Nonsuch Park Joint Management Committee agreed this item on Monday 25 January 2021. Below is the council's own wording, with the papers it was decided on.
Agreed to note the progress of the approved 2020/21 priority planned maintenance works, including the unforeseen additional Health & Safety works carried out during the year. (2) Considered and approved the proposed priority planned maintenance works for 2021-2022.
Word for word from the decision Epsom and Ewell published for this meeting.Source: democracy.epsom-ewell.gov.uk
This report provides an update on the approved 2020-21 priority planned maintenance programme including the unforeseen Health and Safety works undertaken during the year. It also seeks approval for the forthcoming 2021-22 priority planned maintenance works.
Recommendation (s) The Committee is asked to:
(1) Note the progress of the approved 2020/21 priority planned maintenance works, including the unforeseen additional Health & Safety works carried out during the year.
(2) Consider and approve the proposed priority planned maintenance works for 2021-2022.
Reason for recommendation
1.1The proposed priority planned maintenance works are essential to meet the JMC’s landlord obligations and health & safety requirements of the Park.
Background
2.1In February 2020, the JMC received an update on the approved priority works for the previous year. Nonsuch Park Joint Management Committee 25 January 2021 2.2 This report provides an update on the approved priority works for the current year (2020/21). It also identifies the highest priority works for approval to be carried out in 2021/22 from within the budget allocated.
3 Update on 2020/21 Priority and Health & Safety works
3.1External redecoration to Mansion House windows
3.2An earlier inspection of the windows had revealed extensive water damage from rot and decay. This would require major repair prior to redecoration.
3.3The tender documentation was amended to include the repairs. A full specification schedule and drawings were sent out to tender in August 2020 and were returned on 4th September 2020.
3.4Two tender returns were received and two suppliers failed to respond. The lowest cost tender received was £63,164. It did not include an allowance for timber repairs which was anticipated to cost in the region of £10,000.
3.5These costs exceed the £30,000 set aside in the 2020/21 priority works budget and therefore, there are insufficient funds to proceed this year.
3.6It is proposed to carry forward this year’s unspent budget to 2021-22 to provide sufficient funds in next year’s budget and enable the window repairs and redecoration to proceed.
3.7Greenhouse wall to formal Gardens
3.8The works were tendered in June 2020 with 3 tender returns received. The cost was £16,224 and the works were completed in September 2020.
3.9Before and after photos are attached at Appendix 1 to illustrate the high quality workmanship of the specialist brickwork restoration contractor.
3.10Roof Repairs above café
3.11Reports of roof leaks from the tenant were thoroughly investigated and subsequently repaired to prevent any water ingress damage to the Mansion House – in particular, the recently refurbished first floor.
3.12Various roofing repairs were carried out above the café area and Mansion House including;
Removal of defective lead flashing on the parapet wall. This also included the installation of a new roof covering (rubber bond fleece sheeting) above the flats; refitting the slates and refitting lead work to prevent leaks.
All loose ridge roof tiles were removed and re-bedded in fresh mortar. Nonsuch Park Joint Management Committee 25 January 2021 General roof repairs were undertaken to the lead apron. New lead sheeting and sealant were fitted.
3.13The above works were completed in June 2020 and no leaks have since been reported. The cost of the work was £3,000.
3.14Pathway between Nonsuch Mansion and Sparrow Farm Lodge
3.15It was originally intended to continue the rustic surfacing to the worst affected areas of the pathway. An inspection was carried out with the section of pathway from Sparrow Farm Lodge car park down to the gated area being deemed to be in the worst condition.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Nonsuch Park Joint Management Committee at Epsom and Ewell and we tell you when its next papers are published, before the meeting rather than after it.
NJMC Finance Report & Budget 2021/22Agreed to note the latest 2020/21 forecast position; (2) Agreed the revenue budget for 2021/22 as set out in Appendix...
NJMC Finance Report & Budget 2020/21Agreed the revenue budget for 2020/21 as set out in Annexe 1; (3) