Resolved
The Committee agreed to write off the sum of £374,498.27
Strategy and Resources Committee agreed this item on Tuesday 28 November 2017. Below is the council's own wording, with the papers it was decided on.
Resolved
The Committee agreed to write off the sum of £374,498.27
2.1Landowners can provide planning obligations under Section 106 of the Town and Country Planning Act 1990. The usual purpose of such obligations is to make acceptable a development proposal which would otherwise not be acceptable. Traditionally, obligations deal with the use and development of land and the provision of payments to contribute to infrastructure improvements required to mitigate the impact of the development and to make the development acceptable.
2.2Planning obligations are offered either by agreement with the Council as local planning authority, or by unilateral obligations provided by developers. These documents are generally referred to as “section 106 agreements”, and there is also reference to “developer contributions”. Strategy and Resources Committee 28 November 2017 2.3 Since the adoption in Epsom & Ewell of Community Infrastructure Levy, s106 agreements are used only in relation to very site specific requirements and affordable housing contributions.
2.4Persimmon Homes was granted planning permission in 2013 for a development comprising of 85 houses at Lintons Lane. The permission (13/00250/FUL) was subject to a s106 obligation to pay infrastructure contributions totalling £827K. The various contributions fell due for payment at various different stages of development.
2.5The financial contribution of £827,246.59 comprised of:
2.5.1 Education (Primary): £184,016.43
2.5.2 Education (Secondary): £199,634.92
2.5.3 Transport: £177,110.78
2.5.4 Libraries £12,227.06
2.5.5 Open Space (Children) £4,462.43
2.5.6 Open Space (Parks and Gardens and Amenity Green Space) £ 22,396.10
2.5.7 Open Space (Outdoor Sports Facilities) £ 121,544.24
2.5.8 Environmental Improvements) £ 66,461.94
2.5.9 Monitoring Charge @ 5% £ 39,392.69
2.6The development had commenced and an invoice was raised on 15th December 2014 for the first initial scheduled payment and these monies (£282,761.17) were paid by the developer. Interest was applied to the original amount due in accordance with the contracted terms of the S106 agreement.
2.7The initial invoice was in respect of:
2.7.1 Monitoring £39,392.69 + £913.77 interest = £40,306.46
2.7.2 Transport £88,555.39 +£2,054.16 interest = £90,609.55
2.7.3 Open Space (Children) £4,462.43 + £103.51 interest = £4565.94
2.7.4 Open Space (Parks and Gardens and Amenity Green Space) £22,396.10 + £519.51= £22,915.61
2.7.5 Open Space (Outdoor Sports Facilities) £121,544.24 + interest £2,819.38 = £124,363.62 Strategy and Resources Committee 28 November 2017 2.8 A separate application was made during 2014 by the developer under section 73 of the Town and Country Planning Act 1990 to “vary” the conditions attached to the 2013 permission. This application was approved on 8 December 2014 (14//00910/REM), which was after the development had commenced under the original permission.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Write-off: Section 106 AgreementReport | 106 KB | DownloadRead as text |
Follow Strategy and Resources Committee at Epsom and Ewell and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 10 Nov 2026 | Exceptional CIL-Related Ex Gratia Payment PolicyFollowing consideration, the committee unanimously resolved tot was resolved: (1) Note the contents of the Government... | Noted | Open |
| 10 Nov 2026 | Response to consultationFollowing consideration, the committee unanimously resolved to: (1) Note the report | Noted | Open |
| 10 Nov 2026 | Conferring the Title of Honorary FreewomanFollowing consideration, the committee agreed with 7 votes for and 1 member not voting to: (1) recommend that the Cou... | Agreed | Open |
| 10 Nov 2026 | Update from the Town Twinning Working GroupFollowing consideration, the committee agreed with 6 votes for, 1 abstention and 1 member not voting to: (1) Note the... | Agreed | Open |
| 10 Nov 2026 | Urgent DecisionFollowing consideration, it was unanimously resolved to: (1) Note the urgent decision taken and the reasons for that ... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.