03255/25/RVC

Approved Planning 2 papers

AI summaryEast Lindsey approves changes to Mablethorpe Campus Health Hub, cutting short-stay units from 7 to 3 and adding health and community uses, subject to conditions.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedSection 73 variation of condition application granted
MoneyNot stated
What happens nextDevelopment must begin by 1 February 2026As set out in condition 1
Who it affectsNot stated

What was decided

Planning permission was granted subject to 13 conditions covering timescales, approved plans, operating hours, landscaping, flood risk, drainage, parking, ecology, and use of living accommodation. Report P52, P78

The number of short-stay living units in the accommodation block is reduced from 7 to 3, with the remaining space used for health, wellbeing, care, training and community services linked to the main building. Report 7.3, P57, P59

The remaining living accommodation is restricted to short-stay use by staff, students or conference attendees at the main faculty building, with no sole or main residence and a 6-month occupation cap. Report P74, P75

Why

The original 2022 permission for the Campus for Future Living has evolved into a health and wellbeing operation run by ACIS Group, which no longer needs 7 short-stay units but needs more space for community services. Report 7.2, 7.3, 8.1

Policy SP1, SP14 and SP17 in the East Lindsey Local Plan support community buildings and year-round employment in the coastal zone, and the officer found the variation complies with these policies. Report 7.4, P20

Fewer residents on site and no external changes reduce flood risk and visual impact; consultees including the Environment Agency, Lincolnshire Police and Lincolnshire County Council Highways raised no objections. Report 4.6, 4.7, 7.8, 7.10, 7.11

What happens next

Construction must begin no later than 1 February 2026 and the development must follow the approved plans listed in condition 2. Report P53, P54, P55

Non-living accommodation may operate only between 08:30 and 18:00 on weekdays, with limited weekend use for conferences and workshops. Report P57

An up-to-date register of occupiers of the living units and their main home addresses must be kept and made available to the council on request. Report P74

Options considered

  • Chosen: Approve the s73 variation as recommended. Changes reflect the evolved business model, remain policy compliant and reduce flood risk exposure by reducing residents on site. Report 8.1, 8.2, 9.0
  • Rejected: Refuse the application. No reason given in the papers; the officer assessment found the impacts acceptable. Report 7.0, 8.0

Implications

  • Legal: The approval is issued under section 73 of the Town and Country Planning Act and creates a new planning permission; original conditions are re-imposed with amendments. Report 7.15, 8.4
  • Risk: Flood safety is addressed by re-imposing the original Flood Risk Assessment condition, keeping sleeping accommodation upstairs, and capping occupation. Report 4.6, P62, P63, P74
  • Equalities: Mablethorpe Town Council objected on grounds of loss of short-term accommodation, but the officer found the loss justified by the change in operational need and conditioned to minimise conflict. Report 4.4, 7.6, P42
  • Climate: Water use is limited to 110 litres per person per day under Building Regulation Part G(2)(b) because the district is in a water scarce area. Report P76, P77
  • Other: Biodiversity Net Gain requirements do not apply because the original permission was granted before 12 February 2024. Report 7.15

Who and where

  • ACIS Group Ltd, the applicant and operator of the Campus Health Hub Report 7.3
  • Residents of Mablethorpe and Sutton, via the Town Council which objected Report 4.4
  • Users of health, wellbeing, training and community services at the site Report 7.3, P59
  • Short-stay visitors such as staff, students and conference attendees at the faculty building Report P74

Timeline

  • 27 May 2022: EIA screening opinion issued for the Campus for Future Living (N/110/00935/22). Report 5.1
  • 2 September 2022: Full planning permission granted for the Campus for Future Living (N/110/00914/22). Report 5.2
  • 24 November 2022: Conditions 3 and 5 on remediation and construction method statement discharged. Report 5.3
  • 29 January 2024: Conditions 7 and 9 on landscaping and boundary treatments discharged. Report 5.4
  • 23 September 2025: Condition 4 validation report discharged. Report 5.5
  • 1 February 2026: Latest date by which the development must begin under condition 1. Report P53

Plain English for the jargon

  • s73 variation: An application under section 73 of the Town and Country Planning Act 1990 to vary or remove conditions on an existing planning permission, which issues a new permission.
  • Towns Fund: UK government funding for towns to support economic regeneration, used here for the original Campus for Future Living project.
  • BNG: Biodiversity Net Gain, a requirement for development to leave biodiversity in a better state than before; not applicable to permissions granted before 12 February 2024.
  • Sequential and exception tests: Tests set out in planning policy for developments in areas at risk of flooding, requiring applicants to show no suitable lower risk sites are available and that the development provides wider sustainability benefits.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item80

Resolved

That the application be approved subject to the following conditions:
Word for word from the decision East Lindsey published for this meeting. Source: democracy.e-lindsey.gov.uk

Follow this further

Built from East Lindsey's papers

What the report saysPro

Report to Planning Committee

[05]

03255/25/RVC APPLICANT: ACIS Group Ltd

VALID: 07.10.2025 AGENT: [name removed], Oakley Estates

PROPOSAL: Section 73 application to carry out development without complying in full with condition 13 (living accommodation) as previously imposed on planning permission ref. no. N/110/00914/22 (erection of a faculty building housing laboratories, consultation spaces, lecture facilities and ancillary facilities including public facing cafe, 7 bedroom accommodation block for short term stay for researchers and associated public open space with play area, parking for 36 vehicles, mobility scooter parking/charging and new entrance road connecting to the existing roundabout).

