Resolved
View the decision text for item 36/E
AI summaryEast Surrey Shadow Executive noted progress on local government reorganisation, with £32.546m committed from the Implementation Fund, 39 of 104 critical milestones complete, and overall delivery confidence rated amber.
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Resolved
View the decision text for item 36/E
The East Surrey Shadow Authority Executive agreed an approach to Local Government Reorganisation (LGR) programme monitoring and assurance on 9 June 2026. This report sets out the latest position in line with that approach. Also included are the updates on programme risks against critical milestones, top programme risks and the latest position related to the implementation fund.
The Shadow Executive is, jointly with the West Shadow Executive, responsible for keeping under review, and revising as necessary, the Implementation Plan for local government reorganisation in Surrey1 and managing the overall Transition Programme. Recommendations are made to the Shadow Executive for arrangements to support these functions.
It is recommended that the East Surrey Shadow Executive resolves to:
1. Note progress against critical milestones and the overall programme assurance position
2. Note the current programme risk profile and highest scoring risks
3. Note the latest Implementation Fund position.
1. Under the Shadow Authority’s Constitution, the Shadow Executive is responsible for overseeing and managing the transition programme, including maintaining the Implementation Plan and taking the key executive decisions needed to
1 Future Surrey - Implementation Plan -
https://www.surreylgrhub.gov.uk/downloads/file/18/implementation-plan-05-26
OFFICIAL OFFICIAL
establish the new council. Agreeing the recommendations in this report will support the Shadow Executive to discharge these functions.
2. The Shadow Executive will receive regular programme updates providing assurance on overall delivery and highlighting areas requiring direction or decision.
Options, including alternatives (if any)
3. The Surrey (Structural Changes) Order 2026 (SCO) requires the Shadow Authority to keep the Implementation Plan under review and, as set out above, the Constitution confirms the role the Shadow Executive has in this. Whilst the Shadow Executive could choose not to accept the recommendations this could hinder their ability to discharge these functions and risks inconsistency in reporting and reduced public confidence in the transition process.
4. Overall, the programme continues to make progress against key milestones set out in the Implementation Plan; however, the pace and complexity of the programme together with the high number of decisions required to be taken and are beginning to impact the risk profile and will require close management over the coming months.
Progress and Programme Assurance
5. The programme remains on track against its critical path to Vesting Day, with several key enabling milestones delivered since the previous meeting (listed below). However, there remain significant risks related to programme delivery, and delivery confidence is increasingly dependent timely Member decisions and maintaining pace across interdependent themes, particularly IT & data, workforce, and governance.
6. The Implementation Team continues to track progress against critical milestones. Since the previous meeting of the Shadow Executive in July, and at the time of publishing this report, the following milestones have been completed:
Milestone 1. Contract vesting options agreed by Services 2. East Surrey - Interim Draft Corporate Strategy Developed and submitted to Shadow Executive 3. West Surrey - Approach to developing Corporate Strategy reviewed by Shadow Executive and date for completion agreed 4. Service Configurations considered by West/East Surrey Shadow Executives (July) 5. Consultation process agreed with unions
OFFICIAL OFFICIAL
6. East Surrey - Permanent Chief Executive recruited
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Programme Progress & Assurance Update /EAppendix 1 | 693 KB | Download |
PDF |
Risk Update /EAppendix 2 | 375 KB | Download |
PDF |
Implementation Programme UpdateReport | 642 KB | DownloadRead as text |
Follow East Surrey Shadow Authority Executive at Elmbridge and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 19 Nov 2026 | Consenting to the Formation of a Foundation Strategic Authority for SurreyView the decision text for item 3. | Decided | Open |
| 19 Nov 2026 | Appointment of Electoral Appointee for East SurreyView the decision text for item 4. | Decided | Open |
| 9 Nov 2026 | Implementation Programme UpdateView the decision text for item 77/E | Decided | Open |
| 9 Nov 2026 | 2026/27 Quarter 1 Budget Monitoring Report of Existing East Surrey CouncilsView the decision text for item 78/E | Decided | Open |
| 9 Nov 2026 | Strategic PartnershipsView the decision text for item 79/E | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.