Award of Mechanical and Electrical Maintenance and Reactive Repairs Contract

Decided Executive 1 paper

Cabinet decided this item on Wednesday 18 March 2015. Below is the council's own wording, with the papers it was decided on.

Item11

Resolved

View the decision text for item 11.
Word for word from the decision Elmbridge published for this meeting. Source: mygov.elmbridge.gov.uk

Follow this further

Built from Elmbridge's papers

What the report saysPro

Report to Cabinet, 4 pages

Executive summary

To approve the outcome of the tendering process and awarding of the Mechanical and Electrical Maintenance and Reactive Repairs

RECOMMENDATION: THAT

OFFICERS BE AUTHORISED TO AWARD THE MECHANICAL AND ELECTRICAL MAINTENANCE AND REACTIVE REPAIRS CONTRACT TO OPTIMUM GROUP SERVICES PLC FOR A FIVE YEAR PERIOD, WITH AN OPTION FOR THE COUNCIL TO EXTEND FOR A FURTHER PERIOD OF UP TO TWO YEARS (SUBJECT TO THE COUNCIL DECIDING TO DO SO AND SUBJECT TO SATISFACTORY PERFORMANCE)

REPORT:

1. EXISTING ARRANGEMENTS

1.1The Council currently has a limited pre-planned maintenance contract covering the Civic Centre only. This contract is to provide planned maintenance and reactive M&E services to the Civic Centre with an operative based on site for two days per week. The contract is due to expire on the 4th May 2015.

1.2All other mechanical and electrical maintenance and reactive repairs for the Council’s operational property estate is undertaken using a number of different contractors on various arrangements.

2. TENDER PROCESS

2.1This Contract covers all Council properties including the activities covered in the existing Contract with enhanced maintenance for properties which are not currently covered.

2.2The specification, evaluation criteria and documentation was developed and reviewed with Procurement support and advice. 2.3. The value of this contract required the Council to advertise the tender in the Official Journal of the European Union, in accordance with Public Contract Regulations 2006. This resulted in 34 expressions of interest, with 12 companies submitting a Pre-Qualification Questionnaire (PPQ).

2.4Officers from Asset Management and Property Services (AMPS) undertook the PQQ shortlisting process with Procurement carrying out the commercial assessment and shortlisted the six highest scoring companies, who were invited to progress to the Invitation to Tender (ITT) stage.

2.5All six companies were provided with a date, contacts and locations to undertake site visits. All companies took up the option of site visits, with a number of representatives from each company escorted to the various sites by officers from AMPS.

2.6The Tender process was run through Procurement who also supported the clarification requirements. During the tender process two of the companies decided to withdraw from the tender stage of the process. One company withdrew due to their current business configuration and significant increased remodelling that would need to be undertaken to deliver the contract. The other company advised it was not able to accept certain terms and condition of the tender of the Council and therefore withdrew.

2.7The Evaluation Criteria of tender was the most economically advantageous tender with 60% Cost and 40% Quality weighting.

2.8AMPS officers undertook the review of the completed ITT submissions to evaluate the 40% quality weighting criteria. This resulted in the scores shown in the Table below.

2.9AMPS recruited the services of Ridge and Partners LLP, property and construction consultants to undertake the review of the cost elements of the tender returns.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Award of Mechanical and Electrical Maintenance and Reactive Repairs ContractReport 4 pages DownloadRead as text

More from Elmbridge Cabinet

All decisions
MeetingDecisionOutcome
27 Oct 2026 Old Post Office EsherView the decision text for item 22/26 Decided Open
16 Sep 2026 Disposal of land in Oaken Lane, Claygate, EsherView the decision text for item 15/26 Decided Open
16 Sep 2026 Water Play Strategy UpdateView the decision text for item 16/26 Decided Open
16 Sep 2026 Elmbridge Local Plan 2039: Notice of commencement of plan-making and Local Plan timetableView the decision text for item 17/26 Decided Open
16 Sep 2026 2026/27 Revenue and Capital Budget Update - Quarter 1View the decision text for item 19/26 Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies