AI summaryEMCCA Investment Committee approves four projects onto the East Midlands Investment Zone capital pipeline, with combined indicative value of about £30.4m, subject to further business case work.
Written from the decision and the officer reportPDF Pro
OutcomeAgreedDecision taken at CID stage, not final funding approval
MoneyAbout £30.4m indicative totalAcross four shortlisted projects, subject to change
What happens nextProgress through Single Assurance FrameworkFurther schemes expected at September 2026 meeting
Who it affectsEMIZ designated sites and project sponsorsInfinity Park Derby, Hartington Staveley, Explore Park
What was decided
Approved the four projects in Appendix A for inclusion onto the EMIZ capital pipeline at CID stage, to be developed through the Single Assurance Framework process. Report 4.3
Noted the approach for development of the wider pipeline of projects through the EMIZ Programme, with remaining projects to form a Long List for further work before shortlisting. Report 4.4, P12, P13
Noted the approach to revenue funding and bringing projects forward for development, including internal delivery of skills and business support activity. Report P15, P16, P17
Why
Identified pipeline demand of £95m over three years materially exceeds available programme headroom of c.£84m capital, so prioritisation and sequencing is needed rather than parallel progression of all schemes. Report 2.1, 4.2, P21, P22
An independent appraisal framework tested projects against priority sector delivery, priority location, unlocking additional growth, affordability, deliverability and operational viability, leading to four recommendations. Report 4.3, P8
The Long List and Shortlist approach manages financial risk by avoiding over-commitment and ensuring only schemes meeting assurance requirements are progressed. Report P13, P22
What happens next
Officers will work with project sponsors to progress the four shortlisted projects through the Single Assurance Framework, where Final Business Case decisions will be made. Report 4.3, P30
Work on the Long List will progress over the summer, with additional initiatives expected to be presented at the September Investment Committee meeting. Report P14
EMCCA will deliver skills, innovation and business support activity using annual EMIZ revenue allocations, with internal delivery teams seeking synergies with existing provision. Report P15, P16, P17
The money
£95m Identified pipeline demand over three years (up to 20 projects) Report 2.1, 4.2
£160m Total EMIZ funding package, confirmed October 2024 Report 3.2, P21
£140m Flexible fund available to EMCCA across capital and revenue Report 3.3, P21
£20m Spend attributed to tax site hectarage boundary process Report 3.3
c.£84m Indicative capital allocation across the lifetime of the grant (60% of flexible fund) Report P21, P30
£30.4m Total indicative value of the four shortlisted projects in scope of this decision Report P23, P30
c.£15.0m EMCCA contribution toward Infinity HQ, within a £36.2m total scheme Report P23
c.£8.4m IPD Power Infrastructure project indicative funding request Report P23
c.£4.5m New Explore Facility indicative funding request Report P23
c.£2.3m Temporary revenue pressure if early IPD Power Infrastructure phases fall within Business Rates Retention until capitalisation is permitted Report P25
Options considered
Chosen: Approve the four projects in Appendix A for inclusion on the EMIZ capital pipeline at CID stage. Reflects independent appraisal recommendations and officer review of CID submissions against affordability, deliverability and priority criteria Report 4.3
Rejected: Reject the recommendation and pursue alternative pipeline arrangements. Not discussed in the report; the paper sets out only the recommended controlled and deliverable approach Report 2.1, 4.2
Implications
Financial: Inclusion at CID stage does not constitute final funding approval but creates a contingent financial commitment against the EMIZ programme, subject to Single Assurance Framework and Final Business Case approval. Report 6.1, P21, P27
Financial: Costs and funding figures remain indicative and subject to validation of costs, phasing, funding profiles, affordability, subsidy control compliance and value for money. Report P24, P28
Financial: A temporary revenue pressure of c.£2.3m could arise if early IPD Power Infrastructure phases fall within Business Rates Retention and are treated as revenue until capitalisation is permitted. Report P25
Legal: Future support for individual projects remains subject to compliance with the Single Assurance Framework, affordability confirmation, procurement, subsidy control, and appropriate funding agreements or contracts. Report P32
Legal: Appendix A is treated as confidential as it contains commercially sensitive project information; the public interest in maintaining the exemption was judged to outweigh disclosure at this stage. Report P33
