Supporting East Lindsey businesses with energy decisions and investments
ApprovedExecutive2 papers
AI summaryEast Lindsey Executive Board approves £650,000 ELIF-funded business support programme focused on energy management, to launch April 2026 and run until March 2028.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedBusiness support model and funding allocations approved
Money£650,000 over two yearsFrom East Lindsey Investment Fund, Business Support strand
What happens nextLaunch April 2026Two-year programme running to March 2028
Who it affectsEast Lindsey businessesFrom start-ups to larger high energy users
What was decided
The Executive Board approved the business support model and funding allocations set out in the report. Report P3
Delegated authority was granted to the Assistant Director for Strategic Growth and Development, in consultation with the Portfolio Holders for Market Towns and Coastal Economy, to finalise scheme design, enter contracts and launch. Report P4
Why
To deliver a coherent, staged support pathway for East Lindsey businesses to move from energy awareness through to investment and delivery, using both public and private sector expertise. Report 2.3, 2.15, 3.2
Existing energy support was found to be fragmented and time-limited, with public money spent on audits that often were not actioned, and UKSPF funding for current programmes ends in March 2026. Report 2.4, 2.9, 2.10
What happens next
Officers will progress to detailed scheme design and launch the programme in April 2026, acting under delegation and in consultation with the relevant Portfolio Holders. Report 3.2, P85
Procurement of delivery partners across the five pillars will be undertaken, with the Senior Programme Coordinator role continuing to drive coordination. Report 2.41, P83
The money
£10m East Lindsey Investment Fund approved by members in September 2024 Report 1.1
£1.85m Set aside under the Business Support strand at the commencement of ELIF Report P10
£1.2m ELIF funds agreed on 5 November 2025 to support employment land in Louth Report P10
£650,000 Remaining ELIF funds under the Business Support theme, sought as revenue budget over two years Report 2.2, P81
c£150k UKSPF invested in East Lindsey during 2025/26 under Advice4Growth, set to reduce substantially Report 2.38
Options considered
Chosen: Approve the business support model and funding allocations as set out. To deliver the anticipated benefits articulated in the report Report P3, P5
Rejected: Do nothing. The benefits sought from the proposal would not be achieved Report P7
Implications
Financial: Seeks a revenue budget of £650,000 over two years from the East Lindsey Investment Fund. Report P81
Staffing: Includes continuation of the existing Senior Programme Coordinator post from Grants4Growth and Advice4Growth, which ends March 2026. Report P74, P76
Legal: Decisions on ELIF funding rest within the delegated powers of the Executive Board; contracts will arise from procurement of delivery partners. Report P78, P88
Risk: Risks identified include demand, procurement, coordination and quality risks; mitigated through partner due diligence, flexible scaling and dedicated staffing. Report P83
Other: The model is intended to act as a proof of concept that could be considered for adoption by successor authorities under Local Government Reorganisation. Report P15, 3.3
Who and where
East Lindsey businesses of all sizes, from start-ups and micro-enterprises to larger high energy users Report 2.17, P31
Local residents seeking retrofit-related training and qualifications Report P52, 2.35
Private sector energy solutions firms and delivery partners Report 2.12, 2.13
South and East Lincolnshire Councils Partnership (SELCP) through continuation of programme coordination Report 2.26, P70
Timeline
September 2024: Members approved the £10m East Lindsey Investment Fund Report 1.1
February 2025: ELIF funds apportioned across four themes including Business Support Report 1.1
5 November 2025: Members approved £1.2m of ELIF funds for employment land in Louth Report P10
March 2026: UKSPF funding for Grants4Growth and Advice4Growth ends; Low Carbon Lincolnshire provision ceases Report 2.4, 2.9, 2.37
April 2026: Programme planned to launch Report P2, 2.16, P85
March 2028: Programme planned to end after two years Report 2.16, P85
Plain English for the jargon
ELIF: East Lindsey Investment Fund
SELCP: South and East Lincolnshire Councils Partnership
UKSPF: UK Shared Prosperity Funding
PECT: Peterborough Environment City Trust, which delivered the Low Carbon Lincolnshire programme
LGR: Local Government Reorganisation
PPA: Power Purchase Agreement
EV: Electric Vehicle
PV: Photo Voltaic
USP: Unique Selling Point
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item161
Resolved
That the business support model and funding allocations, as set out within this report be approved. 2. That delegated authority be granted to the Assistant Director – Strategic Growth and Development, under consultation with the Portfolio Holder for Market Towns and Portfolio Holder for Coastal Economy, to finalise detailed scheme design, enter into necessary contracts and launch the scheme as per the approach detailed within the report.
Word for word from the decision East Lindsey published for this meeting.Source: democracy.e-lindsey.gov.uk
This report sets out a proposal for an ELIF-funded business support programme, co- ordinated and commissioned by the Council, and designed to provide the local business community with a range of support to assist them in making smart and informed energy management decisions and investment. The proposal also includes funding to support skills development in the supply chain associated with energy efficiency in commercial premises, alongside funding support for general business advisory support that will both enhance the core programme whilst also delivering on the wider business growth ambitions of the district.
The paper sets of the core elements of the model, the outcomes sought from each element, the approach to management and delivery, and support for delegations from members to officers to proceed with detailed design and delivery of the programme. This is with a view to launch the programme in April 2026, providing a continuity of business support for East Lindsey businesses when broader countywide and SELCP-wide programmes come to an end. Recommendations
1. That the business support model and funding allocations, as set out within this report, is approved by Executive Board
2. That delegated authority be provided to the Assistant Director – Strategic Growth and Development, under consultation with the Portfolio Holder for Market Towns and Portfolio Holder for Coastal Economy, to finalise detailed scheme design, enter into necessary contracts and launch the scheme as per the approach detailed within the report.
Reasons for recommendations
To deliver the anticipated benefits, as articulated within this report
Other Options Considered
Do nothing. Under this option, the benefits sought from the proposal within this report are not achieved.
Background
1.1In September 2024, members approved the £10m East Lindsey Investment Fund to support the priorities of making our places welcoming, supporting events and attracting visitors, community development, and supporting business growth. In February 2025 a further paper was considered by members which apportioned those funds across four key themes, those being:
• Pride in Place. This strand is framed around investment into areas that provide the community with a sense of ownership and enhance the levels of pride that the community feels for their place and environs. • Community Development. This strand focuses on a wide-ranging set of activities for engaging and supporting volunteers and development that is focused on addressing East Lindsey challenges – affordable housing, supporting the vulnerable and healthy living are outlined under this theme. • Tourism and Events. This theme includes activities and projects that increases footfall, spend in the economy and promotes our towns, wolds and coast as places to visit, live, work and invest in. • Business Support. This is framed around the SELCP Growth and Prosperity Plan, where enabling business growth through investment, skills and support are key priorities.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
2026/27 Quarter 1 Finance Update1) That the General Fund forecast revenue outturn position for 2026/27 being an underspend of £56k as detailed in Tab...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.