AI summaryElmbridge Borough Council Cabinet approved a £140,000 funding increase and a contract award to Joju Limited for electric vehicle charging at seven pay and display car parks, taking the project total to £370,000.
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Resolved
View the decision text for item 25/25
The council previously approved an initial capital bid of £230,000 (February 2025 Cabinet) for the next phase of electric vehicle (EV) charging facilities in our pay-and- display (P&D) car parks. The project supports residents to access EV charging infrastructure within our car parks where they cannot access EV charging at home.
Since the initial capital bid, the estimated project costs have increased, mainly due to obtaining formalised quotations for bringing in new electrical supplies to the car parks from UK Power Networks (UKPN). As a result, the revised project budget now totals £370,000. Approval is therefore being sought to proceed with the increased expenditure and enter into contract with Joju Limited (Joju) for delivery of the scheme via the Fusion21 Framework.
Recommended: that
(a) Cabinet approves a supplementary capital estimate of £140,000 for the EV charging installations funded by:
£12,000 from the SCC Empty Property Grant £128,000 from the Climate Change Reserve
(b) Cabinet approves the award of a contract to Joju Limited via the Fusion21 framework (Lot 8) for Heating, Renewables and Electricals for the delivery of the next phase of EV charging installation at the identified P&D car parks. Background:
An initial capital bid of £230,000 was approved in February 2025 (and subsequently funded through a SCC Empty Property Grant application) for the next phase of EV charging facilities within the council’s P&D car parks. Unlike the council’s previous schemes where EV chargers were installed at the council’s main operational sites and town centre car parks, this phase aims to provide EV charging within our council- owned car parks where surrounding residential properties do not have off-street parking and cannot charge outside of their homes. As a result, the following car parks were identified as suitable locations for the relevant demographics:
Ashley Road (Thames Ditton) Halfway (Walton) Hare Lane (Claygate) Highwayman’s Cottage (Esher) Mayfield Road (Hersham) Station Avenue (Walton) Walton Road (East Molesey)
Cost update:
The capital bid was based on previous install costs delivered under the same proposed framework; however, it was subject to UKPN’s statutory site-specific surveys. Since the initial budget approval, UKPN’s quotations have been obtained and have exceeded initial cost expectations due to the distance involved in bringing in new electrical supplies to the car parks (significantly at Ashley Road in Thames Ditton and Halfway in Walton).
The updated project cost is £370,000 (including a circa 10% contingency of £33,752.81), with cost breakdown per site as follows:
P&D car park Updated EVC costings Walton Road Car Park £28,359.43 Mayfield Road £35,110.24 Ashley Road Car Park £106,299.69 Hare Lane £31,518.13 Highwayman’s Cottage £25,461.80 Halfway £70,972.23 Station Avenue £38,525.67
Sub Total £336,247.19 Contingency (circa 10%) £33,752.81
Total £370,000.00 Procurement route:
Permission is being sought from Cabinet to enter into contract with Joju Limited for delivery of the project through Fusion21’s framework for Heating, Renewables and Electricals (Lot 8).
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Award of next phase of electric vehicle charging within pay and display car parksReport | 5 pages | DownloadRead as text |
Follow Cabinet at Elmbridge and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 27 Oct 2026 | Old Post Office EsherView the decision text for item 22/26 | Decided | Open |
| 16 Sep 2026 | Disposal of land in Oaken Lane, Claygate, EsherView the decision text for item 15/26 | Decided | Open |
| 16 Sep 2026 | Water Play Strategy UpdateView the decision text for item 16/26 | Decided | Open |
| 16 Sep 2026 | Elmbridge Local Plan 2039: Notice of commencement of plan-making and Local Plan timetableView the decision text for item 17/26 | Decided | Open |
| 16 Sep 2026 | 2026/27 Revenue and Capital Budget Update - Quarter 1View the decision text for item 19/26 | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.