Managed Datacentre Contract

Decided Executive 1 paper

AI summaryElmbridge Cabinet approves move to a fully managed cloud service run by Eloquent Technologies, at £170,000 a year, replacing the 2016 server estate ahead of local government reorganisation in April 2027.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedTwo year term plus optional one year extension
Money£517,750 total£170,000 a year, plus £5,000 setup
What happens nextFinalise contract documentsStrategic Director of Services to execute
Who it affectsCouncil IT infrastructureInternal systems supporting all services

What was decided

Cabinet approved procurement of managed cloud hosted infrastructure services from Eloquent Technologies for an initial two year term, with a one year extension option, at £170,000 per year, covered by the approved annual revenue budget, with a total contracted cost of £517,750. Report P6, P18, P19

Authority was delegated to the Strategic Director of Services to finalise and execute all necessary contract documentation. Report P7

Why

The 2016 server hardware has reached end of support, with no replacement parts available, security patching stopped, and only high cost unsupported bespoke arrangements left, creating an unsustainable operational and security risk. Report P2, P11, P12, P13, P14, P23

Officers preferred a managed cloud service over a like for like hardware refresh because it fits the council's cloud first strategy, avoids capital spend that would not transfer through local government reorganisation, and removes ongoing lifecycle and security risks of owning physical hardware. Report P3, P15, P16

What happens next

Procurement will be carried out through the Kent County Council framework, avoiding a separate tender exercise. Report P21

Hardware decommissioning will follow the council's secure disposal procedures, including certified data sanitisation and responsible recycling. Report P20

The contract length is deliberately matched to the local government reorganisation timetable, with vesting planned for April 2027. Report P4, P15, P27

The money

  • £170,000 per annum Annual charge, covered by the approved revenue budget, fixed for the contract term Report P6, P18, P29
  • £5,000 One off setup fee Report P18, P19
  • £14,243.04 per month Monthly charge over the two year term Report P18, P19
  • £517,750 Total contracted cost including the extension year, as set out in the recommendation Report P6
  • £517,749.44 Total cost as calculated in the financial implications section Report P19

Options considered

  • Chosen: Migrate to Eloquent Technologies fully managed cloud infrastructure service. Aligns with cloud first strategy, avoids capital investment, preserves resilience and business continuity, removes lifecycle and security risks, builds on Eloquent's existing knowledge, and fits the local government reorganisation timetable Report P3, P15, P16
  • Rejected: Like for like hardware refresh of the existing datacentre set up. Would require significant capital investment in physical assets whose value would not transfer cleanly to the successor unitary authority through local government reorganisation Report P3, P15, P16, P18

Implications

  • Financial: Cost is covered by the existing annual revenue budget, with annual pricing fixed at £170,000, avoiding capital expenditure that would not be recoverable through local government reorganisation. Report P6, P18, P29
  • Risk: Continuing with the current unsupported hardware would leave the council exposed to security incidents, prolonged outages and disproportionate remediation costs. Report P23, P25
  • Legal: Procurement through the Kent County Council framework is compliant with the Public Contracts Regulations and the council's Contract Standing Orders, with the Legal Team supporting contract completion and no identified legal risks. Report P21
  • Equalities: None identified, as the contract covers internal infrastructure and will not change how residents access or experience council services. Report P22
  • Climate: Managed cloud services typically deliver lower energy use per unit of compute than legacy on premises infrastructure, and the existing hardware will be securely disposed and recycled. Report P20

Who and where

  • Elmbridge Borough Council ICT service and all users of its internal systems Report P2, P16
  • Residents, whose access to council services depends on the underlying infrastructure during the local government reorganisation transition Report P16
  • The successor unitary authority that takes over after local government reorganisation, with vesting planned for April 2027 Report P16, P27

Timeline

  • 2016: Council relocated its server hardware estate to an offsite datacentre, with Eloquent Technologies Ltd appointed to deliver cloud network, backup and storage services Report P9, P10
  • Two year initial term from contract start: Managed cloud hosted infrastructure services delivered by Eloquent Technologies Report P4, P6
  • Optional one year extension: Continued service if exercised, taking the contract up to three years in total Report P4, P6
  • April 2027: Local government reorganisation vesting date, which the contract length is matched to Report P15, P27

Plain English for the jargon

  • LGR: Local Government Reorganisation, the structural reform that will replace Elmbridge with a new unitary authority, with vesting planned for April 2027
  • Cloud first strategy: The council's adopted policy preference for using cloud hosted services rather than owning physical on premises hardware
  • KCC framework: Kent County Council framework agreement, the established procurement vehicle the council will use to buy the service without running a separate tender
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item70/25

Resolved

View the decision text for item 70/25
Word for word from the decision Elmbridge published for this meeting. Source: mygov.elmbridge.gov.uk

Follow this further

Built from Elmbridge's papers

What the report saysPro

Report to Cabinet, 4 pages

Executive summary

This report seeks Cabinet approval to procure a managed cloud-hosted infrastructure service to replace the council’s existing server estate.

The current infrastructure was implemented in 2016, with hardware procured and owned by the council and hosted within an offsite datacentre, supported by Eloquent Technologies for cloud network, backup and storage services. This hardware has now reached end of support. Replacement parts are no longer available, manufacturer security updates have ceased, and ongoing support is limited to high-cost, non- guaranteed arrangements. Continued reliance on the current platform presents an unsustainable operational and security risk.

Following an options appraisal, migration to Eloquent Technologies fully managed cloud infrastructure service is recommended in place of a like-for-like hardware refresh. This approach aligns with the council’s cloud-first strategy, avoids further capital investment in physical assets that would not transfer effectively through Local Government Reorganisation (LGR), retains existing resilience and business continuity benefits, and removes lifecycle and security risks associated with continued ownership of on-premise hardware.

The proposed contract term is two years, with an optional one-year extension, ensuring continuity of ICT infrastructure services beyond April 2027.

Recommended: that Cabinet

(a) Approves the procurement of managed cloud-hosted infrastructure services for an initial two-year term with a one-year extension option, at an annual cost of £170,000 which is covered by the approved annual revenue budget. The total contracted cost with the extension will be £517,750.

(b) Delegates authority to the Strategic Director of Services, to finalise and execute all necessary documentation required to enact the contract.

1 OFFICIAL OFFICIAL

Background

In 2016 the council relocated its server hardware estate to an offsite datacentre. This decision was driven by three objectives that remain valid: improved business continuity through geographic separation, access to 24/7 supported infrastructure, and enhanced resilience alongside reduced operating costs.

At that time, the hardware within the datacentre was procured, owned and maintained by Elmbridge, with Eloquent Technologies Ltd appointed to deliver cloud network, backup and storage services. Eloquent has therefore developed a strong understanding of the council’s infrastructure environment over an extended period of service delivery.

The hardware procured in 2016 has now reached the end of its operational life and cannot be safely or economically sustained:

• Manufacturer support has ended. • Repair and replacement parts are no longer available.

• Bespoke support is only available at disproportionate cost and without service guarantees.

• Security patching has ceased, creating increasing information security risk.

Officers considered two viable options: a like-for-like hardware refresh, or migration to Eloquent Technologies fully managed cloud infrastructure service. Both were assessed against the council’s cloud-first strategy and the Local Government Reorganisation (LGR) timetable, with vesting in April 2027.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Managed Datacentre ContractReport 4 pages DownloadRead as text

At this meeting

Whole meeting

More from Elmbridge Cabinet

All decisions
MeetingDecisionOutcome
27 Oct 2026 Old Post Office EsherView the decision text for item 22/26 Decided Open
16 Sep 2026 Disposal of land in Oaken Lane, Claygate, EsherView the decision text for item 15/26 Decided Open
16 Sep 2026 Water Play Strategy UpdateView the decision text for item 16/26 Decided Open
16 Sep 2026 Elmbridge Local Plan 2039: Notice of commencement of plan-making and Local Plan timetableView the decision text for item 17/26 Decided Open
16 Sep 2026 2026/27 Revenue and Capital Budget Update - Quarter 1View the decision text for item 19/26 Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies