The Committee agreed: (1) To submit the Capital Programme for 2016/17 as identified in section 4 of the report to Council for approval on 11 February 2016; (2) To confirm that it supported all of the schemes included in the provisional programme for 2017-19 as identified in section 5 of the report The Committee: (3) Noted that schemes for 2017-19 were provisional pending an annual review of funds available for capital investment.
Word for word from the decision Epsom and Ewell published for this meeting.Source: democracy.epsom-ewell.gov.uk
2.1The Capital Strategy was last agreed by the Council on 17 February 2015 at which time the capital programme was approved for 2015/16. Schemes for 2016-2018 were provisional pending the annual budget review and an annual assessment of funds for capital investment.
2.2The Financial Policy Panel provided the Capital Member Group (CMG) with a remit to guide the preparation of a capital programme for 2016-17. The Panel received details of capital bids on 1 December 2015 following an assessment of investment options by the CMG.
2.3The Panel were advised that the proposed level of investment of £2.5 million over three years 2016/17 to 2018/19 would reduce the available capital reserves to £1.3 million at the end of this period. The proposed capital programme assumes funding from capital and revenue reserves, and government grants. Specific schemes may also be funded from other grants where successful bids are made.
2.4The Panel’s guidance relevant to this policy committee’s recommendations was as follows:-
2.4.1 Priority schemes identified by the Capital Member Group should be presented with project appraisals to the policy committees in January to establish whether there is support for the individual projects, with any projects not supported being removed from the draft programme.
2.4.2 There were no schemes identified in section 4 of this report for 2016/17.
3 Proposals
3.1The Committee is asked:-
3.1.1 To note the position for 2016/17;
3.1.2 To agree the provisional programme for 2017-19
3.2The timing of the programme should be based on the ability to deliver with a realistic number of projects in any one year.
3.3The budget assumes that interest earned on capital reserves will be used to help finance the revenue budget. STRATEGY AND RESOURCES COMMITTEE 27 JANUARY 2016
3.4If all schemes in the proposed corporate capital programme for 2016/17 were to progress this would reduce the capital reserves to around £2.1 million and as a result there will be reduced funding available for service delivery. This is reflected in next year’s estimates and the financial forecasts.
4 Core Programme 2016/17 Funded from Capital Reserves
4.1The Financial Policy Panel recommended that no schemes are put forward for this committee for 2016/17.
5 Proposed Capital Programme 2017/18 to 2018/19
5.1The provisional programme proposed for 2017-19 is:-
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Strategy and Resources Committee at Epsom and Ewell and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.