Nonsuch Park JMC - Update on Heritage Lottery Funding (HLF) bid
AgreedCommittee2 papers
Nonsuch Park Joint Management Committee agreed this item on Monday 29 January 2018. Below is the council's own wording, with the papers it was decided on.
It was agreed that in order to progress the development of a bid within the tight deadlines set out by the HLF a working group would be set up to include the following officers/councillors :- Councillors Mary Burstow and Mike Teasdale; Dominic Aslangul (Neighbourhood Officer LBS), Sam Whitehead (Streetcare Manager EEBC), Peter Steel (Head Gardener), Tony Wainwright (Accountant) and Sandra Dessent (Democratic Services Officer). The meeting would be set up following confirmation from the HLF panel that initial proposals were acceptable. Therefore having considered the report the Committee agreed the recommendation as follows: (1) To set up a working group (comprising the attendees listed above) to discuss and finalise proposals for an HLF Grants bid, and determine the feasibility of completing a first round submission by August 2018.
Word for word from the decision Epsom and Ewell published for this meeting.Source: democracy.epsom-ewell.gov.uk
1.1This report sets out proposals to develop an HLF Heritage Grants first-round application for the park, the timescales involved and the financial implications.
2 Issues
2.1In November 2016, the Nonsuch JMC agreed to progress with the development of an HLF Parks for People bid for the park, subject to sufficient match funding being secured. This followed identification of a list of provisional proposals to take forward as part of the first-round application for the park following meetings with the park’s volunteer groups and key stakeholders. NONSUCH PARK JOINT MANAGEMENT COMMITTEE 29 JANUARY 2018
2.2In December 2017, the Heritage Lottery Fund announced that it would cease to take new applications for the Parks for People programme with immediate effect following a reduction in Lottery funding, however the HLF’s Heritage Grants scheme for new grant requests up to £5 million would continue for a limited period; as Heritage Grants is shared between museums, arts projects and other heritage projects, the process is likely to be competitive with a reduction in the overall number of parks projects funded going forward.
2.3The Neighbourhood Manager (LBS) and Streetcare Manager (EEBC) are awaiting detailed feedback from HLF’s Development Manager with regard to the proposed development of a Heritage Grants programme bid, following submission of a project enquiry form (based on the provisional proposals drawn up for the Parks for People bid) sent to the HLF in early January 2018. Initial comments received in advance of the full response are that there is potential to develop a project that addresses the outcomes for Heritage Grants.
3 HLF Heritage Grants Application Process
3.1The application process is in two rounds. The final deadline for first-round applications is 16th August 2018, with HLF deciding whether the applications have been successful in December 2018. Appendix 1 is an extract from the HLF manual, which sets out the different levels of information required in a first-round and second-round application.
3.2If successful at the first-round application, the project enters the development phase, in which the more detailed second-round application is developed using the development grant secured from HLF. Second-round applications can be submitted up to 24 months after first-round approval. There are currently four deadlines each year in March, June, April and December.
3.3Key tasks carried out in the development phase include the commissioning of necessary surveys, consultations or investigations in relation to any proposed capital works to develop plans and proposals (eg traffic and access surveys, hydrological surveys, ecological surveys etc); consultation with new and existing audiences to develop a detailed programme of activities to engage people with heritage; development of a detailed timetable, costs and cash flow for the delivery phase; evidence of how project outcomes will be sustained. These all help to inform and shape the final project proposals for the park, which will be implemented at the delivery phase if the bid is successful and the main grant is secured following the second-round application.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Nonsuch Park Joint Management Committee at Epsom and Ewell and we tell you when its next papers are published, before the meeting rather than after it.
NJMC Finance Report & Budget 2021/22Agreed to note the latest 2020/21 forecast position; (2) Agreed the revenue budget for 2021/22 as set out in Appendix...
NJMC Finance Report & Budget 2020/21Agreed the revenue budget for 2020/21 as set out in Annexe 1; (3) Agreed to seek contributions of £103,430 from both ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.