East Midlands Combined County Authority
Investment Committee, Monday 7 September 2026

EMIZ Funding Decision: New Explore Facility

Agreed Committee 1 paper

AI summaryEMCCA Investment Committee approves Final Business Case for the New Explore Facility, committing up to £4.62m of EMIZ capital funding towards the £9.1m project.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedSubject to final subsidy assessment and legal, financial and assurance controls
Moneyup to £4.62m from EMCCATotal project cost approximately £9.1 million
What happens nextEnter into Grant Funding AgreementThen move the project into delivery
Who it affectsNot stated

What was decided

The Investment Committee approved the Final Business Case for the New Explore Facility, enabling EMCCA to enter into a Grant Funding Agreement subject to final subsidy assessment. Report 2.1, 2.2

Why

The project is the first scheme from the approved EMIZ capital pipeline to come forward for a final funding decision, following shortlisting agreed in June 2026, and is supported by the Investment Panel. Report 2.1, 4.3, P12

What happens next

EMCCA will enter into a Grant Funding Agreement with the grant recipient incorporating milestone-based payments, monitoring, subsidy control compliance and clawback provisions. Report P16, P27

The recipient must procure project contracts in line with the procurement strategy approved by EMCCA, demonstrating open, fair and proportionate competition. Report 6.3

The money

  • up to £4.62m EMIZ capital funding from EMCCA towards the New Explore Facility Report P17, 6.2
  • approximately £9.1 million Total development costs of the project, remainder funded by grant recipient Report P17, 6.2
  • £160 million Total EMIZ funding package Report 3.2
  • up to £140 million Flexible fund accessible to EMCCA after tax site boundary process Report 3.3
  • £95 million Identified pipeline demand over three years, covering up to 20 projects Report 4.2
  • £14.21 million EMIZ Capital Grant budget for 2026/27 approved by EMCCA Board in January 2026 Report P19
  • £47.2 million EMIZ indicative funding allocation through to 2030/31 within EMCCA's Medium-Term Financial Strategy Report P20

Options considered

  • Chosen: Approve Final Business Case and proceed to Grant Funding Agreement. Supported by Investment Panel, demonstrates positive economic case with forecast productivity, employment and GVA benefits Report 2.1, P12, P23

Implications

  • Financial: EMCCA will not be obliged to provide additional funding in the event of cost increases; any expenditure above the approved budget will be met by the grant recipient unless further funding is approved through EMCCA's governance. Report P19, P26, 6.2
  • Financial: The EMCCA contribution is approximately £0.30m higher than the indicative funding allocation identified at CID stage; the summary in section 6.2 describes this as around £0.1m higher. The additional requirement can be accommodated within the approved 2026/27 EMIZ Capital Grant budget of £14.21 million. Report P18, P19, 6.2
  • Financial: No additional pressure on EMCCA's core budgets is anticipated, as the grant is funded entirely from Investment Zone grant provided by central government. Report P22
  • Legal: The approach must comply with EMIZ funding arrangements and statutory requirements. The Grant Funding Agreement will include Subsidy Control clauses, clawback provisions, and procurement obligations requiring open, fair and proportionate competition. Report 6.3, P27
  • Legal: Appendix A is exempt under paragraph 3 of Part 1 of Schedule 12A to the Local Government Act 1972, with the public interest in maintaining the exemption outweighing disclosure at this time. Report P31, P32, P33

Who and where

  • The grant recipient for the New Explore Facility Report P17, P27
  • East Midlands Investment Zone programme and its three designated sites: Infinity Park Derby, Hartington Staveley in Chesterfield, and Explore Park Report 3.2
  • EMCCA's Medium-Term Financial Strategy, as the EMIZ allocation through to 2030/31 is incorporated within it Report P20

Timeline

  • October 2024: 10-year tax incentives confirmed for EMIZ Report 3.2
  • 7 July 2025: Investment Committee approved the EMIZ Strategy and Investment Plan Report 3.4, 6.5
  • January 2026: EMCCA Board approved £14.21 million EMIZ Capital Grant budget for 2026/27 Report P19
  • March 2026: Project forecast to start, with completion approximately one year later Report P26
  • 29 June 2026: Investment Committee approved four projects into the EMCCA pipeline and CID stage approval for New Explore Facility Report 4.2, 4.3, 6.1
  • 2026/27 and 2027/28: Grant payments expected to be made and fully defrayed Report P21
  • 2026-09-07: Investment Committee approved Final Business Case for New Explore Facility
  • through to 2030/31: EMIZ indicative funding allocation of £47.2 million within EMCCA's Medium-Term Financial Strategy Report P20

Plain English for the jargon

  • EMIZ: East Midlands Investment Zone, a government-backed initiative to drive economic growth in clean industries and advanced manufacturing
  • EMCCA: East Midlands Combined County Authority
  • FBC: Final Business Case
  • CID: Concept Initiation Document, an earlier stage in the assurance pipeline
  • GVA: Gross Value Added, a measure of economic output
  • MTFS: Medium-Term Financial Strategy
  • Single Assurance Framework: EMCCA's process for project approval and assurance
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item8

Resolved

RESOLVED to unanimously agree: A) That the Final Business Case for the New Explore Facility, included in Appendix A, be approved to enable EMCCA to enter into a Grant Funding Agreement subject to final subsidy assessment.
Word for word from the decision East Midlands Combined County Authority published for this meeting. Source: democracy.eastmidlands-cca.gov.uk

Follow this further

Built from East Midlands Combined County Authority's papers

What the report saysPro

Report to Investment Committee

Executive summary

2.1This report seeks Investment Committee approval of the Final Business Case for EMIZ capital investment in the New Explore Facility project. The project is the first scheme from the approved EMIZ capital pipeline to come forward for a final funding decision, following the pipeline development work and shortlisting agreed through the June Investment Committee process.

2.2Approval will allow EMCCA to enter into a Grant Funding Agreement and move the project into delivery, subject to the normal legal, financial and assurance controls. The recommendation is supported by the Investment Panel and is in line with the EMIZ Strategy and Investment Plan, which prioritised early investment in strategic sites to unlock growth, support clean industries and advanced manufacturing, and strengthen the long-term benefits of the Investment Zone programme.

Background

3.1EMIZ is a government-backed initiative designed to supercharge economic growth in the region by focusing on clean industries and advanced manufacturing. It’s part of a broader UK strategy to create high-potential clusters that attract investment, create jobs, and drive innovation. The East Midlands investment zone has designated areas where EMCCA can offer special incentives to attract businesses and stimulate economic growth.

3.2EMIZ has a £160 million total funding package, and 10-year tax incentives were confirmed in October 2024. The designation includes three specialised sites which will host a variety of tax benefits and includes two sites which will adopt Business Rate Retention facilities to enable reinvestment for economic growth purposes. Business Rate Retention and tax incentives are available at Infinity Park Derby and the Hartington Staveley site in Chesterfield. Explore Park is the third designated Investment Zone site and benefits from a tax incentive offer.

3.3Of the £160 million, EMCCA has access to a flexible fund of up to £140 million which was determined following the conclusion of the tax site boundary process which utilises £20 million of spend based on the hectarage of the tax sites. The funding is split into defined flexible-spend themes, including skills, local infrastructure, innovation, business support, planning and management costs. These themes will determine both the capital and revenue spend of the programme to support the growth of the key sectors, and funding is divided 60% capital and 40% revenue.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
EMIZ Funding Decision: New Explore FacilityDecisions 160 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 13 attended
NK
Councillor Neghat KhanChair, present
SR
Councillor Stephen ReedVice-Chair, present
KK
Councillor Kathy KozlowskiConstituent Member, apologies
NO
Councillor Ndukwe OnuohaConstituent Member, present
JL
Councillor John LawsonConstituent Member, present
PI
Councillor Patience IfedioraConstituent Member, present
SM
Councillor Stuart MatthewsConstituent Member, present
JR
Councillor James RawsonConstituent Member, present
JY
Councillor Jane YatesNon-Constituent Member, apologies
CE
Councillor Chris Emmas-WilliamsNon-Constituent Member, apologies
NC
Councillor Neil Clarke MBENon-Constituent Member, apologies
JC
Councillor John Clarke MBENon-Constituent Member, present

All 13 on the meeting page

On this subject at East Midlands Combined County Authority

Search all
  1. EMIZ Funding Decision: New Explore FacilityThis decision
  2. EMIZ Funding DecisionsAgreed

More from East Midlands Combined County Authority Investment Committee

All decisions
MeetingDecisionOutcome
7 Sep 2026 Minutes of the previous meetingRESOLVED to unanimously agree: That the minutes of the meeting of the Investment Committee held on 29 June 2026 be ap... Agreed Open
7 Sep 2026 EMCCA Investment PortfolioRESOLVED to unanimously agree: A) That the and the information around future reporting of project and programme perfo... Agreed Open
7 Sep 2026 Local Growth Fund - Project Update and ApprovalsRESOLVED to unanimously agree: A) That the authority to approve the final business case for the £8.1m Business Invest... Agreed Open
7 Sep 2026 Investment Committee Work ProgrammeRESOLVED to unanimously agree: A) That the draft Work Programme attached at Appendix A be approved and that regular u... Agreed Open
7 Sep 2026 Exclusion of Press and PublicRESOLVED to unanimously agree: A) That the public and press be excluded for the remaining item of business for the re... Agreed Open