Cabinet, Wednesday 5 July 2023 at 7.00pm

Esher Town Centre Vision

Decided Executive 3 papers

Cabinet decided this item on Wednesday 5 July 2023. Below is the council's own wording, with the papers it was decided on.

Item17/23

Resolved

View the decision text for item 17/23
Word for word from the decision Elmbridge published for this meeting. Source: mygov.elmbridge.gov.uk

Follow this further

Built from Elmbridge's papers

What the report saysPro

Report to Cabinet, 3 pages

Executive summary

The Esher Town Centre Vision has been updated following the public consultation in March 2023 and is ready for adoption. The next stage in the project is the commissioning of the Stage 1 Feasibility Study to assess the options for, and deliverability of, public realm improvements identified in the Vision. This includes for example, increasing the permeability of the town centre for pedestrians and cyclists, decreasing the disturbance from traffic and creating a children’s play space.

Recommended: that

(a) Cabinet agrees the adoption of the Esher Town Centre Vision; and

(b) Cabinet agrees the allocation of £75,000 for the funding of the Feasibility Study from the Community Infrastructure Levy (CIL) Infrastructure Feasibility Fund.

Report: 1. Esher Town Centre Vision

1.1The Esher Town Centre Vision (Appendix 1) was drafted to support the exploratory work on the options for redeveloping the Civic Centre. The Vision provides an opportunity to create the overarching principles for Esher Town Centre based on our 2030 Vision and place-making ambitions; creating a sustainable, thriving Elmbridge driven by the power of our community.

1.2On 8 February 2023, Cabinet agreed the draft Vision for public consultation from 1 March to 31 March 2023. Over 50 comments on the draft Vision were made at the launch of the Elmbridge Vision 2030 event and over 850 comments submitted via the Council’s on-line consultation portal (see Appendix 2).

1.3Feedback from the public consultation has been used to update the Vision.

1.4Once adopted, the next stage is to commission a Stage 1 Feasibility Study to assess the options for, and deliverability of, the public realm improvements identified in the Vision. This includes for example, increasing the permeability of the town centre for pedestrians and cyclists, decreasing the disturbance from traffic and creating a children’s play space. These were key themes from the consultation responses.

2. Funding the Esher Town Centre Feasibility Study

2.1In March 2019, Cabinet agreed to the establishment of an Infrastructure Feasibility Fund which would see £250,000 per annum, for up to five years, be committed to ensure that resources were available and ring-fenced to support project development. The fund is reserved for collaborative projects with Surrey County Council (SCC).

2.2The proposed public realm improvements within Esher Town Centre form part of SCC’s wider vision outlined in the Surrey 2050 Place Ambition, providing an opportunity for Elmbridge to work collaboratively with SCC.

2.3Taking a similar approach to that agreed by Cabinet in September 2020, when £270,000 from the fund was ring-fenced for the Local Cycling and Walking Infrastructure Plans (LCWIP) project, it is proposed that Cabinet approve to fund the Esher Town Centre Feasibility Study from this source.

2.4There is £980,000 unallocated in the Feasibility Fund although, it should be noted that as part of this Cabinet agenda, £15,000 is also sought to undertake a Feasibility Study for the Walton Town Centre Greening Project. Based on similar projects undertaken, a provisional estimate for the cost of the initial Esher Town Centre Feasibility Study is £75,000.

Financial implications: There is £980,000 unallocated in the CIL Infrastructure Feasibility Fund although, it should be noted that as part of this Cabinet agenda, £15,000 is also sought to undertake a Feasibility Study for the Walton Town Centre Greening Project. Nevertheless, based on similar projects, a provisional estimate for the cost of the initial Esher Town Centre Feasibility Study is £75,000.

Environmental/Sustainability Implications: None for the purpose of this report.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Esher Town Centre Vision /23Appendix 1 2 pages Download
PDF
Summary of Consultation Responses /23Appendix 2 8 pages Withheld: personal details
PDF
Esher Town Centre VisionReport 3 pages DownloadRead as text

More from Elmbridge Cabinet

All decisions
MeetingDecisionOutcome
27 Oct 2026 Old Post Office EsherView the decision text for item 22/26 Decided Open
16 Sep 2026 Disposal of land in Oaken Lane, Claygate, EsherView the decision text for item 15/26 Decided Open
16 Sep 2026 Water Play Strategy UpdateView the decision text for item 16/26 Decided Open
16 Sep 2026 Elmbridge Local Plan 2039: Notice of commencement of plan-making and Local Plan timetableView the decision text for item 17/26 Decided Open
16 Sep 2026 2026/27 Revenue and Capital Budget Update - Quarter 1View the decision text for item 19/26 Decided Open