Resolved
View the decision text for item 29/21
Cabinet decided this item on Wednesday 15 September 2021. Below is the council's own wording, with the papers it was decided on.
Resolved
View the decision text for item 29/21
This quarterly monitoring report against the 2021/22 approved budget provides an update on the Revenue and Capital budget position as at 30 June 2021.
Recommended: that Cabinet is asked to note
(a) The revenue and capital budget position for the first quarter of 2021/22.
Report:
1. Revenue Budget
1.1At the end of June 2021, the operational revenue position is £429,522 lower than the net operational budget. The underspend is mainly due to the inclusion of the estimated government support for the under recovery of income in the first three months as a direct consequence of Covid-19. The government have indicated that the support for reductions in sales fees and charges income is for the first quarter of the year only. The continued impact of the decrease in the incomes generated from these services will, if no additional government support is provided, have a direct impact on the outturn for the year,
The additional costs relating to Covid-19 for the first quarter and a proportion of the £0.5 million Covid-19 grant received from Central Government funding those additional costs of the Councils response have been included in the Q1 monitoring. It has been assumed that this government grant towards the additional Covid-19 costs in 2021/22, will be the only funding made available by government towards the costs this year. The grant has been apportioned in line with the current forecast profile for the additional expenditure to be incurred.
1.2Appendix A contains the budget monitoring by portfolios to 30 June 2021, with Appendix B showing the variances against the key indicators. The following significant variations against the profiled budget by portfolio are as follows: Corporate Development
The underspend of £140,000 is mainly due to provisional cost savings of £76,000 on the Borough elections as a result of sharing the costs with both Surrey County Council and the Police Commissioner along with £44,000 of unexpected government support towards the cost of the elections. There are also other savings resulting from Covid-19 pandemic including cancellation of the mayor’s civic reception and the publication of the Elmbridge review.
Environment
The overspend of £47,000 is mainly due to reduced levels of Green Waste subscriptions being received than budgeted for in the first three months. There was an increase in activity last year, the budget was increased to reflect the increase in volumes. There was also additional income from the increase in the fees charged for this service and overall this additional income has not been achieved.
In addition there is an increase against budget on the fixed elements of the Joint Waste contract and it is expected that this overspend will increase, once the invoices for the variable elements of the contract are received The Council has not received/processed any invoices for the variable elements of the contract this financial year, as consequence it is difficult to predict the exact amount of overspend on the contract at this stage.
The impact of Covid-19 on the employees of the council’s waste contractor resulted in the suspension for the garden waste collection service, as a result the Council have currently extended the subscription period by 1 month. This will also reduce the income due for 2021/22 impacting the outturn for the year.
Highways & Transport
The overspend of £283,000 is mainly due to the reduced activity levels relating to off-street parking due to Covid-19. Appendix B shows a loss of parking income to the end of June of £288,000 with the majority in the commuter car parks. This is offset by a small amount of cost savings relating to income collection and car park maintenance.
Housing
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
2021/22 Revenue and Capital Budget Update: Quarter 1Report | 7 pages | DownloadRead as text |
PDF |
Financial Performance Monitoring by Portfolio to June 2021 /21Appendix A | 1 pages | Download |
PDF |
Financial Performance Monitoring Significant/Key Budgets to June 2021 /21Appendix B | 1 pages | Download |
PDF |
Capital Budget Monitoring to June 2021 /21Appendix C | 3 pages | Download |
Follow Cabinet at Elmbridge and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 27 Oct 2026 | Old Post Office EsherView the decision text for item 22/26 | Decided | Open |
| 16 Sep 2026 | Disposal of land in Oaken Lane, Claygate, EsherView the decision text for item 15/26 | Decided | Open |
| 16 Sep 2026 | Water Play Strategy UpdateView the decision text for item 16/26 | Decided | Open |
| 16 Sep 2026 | Elmbridge Local Plan 2039: Notice of commencement of plan-making and Local Plan timetableView the decision text for item 17/26 | Decided | Open |
| 16 Sep 2026 | 2026/27 Revenue and Capital Budget Update - Quarter 1View the decision text for item 19/26 | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.