Resolved
View the decision text for item 53/21
At the Overview and Scrutiny Committee meeting on 25 November 2021, the Community Safety Working Group reported on the Elmbridge public space CCTV and made recommendations regarding its procurement in 2022.
The Elmbridge public space CCTV monitoring and maintenance contract expires in July 2022. Luton Council, who own the CCTV control room at Luton Town Hall, which Elmbridge uses, are tendering for the CCTV and access control in January 2022 and plan to appoint a supplier in March 2022. Meaning that should Luton Council appoint a new supplier this will have a consequence for the monitoring of Elmbridge CCTV.
It is recommended that Elmbridge partner Luton in their upcoming procurement, whilst also continuing to analyse the market to keep the options open for Elmbridge should it not prove economically advantageous.
Recommended: that
(a) the information regarding Elmbridge public space CCTV is noted; and
(b) authority be delegated to the Chief Executive, in consultation with the Leader of the Council, to agree the Elmbridge Public Space CCTV contract with the chosen supplier as appropriate.
Report:
1. Introduction
1.1Elmbridge Borough Council has provided a public space CCTV service since 2003.
1.2The system was originally run in-house, from a control room at Walton Police Station. From April 2012 to 2018 it was outsourced to Runnymede Borough Council and since 2018 it has been contracted to Quadrant Security Group Ltd (Now known as Synectics Security Ltd) where it is monitored in a control room located at Luton Town Hall. 1.3 The Overview and Scrutiny Community Safety Working Group reviewed the options for CCTV procurement and the preferred way forward is to:
Reduce monitoring times to an agreed 12-hour period (to be agreed with Surrey Police) Join the Luton Council CCTV procurement and safeguard the risk to Elmbridge if it is not economically advantageous to procure a similar service
2 Background and context
2.1Elmbridge expenditure in relation to CCTV includes 24/7 monitoring, reactive and pre-planned maintenance, BT line rental, electricity, insurance and other associated costs.
2.2In a letter dated 18 November 2020 from Chief Superintendent Lynette Shanks, it was confirmed that Surrey Police’s contribution to Elmbridge CCTV would be £60,000 in 2021/22 and (as it currently stands) Surrey Police’s contribution for 2022-23 is likely to be in the region of £47,250. However, it was stated in the letter that future contributions may vary up or down depending on service provision i.e. increased number of cameras, improved monitoring etc. Therefore, there would be a budget deficit for Elmbridge in 2021/22 and even greater the following year should expenditure stay the same – subject to procurement.
2.3Most Surrey district and borough councils with access to public space CCTV do not monitor it on a 24/7 basis and do not receive as greater financial contribution from Surrey Police for CCTV.
2.4At this time, the Working Group noted that savings have been maximised on aspects of the CCTV service in terms of BT line rental (further discount pending subject to contract length) and electricity.
3 Proposed procurement
3.1Luton Council are tendering for their CCTV services and access control systems in early 2022. At this time, Luton Council plan to keep the control room, which Elmbridge utilises (including staff), for its monitoring so should they procure a new provider it is likely to mean a TUPE of staff.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Elmbridge Public Space CCTV ProcurementReport | 4 pages | DownloadRead as text |
Follow Cabinet at Elmbridge and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 27 Oct 2026 | Old Post Office EsherView the decision text for item 22/26 | Decided | Open |
| 16 Sep 2026 | Disposal of land in Oaken Lane, Claygate, EsherView the decision text for item 15/26 | Decided | Open |
| 16 Sep 2026 | Water Play Strategy UpdateView the decision text for item 16/26 | Decided | Open |
| 16 Sep 2026 | Elmbridge Local Plan 2039: Notice of commencement of plan-making and Local Plan timetableView the decision text for item 17/26 | Decided | Open |
| 16 Sep 2026 | 2026/27 Revenue and Capital Budget Update - Quarter 1View the decision text for item 19/26 | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.