Cabinet decided this item on Wednesday 13 September 2023. Below is the council's own wording, with the papers it was decided on.
Resolved
View the decision text for item 29/23
Elmbridge Borough Council (“the Council”) spends circa £400,000 a year on electricity and gas. The Council needs to re-procure its supply contracts to comply with the Council’s legal obligations and to secure value for money.
Since 2012, the Council has procured electricity and gas through the LASER Energy Buying Group (“LASER”), a Professional Buying Organisation (PBO) established by Kent County Council (KCC). LASER provides energy procurement and contract management on behalf of its public sector members. LASER currently procures energy for over 200 public organisations on behalf of around 85,000 end users, representing over £1.5 billion of gas, electricity and water procurement. LASER also assist with mitigating the rising cost of energy and achieving net zero targets.
The current agreement with LASER runs until the end of September 2024 so the procurement process is at the stage where Cabinet approval is required in order to enter into the appropriate customer access agreements with LASER to enable us to use their framework agreements for the supply of energy and ancillary services from 1 October 2024.
The Council will need to decide by the end of September 2023 whether it wishes to continue to procure its future energy requirements for the period 2024-2028 through LASER. A commitment from the Council is required by the end of September to allow LASER to include the Council’s estimated demand in its aggregate advance procurement volumes.
This report sets out recommendations arising from work on options for the provision of energy and ancillary services to premises owned or operated by the Council following the end of the current framework provision. Recommendation(s): that Cabinet;
(a) approves the Council’s entry into the Access Agreement with Kent County Council to enable its participation and purchase of gas and electricity from the frameworks referred to in recommendations (b) and (c) below;
(b) approves the award of a contract for the supply of electricity to NPower Limited for up to four years from 1 October 2024 via a call-off from LASER Framework ref Y22009;
(c) approves the award of a contract for the supply of gas to Total Energies for up to four years from 1 October 2024 via a call-off from the LASER Framework ref Y22008;
(d) approves the award of contracts for gas and electricity to the next ranked Suppliers on Lot 1 of each of the frameworks if NPower Limited or Total Energies cannot, or do not accept the offer of a Council contract. Such award shall be in accordance with the frameworks listed above;
(e) approves the instruction of LASER’s bureau and fully managed energy services as described in section 3;
(f) approves the continued use of Renewable Energy Guarantee of Origin (“REGO”) certificates as the only offsetting option currently available as described in section 6; and
(g) approves delegated authority to the Strategic Director (Services) following consultation with the Portfolio Holder for Climate Change & Sustainability and the Portfolio Holder for Finance and Resources, to move between energy baskets within the framework during the term of the framework as energy markets dictate.
Report:
1.1The current bulk energy contracts for the Council stem from call off contracts placed in 2020 under the existing LASER framework agreements. LASER are a PBO who have managed gas and electricity supply contracts on behalf of the Council.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Authority to Award Contracts for the Purchase of Gas and ElectricityReport | 14 pages | DownloadRead as text |
Follow Cabinet at Elmbridge and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 27 Oct 2026 | Old Post Office EsherView the decision text for item 22/26 | Decided | Open |
| 16 Sep 2026 | Disposal of land in Oaken Lane, Claygate, EsherView the decision text for item 15/26 | Decided | Open |
| 16 Sep 2026 | Water Play Strategy UpdateView the decision text for item 16/26 | Decided | Open |
| 16 Sep 2026 | Elmbridge Local Plan 2039: Notice of commencement of plan-making and Local Plan timetableView the decision text for item 17/26 | Decided | Open |
| 16 Sep 2026 | 2026/27 Revenue and Capital Budget Update - Quarter 1View the decision text for item 19/26 | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.