The future of the Civic Centre site is an integral part of our placemaking plans for Esher town centre, as set out in Elmbridge’s 2030 Vision. The aim is to ensure that our civic presence in Esher delivers services and facilities for residents, visitors, councillors, and employees efficiently and effectively, in a way that is modern, affordable and sustainable.
This report provides an update on the progress of the project; focused on the review of the project objectives and the next steps required to bring together the workstreams to support the completion of the Outline Business Case. It also sets out a high-level framework for how communication and engagement will be approached as the project develops.
Recommended: that
(a) Cabinet approves the updated Civic Centre Project Objectives, to fully reflect all the options for the future of the Civic Centre site.
(b) Cabinet recommends to Council the funding of £110,000 required to continue to progress the business case and associated supporting work, the outcome of which will be presented to Cabinet in November 2024, to be funded from the Business Rates Equalisation Reserve.
Report:
Since early 2022, work has been ongoing on the project to identify and refine options for the Council’s future accommodation and the development of the wider site. Initial feasibility work was undertaken by Urban Vision, the outcome of this was presented to Cabinet in November 2023. This recommended two primary options be taken forward for further review; refurbishment of the existing Civic Centre; or demolition and re-build of a new, smaller Civic Centre on the same site. In August 2023, consultancy firm 31ten were appointed to provide advice on how the project might be funded and delivered. The development of the Civic Centre project objectives was a key initial output of their commission, and these objectives, approved by Cabinet in November 2023, were used as the basis for the scoring criteria in the subsequent options appraisal report produced in January 2024.
In January 2024, an additional option was introduced – an acquisition of, and relocation to, an alternative office building located in Esher. This potential site was appraised by 31ten in February 2024 using the same criteria as the earlier options.
The options appraisal demonstrated the existing Civic Centre accommodation should not be refurbished and both the new build office and the alternative office building located in Esher should be further explored. The appraisal also identified a 50/50 corporate Joint Venture as the preferred delivery route for the Civic Centre site, however it recommended this be further explored in the next stages of the project.
Since Spring 2024, the Council has been looking at the suitability of the alternative office building for its future office accommodation and engaging in commercial discussions.
Alongside the addition of a new option, there has been change in the Leadership of the Council since the project objectives were first agreed. In this context, officers considered it appropriate to undertake a review with Cabinet, of the Civic Centre project objectives to ensure they are still fit-for-purpose, to underpin the decision making on the project.
Updated Civic Centre Project Objectives
Following a recent workshop with Cabinet Members, the current six project objectives were reviewed, and possible additional objectives were discussed. The objectives have now been updated and are presented to Cabinet for consideration and approval:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Civic CentreReport | 6 pages | DownloadRead as text |
Follow Cabinet at Elmbridge and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 27 Oct 2026 | Old Post Office EsherView the decision text for item 22/26 | Decided | Open |
| 16 Sep 2026 | Disposal of land in Oaken Lane, Claygate, EsherView the decision text for item 15/26 | Decided | Open |
| 16 Sep 2026 | Water Play Strategy UpdateView the decision text for item 16/26 | Decided | Open |
| 16 Sep 2026 | Elmbridge Local Plan 2039: Notice of commencement of plan-making and Local Plan timetableView the decision text for item 17/26 | Decided | Open |
| 16 Sep 2026 | 2026/27 Revenue and Capital Budget Update - Quarter 1View the decision text for item 19/26 | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.