LOCATION: Land off Stanley Avenue, Mablethorpe.

1.0REASONS FOR COMMITTEE CONSIDERATION

1.1The application site is owned by East Lindsey District Council and this application is submitted for committee consideration on the grounds of transparency.

2.0THE SITE AND SURROUNDINGS

2.1The application site lies at the southern end of the cul-de-sac that is Stanley Avenue in the town of Mablethorpe. The site measures about 1.57 hectares. The land is flat with roadside grassed bunds. The site has recently been developed for the Campus for Future Living which consists of a main two-storey building of modern design at the southern end of the site with a smaller two-storey building to the north designed to provide short-term living accommodation for those employed in connection with the use of the main building. The site is landscaped with areas of car parking and a buggy/cycle shelter and it is served from the existing roundabout on Stanley Avenue. The application site also includes an area of meadow with an attenuation pond to its south-west.

2.2To the south of the site is the Marisco Medical Centre with car park and a caravan park, to the west is residential development off Phoenix Court with a public footpath in between which runs on the top of a drainage board culvert. To the east is the library and children’s centre and to the north is a community centre beyond another leg of the public footpath.

2.3Stanley Avenue is a two-lane road which is street lit with pavements either side of the carriageway. It features traffic calming measures with kerbside parking restrictions in force for the length of the road. Stanley Avenue ends at a roundabout at its southern end and connects to the A1104 at its northern end. The A1104 connects Mablethorpe with Alford.

2.4The application site lies within Flood Zone 3 and the Coastal Zone. 3.0 DESCRIPTION OF THE PROPOSAL

3.1The Campus for Future Living was granted planning permission in 2022. It has been built and the main building is occupied by ACIS. As set out above the development relates to two separate buildings. The first is the main building where most of the medical, health and well-being activities were approved to occur, and the second building was to provide 7 units of living accommodation in connection with people employed in those activities. The living accommodation was conditioned as set out in condition 13 which reads as follows:

“The accommodation block hereby approved shall be used for short-term living accommodation only and only by those employed by, carrying out research for, or a student at the main faculty building on site and no one person shall live in the building for any longer than 6 months at a time. In addition, the accommodation shall not be occupied as a person's sole or main place of residence. The owners/operators of the site shall maintain an up-to-date register of the names of all occupiers of the accommodation on site, and of their main home addresses, and shall make this information available to the Local Planning Authority upon request.”

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
03255 25 RVC 260108Report 158 KB DownloadRead as text
PDF
03255/25/RVC:Report 340 KB Download

At this meeting

Whole meeting

Who was there

10 of 22 attended
SE
Councillor Stephen EyreChairman, present
AH
Councillor Alex HallVice-Chairman, present
TA
Councillor Terry AldridgeCommittee Member, present
RC
Councillor Richard CunningtonCommittee Member, apologies
DE
Councillor Dick EdgintonCommittee Member, apologies
DH
Councillor David HallCommittee Member, present
NJ
Councillor Neil JonesCommittee Member, present
SK
Councillor Samuel KempCommittee Member, present
TK
Councillor Terry Knowles (Independent)Committee Member, apologies
SM
Councillor Steve McMillanCommittee Member, present
DM
Councillor Daniel McNallyCommittee Member, apologies
KM
Councillor Kate MarnochCommittee Member, present

All 22 on the meeting page

On this subject at East Lindsey

Search all
  1. 03255/25/RVCThis decision
  2. 02166/25/rvcApproved

More from East Lindsey Planning Committee

All decisions
MeetingDecisionOutcome
2 Sep 2026 Tree Preservation Order: 137, Eastgate, Louth (105.36)That 137 Eastgate, Louth (105.36) Tree Preservation Order be confirmed (made permanent). Decided Open
2 Sep 2026 Tree Preservation Order: Land adjacent 116C Horncastle Road, Roughton Moor (215.31)That land adjacent to 116C Horncastle Road, Roughton Moor (215.31) Tree Preservation Order be confirmed (made permane... Decided Open
2 Sep 2026 00489/26/fulThat the application be approved. Approved Open
2 Jul 2026 03860/25/fulThat this Council resolve to grant planning permission with the application being referred to the Secretary of State ... Decided Open
20 May 2026 Election of ChairmanThat Councillor Stephen Eyre be elected Chairman of the Planning Committee for the Council year 2026/27. Decided Open