The Committee agreed: (1) Not to make an additional contribution from the Community Infrastructure Levy (CIL) towards the cost of the Plan E Epsom Town Centre Highway and Public Realm Improvement Scheme; (2) That blockwork equivalent to the existing materials in the public realm, the cost of which could be afforded across the entire scheme within the established budget, be the material used for surfacing paths in various phased of the scheme and for surfacing the market place and other locations.
Word for word from the decision Epsom and Ewell published for this meeting.Source: democracy.epsom-ewell.gov.uk
2.1On 17 February 2015 Epsom & Ewell Borough Council agreed to increase its contributions to the Epsom Town Centre Highway and Public Realm Improvement Scheme. At that point the agreed funding was set out in the table below:
Original Revised £ £ Total Project Cost 2,700,000 3,375,000 Funded by Local Growth Funding – 80% (LEP) - 2,160,000 - 2,700,000 Economic Fund - SCC - 252,000 - 252,000 Capital Reserves - EEBC - 200,000 - 200,000 S106 - SCC - 88,000 -146,991 S106 - EEBC 0 - 28,984 CIL 0 - 47,025 Total Funding - 2,700,000 - 3,375,000
2.2The table shows that the Borough Council agreed to contribute an additional £76k in order to help secure a substantive additional grant from the Local Enterprise Partnership (LEP) amounting, with SCCs additional contribution, to a total increase of £675k in the funding available.
2.3It was anticipated that the uplift in funding could be used to enhance the specification for the Market Place and other areas of public realm.
2.4For the record, there was also an additional £400k in the reckoning which comprised a separate grant of £200k from the LEP and match funding of £200k from the Borough Council. This too, it was anticipated could be used for public realm improvements but had been originally agreed on the basis of works to the Quadrant Junction and not for the current scheme. Subsequently, the Borough Council withdrew that bid on 10 May 2016 due to the fact that it was dedicated to the Quadrant and the scheme for that junction was not well developed and would have been far more costly than the original estimates. For the sake of STRATEGY AND RESOURCES COMMITTEE 27JUNE 2017
clarity, therefore, the extra £400k referred to in the February 2015 report (though not included in the table above) was never really available for this project although the Borough Council’s CIL monies committed to that bid are still available to be used for other purposes.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Strategy and Resources Committee at Epsom and Ewell and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.