The Committee: (1) Received the end of year progress report on the backlog maintenance programme (2) Noted changes made to the programme under delegated authority (3) Approved the carry forward of all unspent monies and schemes as indicated in Annexe 1 to the report assuming there were sufficient funds within the General Fund at year end (4) Authorised Officers to make adjustments to the recommended programme, within the overall budget, as a result of improved estimates becoming available where adjustment is less than £20K
Word for word from the decision Epsom and Ewell published for this meeting.Source: democracy.epsom-ewell.gov.uk
2.1A mid-year progress report was presented to Financial Policy Panel in October 2015 which included changes to proposed schemes. These schemes are shown in Annexe 1. The changes were ratified by Strategy and Resources.
2.2Annexe 1 shows the 2015/16 current position and includes minor changes to scheme budgets as well as current and forecast spend on schemes.
2.3Due to financial restrictions minimal works have been carried over the past 6 months with the exception of emergency works of a Health & Safety nature. For example, the hard standing to the front of the Playhouse had become damaged by tree roots and works were carried out on an emergency basis prior to the Pantomime season commencing.
2.4Officers have delegated authority to make adjustments to schemes of up to £20,000 subject to the programme being completed within the approved budget. Since the reschedule of schemes referred to in 2.1 above, 4 additional schemes have been included in the programme as follows:
2.4.1 Minor improvements to reduce water consumption – leaks at the Town hall £5,439
2.4.2 Upgrade to intruder alarms – Town Hall, The Wells, Alexandra Recreation ground, King Georges Field, Gibraltar Recreation Ground, Auriol Pavilion, Horton Country Park £12,506
2.4.3 Path repairs – Alexandra Recreation ground £4,409
2.4.4 Relay uneven paving in front of the Playhouse - £7,166
3 Backlog schemes – 2015/16
3.1Annexe 1 contains the 2015/16 position of actual spend and forecast outturn for the current year schemes. A summary is shown at 4.1 below.
3.2A number of non-committed schemes were put “on hold” during the year in response to the requirement to limit non-essential spend across all services. It is proposed that these schemes will be carried into 2016/17. The total value of these is £127,000 and these are marked up as “To be carried over” on Annexe 1. These will be funded from drawdown from the property maintenance reserve assuming there are sufficient funds available within the General Fund at year end. STRATEGY AND RESOURCES COMMITTEE 5 APRIL 2016
3.3Works on some approved schemes are still in progress across the two financial years. A further drawdown form the property maintenance reserve will be made in 2016/17 to cover these remaining costs. The actual value of these will not be known until after the year end but is likely to be less than £20,000. Underspending from schemes which have either come in under budget or are not progressing will be transferred to and remain within the Property maintenance reserve.
4 Financial and Manpower Implications
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Strategy and Resources Committee at Epsom and Ewell and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.