Cabinet, Wednesday 15 November 2017 at 7.00pm

River Thames Scheme

Decided Executive 3 papers

Cabinet decided this item on Wednesday 15 November 2017. Below is the council's own wording, with the papers it was decided on.

Item56/17

Resolved

View the decision text for item 56/17
Word for word from the decision Elmbridge published for this meeting. Source: mygov.elmbridge.gov.uk

Follow this further

Built from Elmbridge's papers

What the report saysPro

Report to Cabinet, 5 pages

Executive summary

The River Thames Scheme has been in development for many years but the flooding in 2014 meant that there was a sense of urgency both locally and in central government to provide some form of flood protection. There has been progress across a range of initiatives as summarised in this report. However, there remains a funding gap in both the costs to complete the feasibility studies and the construction costs. There is work on-going to try and address the shortfall but the Local Authorities along the stretch of River between Maidenhead and Teddington are being asked to contribute.

RECOMMENDED: THAT CABINET

NOTES THE PROGRESS WITH THE RIVER THAMES SCHEME AND THE COUNCIL’S IN PRINCIPLE AGREEMENT TO FUND ELMBRIDGE’S CONTRIBUTION FROM THE CIL STRATEGIC INFRASTRUCTURE PROJECTS BUDGET.

REPORT:

1. The purpose of this report is to update Members on the River Thames Scheme and to seek agreement to a contribution to the scheme construction costs.

Background

2. Following the floods in 2012, The Environment Agency has been leading on the development of what is called the River Thames Scheme. The intention of the scheme is to reduce flood risk in communities between Datchet and Teddington. This stretch of river has the largest area of developed floodplain in England without flood defences. Key details of the scheme can be found in the scheme brochure in appendix 1. Full detail can be found at: https://www.gov.uk/government/collections/river-thames-scheme

3. The initial work was carried out in 2009 as a part of the then Lower Thames flood risk management strategy which was finalised after consultation with other public bodies, businesses and residents. The scheme consists of:  a new flood channel  improvements to 3 of the existing Thames weirs  installation of property level products for up to 1,200 homes (to make them more resistant to floods)

4. The Environment Agency (EA) is the lead agency working on the scheme and has established:

 A Sponsoring Group which consist of the Leaders from all 7 local authorities along this stretch of river and representatives from DEFRA, The Treasury and Thames Water  A Programme Board of senior officers from the 7 local authorities and other public bodies to oversee the development of the scheme  Working Groups including planning and finance.

5. Cabinet received a report on progress on the 8 July 2015 where it was agreed that the Council would commit £12,920 per year for the next five years as a contribution towards the feasibility costs.

Elmbridge’s Focus

6. There are three key issues for the Officer’s and Leader on these Boards:

 To ensure that the scheme provides as much protection as possible to the properties in Elmbridge affected by the flooding in 2014. Hence the Community Resilience work that has been led by the EA in affected areas helping local communities to draft emergency plans and agree how to protect their properties  Take as many properties as possible out of the flood zone. To date this is estimated to be 99  To ensure the works up stream don’t impact in any way on river levels down river including Elmbridge. The proposed work on the weirs which will occur prior to any other work are an example of this. There has been detailed modelling of the scheme design to assess the impact of the various elements.

Consultation

7. During the design of the scheme there have been various consultations with local residents’ groups the next being on the 14th November 2017. In addition, Officers from the EA have attended Overview and Scrutiny meetings to provide updates on the scheme design and community resilience work.

Benefits for Elmbridge

8. According to studies carried out by the EA, the River Thames Scheme in the Elmbridge area will:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Scheme Details /17Appendix 1 3 pages Download
PDF
Funding Proforma /17Appendix 2 2 pages Download
PDF
River Thames SchemeReport 5 pages DownloadRead as text

More from Elmbridge Cabinet

All decisions
MeetingDecisionOutcome
27 Oct 2026 Old Post Office EsherView the decision text for item 22/26 Decided Open
16 Sep 2026 Disposal of land in Oaken Lane, Claygate, EsherView the decision text for item 15/26 Decided Open
16 Sep 2026 Water Play Strategy UpdateView the decision text for item 16/26 Decided Open
16 Sep 2026 Elmbridge Local Plan 2039: Notice of commencement of plan-making and Local Plan timetableView the decision text for item 17/26 Decided Open
16 Sep 2026 2026/27 Revenue and Capital Budget Update - Quarter 1View the decision text for item 19/26 Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies