Resolved
View the decision text for item 41/E
AI summaryEast Surrey Shadow Executive approves Woodhatch Place in Reigate as the Day 1 headquarters for the new East Surrey Council, with running costs of £2.75m per year. Existing local services and staff locations will continue.
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Resolved
View the decision text for item 41/E
To present the Property Workstream’s options appraisal for Day 1 HQ accommodation for East Surrey Council and seek approval of the preferred accommodation arrangement to support Vesting Day.
The report is intended to provide clarity for Members, staff and residents on the proposed Day 1 corporate base for the new authority. It does not determine the future location of all staff or the longer-term shape of the East Surrey estate. This represents the first stage of accommodation planning, with further review required following Vesting Day once the new Council’s service delivery model, workforce requirements, operating arrangements and strategic priorities are confirmed.
It is recommended that the East Surrey Shadow Executive resolves to:
1. Approve Woodhatch Place, 11, Cockshot Hill, Reigate RH2 8EF as the preferred Day 1 Headquarters for the new East Surrey Council;
2. Approve progression of the preferred option into detailed implementation and mobilisation planning to support operational readiness for Vesting Day; and
3. Delegate authority to the Chief Executive, in consultation with the Portfolio Holder, Chief Finance Officer and Monitoring Officer, to approve any minor operational amendments necessary to implement the approved Day 1 accommodation arrangements, provided these do not materially alter the approved recommendation.
1. Woodhatch Place provides the strongest overall fit against the agreed Day 1 requirements and offers a deliverable, operationally resilient and cost-effective solution for East Surrey Council’s headquarters from Vesting Day.
2. The recommendation will support continuity of services and effective democratic governance for East Surrey residents, while allowing the new Council to
1 OFFICIAL
determine its longer-term accommodation and estate strategy following Vesting Day.
Options, including alternatives (if any)
1. The following high-level options were considered for East Surrey Council’s Day 1 headquarters and civic accommodation:
Woodhatch Place - Recommended - Designate Woodhatch Place as the principal HQ and Civic Centre from Vesting Day.
Alternative shortlisted property - Select another property identified through the shortlist and options appraisal as the principal HQ and Civic Centre.
Alternative existing property within the East Surrey estate - Identify and assess another existing property outside the shortlist for use as the principal HQ and Civic Centre.
Split HQ and Civic functions across different locations - Provide the principal corporate headquarters and civic/democratic functions from separate buildings within the East Surrey estate.
Dispersed / campus model - Operate corporate, democratic and civic functions across a number of smaller existing locations without establishing a single combined HQ and Civic Centre.
Secure additional accommodation - Lease, hire or otherwise secure additional accommodation outside the existing estate to meet the Day 1 HQ and/or civic requirement.
2. The options above, including the reasons for progressing or discounting them, and the detailed appraisal of the shortlisted properties, are set out further in the report.
1. As part of Local Government Reorganisation, East Surrey requires suitable Headquarters and Civic accommodation to enable the new authority to operate safely and lawfully from Vesting Day.
2. Section 16 of the Local Government and Public Involvement in Health Act 2007, together with the Local Government (Structural Changes) (Transfer of Functions, Property, Rights and Liabilities) Regulations 2008, provides the framework for the transfer and vesting of assets, rights and liabilities arising from local government reorganisation.
2 OFFICIAL
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Option Appraisal Pack /EAppendix 1 | 1.7 MB | Download |
PDF |
East Surrey Day 1 Headquarters (HQ)Report | 502 KB | DownloadRead as text |
PDF |
Supplementary Information: O&S Minute Extract: East Surrey Day 1 Headquarters (HQ) /ESupplementary | 208 KB | Download |
Follow East Surrey Shadow Authority Executive at Elmbridge and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 9 Nov 2026 | Implementation Programme UpdateView the decision text for item 6. | Decided | Open |
| 9 Nov 2026 | 2026/27 Quarter 1 Budget Monitoring Report of Existing East Surrey CouncilsView the decision text for item 7. | Decided | Open |
| 9 Nov 2026 | Strategic PartnershipsView the decision text for item 8. | Decided | Open |
| 9 Nov 2026 | Equality Diversity and Inclusion ApproachView the decision text for item 9. | Decided | Open |
| 9 Nov 2026 | Performance Management ApproachView the decision text for item 10. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.