Elmbridge Borough Council
Cabinet, Wednesday 19 November 2025 at 7.00pm

Award of next phase of electric vehicle charging within pay and display car parks

Decided Executive 1 paper

AI summaryElmbridge Borough Council Cabinet approved a £140,000 funding increase and a contract award to Joju Limited for electric vehicle charging at seven pay and display car parks, taking the project total to £370,000.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedJoju Limited will deliver chargers at seven council car parks.
Money£140,000Total project cost: £370,000. Existing provision: £230,000.
What happens nextContract document approval and deliveryLegal and service teams will review the contract documents.
Who it affectsSeven council car parksResidents without off street parking or home charging.

What was decided

Cabinet approved a supplementary capital estimate of £140,000. Funding comes from £12,000 from the SCC Empty Property Grant and £128,000 from the Climate Change Reserve. Report P4, P5

Cabinet approved awarding the delivery contract to Joju Limited through Fusion21 framework Lot 8, covering Heating, Renewables and Electricals, for charging at the selected pay and display car parks. Report P6

Cabinet authorised the increased expenditure and entry into the contract. The revised project budget is £370,000. Report P2, P33

Why

The scheme gives residents without off street parking access to charging where they cannot charge at home. Report P1, P7, P35

UKPN quotations increased costs because new electrical supplies must be brought in over long distances, especially at Ashley Road and Halfway. Report P10, P25

Joju delivered the first phase, so its quality and deliverability are known. The award also keeps continuity of the existing charging software and payment app. Report P17

What happens next

The Asset Management and Property Services team and legal services will review and approve all contract documents. This includes payment milestones, warranties, liability, insurance, health and safety, and performance guarantees. Report P32

Robust project management, clear contracts and early engagement with UKPN will help manage delays to electrical connections. Report P36

Construction will use site safety plans, signage and liaison with the public. Clear information will cover access changes, charging availability and expected completion dates, with routine maintenance and safety checks after installation. Report P38, P39, P40

The money

  • £370,000.00 Total project cost, including site costs and contingency. Report P14
  • £140,000 Additional funding required as supplementary capital. Report P22
  • £12,000 SCC Empty Property Grant contribution. Report P22
  • £128,000 Climate Change Reserve contribution. Report P22
  • £230,000 Existing budget provision. Report P21
  • £336,247.19 Subtotal for seven sites: Walton Road Car Park £28,359.43; Mayfield Road £35,110.24; Ashley Road Car Park £106,299.69; Hare Lane £31,518.13; Highwayman’s Cottage £25,461.80; Halfway £70,972.23; Station Avenue £38,525.67. Report P12, P13
  • £33,752.81 Contingency of circa 10%. Report P11, P13
  • 3.5% Fusion21 framework access and contract management fee included in the project cost. Report P18

Options considered

  • Chosen: Proceed with increased expenditure and a £370,000 revised budget. Formal UKPN quotations showed that new electrical supplies cost more, particularly at Ashley Road and Halfway. Report P2, P10, P14, P25
  • Chosen: Award the contract to Joju Limited through Fusion21 Lot 8. Fusion21 follows public procurement requirements. Joju delivered the first phase, so quality and deliverability are known, and the award maintains continuity of the existing software and payment app. Report P16, P17, P31

Implications

  • Financial: The revised project budget is £370,000, made up of the existing £230,000 provision and £140,000 additional funding. Report P20, P21, P22
  • Financial: The project cost includes a 3.5% Fusion21 framework access and contract management fee. Report P18
  • Legal: Fusion21 was procured under the Public Contracts Regulations 2015, and the direct award follows council contract standing orders. Legal services and the Asset Management and Property Services team will review all contract documents. Report P31, P32
  • Climate: The scheme supports the council's carbon neutrality goal for 2030, reduces local emissions and encourages a shift away from fossil fuels. Report P26, P27, P28
  • Equalities: Locating chargers in publicly accessible car parks supports equitable access for residents across the borough who lack off street parking or home charging. Report P35
  • Risk: Delays in UKPN connections could affect the project timetable. Construction may temporarily affect car park users, while warranties, maintenance and defects create long term contractual risks. Report P36, P37, P38
  • Risk: Public car park works will follow health and safety legislation and electrical safety standards, with site safety plans, signage and public liaison. Report P38
  • Other: The procurement approach includes social value through local employment, apprenticeships and community benefits. Report P29, P30

Who and where

  • Ashley Road car park, Thames Ditton Report P8
  • Halfway car park, Walton Report P8
  • Hare Lane car park, Claygate Report P8
  • Highwayman’s Cottage car park, Esher Report P8
  • Mayfield Road car park, Hersham Report P8
  • Station Avenue car park, Walton Report P8
  • Walton Road car park, East Molesey Report P8
  • Residents without off street parking or home charging Report P35

Timeline

  • February 2025: An initial capital bid of £230,000 was approved and later funded through an SCC Empty Property Grant application. Report P1, P7
  • Since the initial capital bid: UKPN surveys and quotations produced higher electrical supply costs, leading to the revised £370,000 budget. Report P10, P11, P14
  • During construction: Works may temporarily affect public car park users, with site safety plans, signage and liaison in place. Report P38
  • Post-installation: Charging points will receive routine maintenance and safety checks. Report P40
  • 2030: The council's stated carbon neutrality target is supported by the charging scheme. Report P26

Plain English for the jargon

  • Electric vehicle charging: Providing electricity to charge electric vehicles at the selected public car parks.
  • Pay and display car parks: Council owned car parks included in this charging phase.
  • UK Power Networks: The company providing new electrical supplies and carrying out statutory site surveys.
  • Fusion21: A procurement framework for Heating, Renewables and Electricals, Lot 8.
  • Joju Limited: The first phase installer and selected contractor for the next phase.
  • SCC Empty Property Grant: A grant source contributing to the project funding.
  • Climate Change Reserve: A reserve funding source contributing to the project.
  • Supplementary capital: Additional money added to the approved project budget.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item25/25

Resolved

View the decision text for item 25/25
Word for word from the decision Elmbridge published for this meeting. Source: mygov.elmbridge.gov.uk

Follow this further

Built from Elmbridge's papers

What the report saysPro

Report to Cabinet, 5 pages

Executive summary

The council previously approved an initial capital bid of £230,000 (February 2025 Cabinet) for the next phase of electric vehicle (EV) charging facilities in our pay-and- display (P&D) car parks. The project supports residents to access EV charging infrastructure within our car parks where they cannot access EV charging at home.

Since the initial capital bid, the estimated project costs have increased, mainly due to obtaining formalised quotations for bringing in new electrical supplies to the car parks from UK Power Networks (UKPN). As a result, the revised project budget now totals £370,000. Approval is therefore being sought to proceed with the increased expenditure and enter into contract with Joju Limited (Joju) for delivery of the scheme via the Fusion21 Framework.

Recommended: that

(a) Cabinet approves a supplementary capital estimate of £140,000 for the EV charging installations funded by:

 £12,000 from the SCC Empty Property Grant  £128,000 from the Climate Change Reserve

(b) Cabinet approves the award of a contract to Joju Limited via the Fusion21 framework (Lot 8) for Heating, Renewables and Electricals for the delivery of the next phase of EV charging installation at the identified P&D car parks. Background:

An initial capital bid of £230,000 was approved in February 2025 (and subsequently funded through a SCC Empty Property Grant application) for the next phase of EV charging facilities within the council’s P&D car parks. Unlike the council’s previous schemes where EV chargers were installed at the council’s main operational sites and town centre car parks, this phase aims to provide EV charging within our council- owned car parks where surrounding residential properties do not have off-street parking and cannot charge outside of their homes. As a result, the following car parks were identified as suitable locations for the relevant demographics:

 Ashley Road (Thames Ditton)  Halfway (Walton)  Hare Lane (Claygate)  Highwayman’s Cottage (Esher)  Mayfield Road (Hersham)  Station Avenue (Walton)  Walton Road (East Molesey)

Cost update:

The capital bid was based on previous install costs delivered under the same proposed framework; however, it was subject to UKPN’s statutory site-specific surveys. Since the initial budget approval, UKPN’s quotations have been obtained and have exceeded initial cost expectations due to the distance involved in bringing in new electrical supplies to the car parks (significantly at Ashley Road in Thames Ditton and Halfway in Walton).

The updated project cost is £370,000 (including a circa 10% contingency of £33,752.81), with cost breakdown per site as follows:

P&D car park Updated EVC costings Walton Road Car Park £28,359.43 Mayfield Road £35,110.24 Ashley Road Car Park £106,299.69 Hare Lane £31,518.13 Highwayman’s Cottage £25,461.80 Halfway £70,972.23 Station Avenue £38,525.67

Sub Total £336,247.19 Contingency (circa 10%) £33,752.81

Total £370,000.00 Procurement route:

Permission is being sought from Cabinet to enter into contract with Joju Limited for delivery of the project through Fusion21’s framework for Heating, Renewables and Electricals (Lot 8).

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Award of next phase of electric vehicle charging within pay and display car parksReport 5 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 17 attended
MR
Councillor Mike RollingsLeader, present
SW
Councillor Simon WaughDeputy Leader, present
AB
Councillor Alex BatchelorCommittee Member, present
GC
Councillor Gill CoatesCommittee Member, present
KH
Councillor Kirsty HewensCommittee Member, present
CJ
Councillor Caroline JamesCommittee Member, present
JL
Councillor Jez LanghamCommittee Member, present
AT
Councillor Ashley TillingCommittee Member, present
AM
Councillor Alistair MannGuest, in attendance
AC
Adam ChalmersOfficer, in attendance
AC
Andrew CooperOfficer, in attendance
DC
Dawn CreweOfficer, in attendance

All 17 on the meeting page

More from Elmbridge Cabinet

All decisions
MeetingDecisionOutcome
27 Oct 2026 Old Post Office EsherView the decision text for item 22/26 Decided Open
16 Sep 2026 Disposal of land in Oaken Lane, Claygate, EsherView the decision text for item 15/26 Decided Open
16 Sep 2026 Water Play Strategy UpdateView the decision text for item 16/26 Decided Open
16 Sep 2026 Elmbridge Local Plan 2039: Notice of commencement of plan-making and Local Plan timetableView the decision text for item 17/26 Decided Open
16 Sep 2026 2026/27 Revenue and Capital Budget Update - Quarter 1View the decision text for item 19/26 Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies