Resolved
View the decision text for item 10/24
Cabinet decided this item on Wednesday 3 July 2024. Below is the council's own wording, with the papers it was decided on.
Resolved
View the decision text for item 10/24
This report is the first of a three-stage review of the circumstances that led to the temporary closures of the Centres for the Community (centres) in November 2023. It sets out the findings of the Strategic Director for Place and Community and Head of Community Service as well a timetable of actions taken.
The day centre service run from the centres is a much-loved service, that provides socialisation, food and purpose for some of our elderly residents. However, over time, it has been reduced of the essential resources required to enable it to operate safely. The scale of the issues were fully realised at the end of November of 2023 when the council was left with no option but to close the centres to put in place the necessary training, policies, and procedures to enable them to operate safely. Continuing to operate without making these changes would have left our clients, volunteers, hirers and employees at risk.
The reopening of the centres has been a cross-council endeavour with resources being redirected to expedite the reopening. Additional funds of over £500,000 have also been allocated to resource the service.
The council recognises that the temporary closures were difficult for many of our clients, volunteers, and hirers, especially on the run up to Christmas. We’d like to thank our clients and hirers for their understanding and our volunteers for their offers of taking on additional duties in the centres. We’d also like to thank our centre employees who changed their places of work and hours of work to enable the reopening of centres.
Although the centre service is able to operate safely four days a week, the service is not as robust as it should be. This is because of the way the service has evolved, it will take time to continue with improved systems, staffing procedures and service efficiencies still to be actioned.
Recommendation: that
(a) the safety concerns that led to the temporary closures of the Centres for the Community be noted; and
(b) the timetable for the audit, health checks and multi-level systems check be noted. Background On 21 February 2024 Full Council, on the recommendation of Cabinet, commissioned an independent review of the temporary closing of the Centres for the Community in November 2023.
The review will be managed by an independent audit organisation called Orbis IA. The Orbis IA is a Public Sector Partnership between Surrey County Council, East Sussex County Council and Brighton and Hove City Council. The partnership is a leading public sector provider of high-quality audit and counter fraud services whose services the Council employs for such purposes.
The review will provide reassurance to our centre users, employees, volunteers, hirers, Councillors, and residents. It will ensure that all strategic and operational risks have been identified and control measures embedded.
The review is comprised of three elements.
1. The Strategic Director to produce an initial report to the first Cabinet meeting in the new Municipal Year highlighting the issues encountered.
2. Orbis lA undertake an independent and robust in-depth audit, and this be reported to the Audit and Standards Committee upon completion.
3. The Council’s Risk Management Partners undertake a series of health checks and multi-level assessments to critically examine the Council’s systems focusing on the Health and Safety approach of ‘Plan, Do, Check and Act’.
The review will also consider the 2020 internal audit report and any necessary actions leading from the report.
Safety concerns
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
List of actions taken to reopen centre /24Appendix A | 3 pages | Download |
PDF |
Community Service Initial Findings ReportReport | 8 pages | DownloadRead as text |
Follow Cabinet at Elmbridge and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 27 Oct 2026 | Old Post Office EsherView the decision text for item 22/26 | Decided | Open |
| 16 Sep 2026 | Disposal of land in Oaken Lane, Claygate, EsherView the decision text for item 15/26 | Decided | Open |
| 16 Sep 2026 | Water Play Strategy UpdateView the decision text for item 16/26 | Decided | Open |
| 16 Sep 2026 | Elmbridge Local Plan 2039: Notice of commencement of plan-making and Local Plan timetableView the decision text for item 17/26 | Decided | Open |
| 16 Sep 2026 | 2026/27 Revenue and Capital Budget Update - Quarter 1View the decision text for item 19/26 | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.