders via the Neighbourhood Board. [P42] Report P42
  • Other: The Council is not asked to allocate additional funding to support the programme management or delivery functions. [4.4] Report 4.4

Who and where

  • Residents, businesses and visitors of Skegness Report 1.3, 2.6
  • Skegness Neighbourhood Board, which decides how and where the funding is spent in partnership with East Lindsey District Council Report 1.3
  • East Lindsey District Council service areas including finance, communications, legal and economic development Report 4.4
  • South and East Lincolnshire Councils Partnership, cumulatively due to receive up to £80m of new investment across four towns Report P31

Timeline

  • 8th July 2025: Executive Board approved the Plan for Neighbourhoods Capacity Fund report Report 1.4, P52
  • 25th September 2025: UK Government published the wider Pride in Place Strategy Report 1.1
  • 30th October 2025: All Member Briefing provided to East Lindsey District Council Members Report 1.4
  • 28th November 2025 by midday: Deadline for submission of Regeneration Plan and investment profile via Delta portal Report P1, 5.2
  • March 2026: UK Government assessment process expected to complete, prior to which further queries may be addressed by the Director of Economic Development Report 5.4
  • April 2026: Pride in Place Phase One delivery commences for Skegness Report 1.1
  • 2026/27 to 2029/30: First four-year investment period for the programme
  • April 2027: Phase Two of the Programme commences delivery, with Mablethorpe receiving the same level of funding Report 1.1

Plain English for the jargon

  • Pride in Place Programme: UK Government programme (formerly Plan for Neighbourhoods) allocating new grant funding to towns for regeneration, with three core objectives around thriving places, stronger communities and local control. [1.1, 1.2]
  • Skegness Neighbourhood Board: Local decision-making body that decides how and where the new funding is spent, working in partnership with East Lindsey District Council. [1.3]
  • MHCLG: Ministry of Homes, Communities and Local Government. [P48]
  • Accountable body: The Council, responsible for overall delivery, fair and effective distribution of public funds, and compliance with Nolan Principles, Managing Public Money, Subsidy Control Act 2022 and procurement rules. [2.3, P35]
  • Nolan Principles: The seven principles of public life that govern the conduct of those holding public office. [2.3, P35]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item133

Resolved

That the submission of the ten-year Regeneration Plan and Vision for Skegness, attached at Appendix 2 of the report referred be approved. 2. That the proposed four year investment plan profile for Skegness as set out at Sections 3 and 4 in the report be approved. 3. That authority be delegated to the Director of Economic Development, in consultation with the Chair of the Skegness Neighbourhood Board, Section 151 Officer and Coastal Economy Portfolio Holder to agree any further amendments to the final draft Regeneration Plan and Investment Profile during the submission and assessment phase with UK Government. 4. That authority be delegated to the Council’s Section 151 Officer to approve the submission of the Pride in Place Programme information for Skegness to UK Government by the 28th November.
Word for word from the decision East Lindsey published for this meeting. Source: democracy.e-lindsey.gov.uk

Follow this further

Built from East Lindsey's papers

What the report saysPro

Report to Executive Board, 14 pages

Reasons for recommendations

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Pride in Place Skegness Submission: 251125 FINAL EBB COPY FOR ISSUE.docx 21.11.25Report 14 pages DownloadRead as text
PDF
Skegness PfN Regeneration Plan 211125 FINAL.docx 21.11.25Report 33 pages Download
PDF
SkegnessconsultationandengagementFINALREPORTReport 77 pages Download

At this meeting

Whole meeting
132Local Government Re-organisation - proposal to GovernmentApproved
133Pride in Place Programme (Skegness)This decision

Who was there

6 of 31 attended
CL
Councillor Craig LeylandChairman, present
GM
Councillor Graham MarshDeputy, present
TA
Councillor Tom AshtonCommittee Member, apologies
SD
Councillor Sarah DevereuxCommittee Member, present
MF
Councillor Martin FosterCommittee Member, apologies
WG
Councillor William GrayCommittee Member, present
AG
Councillor Adam GristCommittee Member, apologies
TK
Councillor Thomas KempCommittee Member, present
SK
Councillor Steve KirkCommittee Member, present
RB
Robert BarlowOfficer, in attendance
PP
Pranali ParikhOfficer, in attendance
JG
James GilbertOfficer, in attendance

All 31 on the meeting page

On this subject at East Lindsey

Search all
  1. Pride in Place Programme (Skegness)This decision
  2. Pride in Place Programme DeliveryApproved

More from East Lindsey Executive Board

All decisions
MeetingDecisionOutcome
23 Sep 2026 East Lindsey Investment Fund Update ReportThat the un-committed spend of ELIF 1 in para 2.3 and for ELIF 2 in para 2.5 be noted. 2. That the proposed activitie... Noted Open
23 Sep 2026 Acceptance of Ministry of Housing, Communities and Local Government (MHCLG) Playground Fund GrantThat the signed Memorandum of Understanding between East Lindsey District Council and MHCLG for the Playground Fund b... Noted Open
23 Sep 2026 Vehicle parking improvements to the Waste Depot, Fairfield Industrial Estate, LouthThat the addition of £500,000 to the 2026/27 Capital Programme to fund the improvements to vehicle parking provision ... Approved Open
23 Sep 2026 2026/27 Quarter 1 Finance Update1) That the General Fund forecast revenue outturn position for 2026/27 being an underspend of £56k as detailed in Tab... Noted Open
23 Sep 2026 Quarter 1 26/27 Performance and Risk ReportThat the performance and risk information contained within the report and appendices be noted. 2. That the risk appet... Noted Open