The Committee: · Noted the annual report prepared by the London Borough of Sutton in respect of the new insurance arrangements and continues action taken to improve the handling of claims; · Agreed that the Head of Corporate Risk progress discussions with the London Borough of Sutton for a longer term arrangement to achieve potential savings and economies of scale with a view to extending the current Collaboration Agreement.
Word for word from the decision Epsom and Ewell published for this meeting.Source: democracy.epsom-ewell.gov.uk
2.1Strategy and Resources Committee gave approval to the transfer of insurance cover to the London Borough of Sutton on the 26 June 2012 due to Zurich Municipal breaking the long term agreement with a proposed 32% increase in premiums. STRATEGY & RESOURCES COMMITTEE 17 NOVEMBER 2015
2.2London Borough of Sutton has dedicated teams who provide administrative and technical support. The partnership arrangement has now been in place for over 3 years. There are regular reviews of performance and they offer a bespoke, direct, claims service which is also focused on the needs of the residents and which is more robust and resilient. They provide:-
Integrated insurance services
Proactive claims handling service
A single point of contact
Provision of training and support to services to mitigate risk
Provision of specialist advice and guidance
2.3The London Borough of Sutton has also provided a run off service by handling all claims prior to 1 July 2012. There are currently 19 mature open claims with an outstanding estimate of in the region of £475,000. These relate to complex public liability claims.
2.4From April 2014, the London Borough of Sutton also provides insurance arrangements for Surrey Heath Borough Council and is actively seeking to work with other Boroughs.
3 Annual Review of Insurance
3.1The London Borough of Sutton has provided an Annual Claims Report which is attached as an Annexe to this report.
3.2The arrangement continues to work well. The Insurance Team provide a single point of contact for Council staff and claimants. A key philosophy to London Borough of Sutton’s claims handling is to make early decisions on liability which reduces legal costs. They have recently reduced the time to investigate all EL claims to 30 days and PL claims to 40 days in line with the on line portal introduced from the Jackson Reforms.
3.3The fire at Ewell Court House in December 2013 has resulted in a substantial insurance claim currently reserved at over £2 million. The reinstatement is moving into the final stages, with finishing touches being agreed. Watts (the project managers) have confirmed the project in on target for completion and works should be finished by 30 October 2015. The opening ceremony has been scheduled for 12 November 2015, to re-launch the venue. STRATEGY & RESOURCES COMMITTEE 17 NOVEMBER 2015
3.4Key improvements and key performance indicators:
Year The level of self-funding (EEBC) requirements/outstanding reserve (£) 1 July 2012 416,000.00 31 March 2013 301,561.97 31 March 2014 167,289.90 31 March 2015 146,819.32
At the end of September 2015 , there were 106 open claims
100% compliance to the relevant Pre-Action Protocols this financial year
All requests for technical advice are dealt with quickly
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Strategy and Resources Committee at Epsom and Ewell and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.