Risk: The pipeline approach manages financial risk by sequencing projects and avoiding over-commitment against available resources, given pipeline demand exceeds current capital allocation. Report P22, P30
Who and where
Project sponsors of the four shortlisted projects (Hartington Commerce Park Phase 1, Infinity HQ, IPD Power Infrastructure, and the New Explore Facility) Report P23, 4.3
Businesses and investors at the three EMIZ designated sites: Infinity Park Derby, Hartington Staveley in Chesterfield, and Explore Park Report 3.2
Clean industries and advanced manufacturing sectors targeted by the Investment Zone programme Report 3.1
Sponsors of Long List projects, which require further development before shortlisting Report 4.4, P12, P13
Timeline
October 2024: EMIZ designation confirmed with £160m total funding package and 10 year tax incentives Report 3.2
7th of July 2025: Investment Committee approved the EMIZ Strategy and Investment Plan Report 5.7
Summer 2026: Work will progress on the Long List of remaining projects Report P14
29 June 2026: Investment Committee approved the four projects for inclusion on the EMIZ capital pipeline at CID stage
September 2026: Additional initiatives expected to be presented at the Investment Committee meeting Report P14
Plain English for the jargon
EMIZ: East Midlands Investment Zone, a government backed initiative focused on clean industries and advanced manufacturing in the region
EMCCA: East Midlands Combined County Authority
CID: Concept Initiation Document, the early stage at which projects enter the pipeline before full business case development
Single Assurance Framework: The process through which projects are assessed and approved before contract award
Business Rate Retention: A facility available at two of the three EMIZ sites, enabling reinvestment of retained business rates for economic growth
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item10
Resolved
RESOLVED to unanimously agree: A) That the projects in Appendix A for inclusion onto the EMIZ capital pipeline to be developed through the Single Assurance Framework process be approved. B) That the approach for development of the wider pipeline of projects through the EMIZ Programme be noted. C) That the approach to revenue funding and bringing projects forward for development be noted.
Word for word from the decision East Midlands Combined County Authority published for this meeting.Source: democracy.eastmidlands-cca.gov.uk
Follow this further
Built from East Midlands Combined County Authority's papers
2.1This report asks the Investment Committee to approve a controlled and deliverable approach to the EMIZ capital pipeline over the next three years. Following independent appraisal and officer review, four projects are recommended for inclusion in the EMCCA pipeline at CID stage so they can progress into business case development and the Single Assurance Framework process. This approach reflects the need to prioritise and sequence investment, given identified pipeline demand of £95m over three years against available programme headroom.
2.2The report also sets out the approach for progressing the wider EMIZ pipeline. Remaining projects will form a Long List and will be developed through structured engagement and project development activity to address gaps in scope, deliverability, affordability, match funding and value for money before being brought forward for Shortlisting and formal assurance. In parallel, EMCCA will implement revenue-funded activity in the Skills, Innovation and Business Support workstreams in line with the Strategy and Investment Plan previously agreed by the Investment Committee, ensuring that capital and revenue interventions are aligned as the programme moves into delivery.
Background
3.1EMIZ is a government-backed initiative designed to supercharge economic growth in the region by focusing on clean industries and advanced manufacturing. It’s part of a broader UK strategy to create high-potential clusters that attract investment, create jobs, and drive innovation. The East Midlands investment zone has designated areas where EMCCA can offer special incentives to attract businesses and stimulate economic growth.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Investment Committee at East Midlands Combined County Authority and we tell you when its next papers are published, before the meeting rather than after it.
Minutes of the previous meetingRESOLVED to unanimously agree: That the minutes of the meeting of the Investment Committee held on 29 June 2026 be ap...
Investment Committee Work ProgrammeRESOLVED to unanimously agree: A) That the draft Work Programme attached at Appendix A be approved and that regular u...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.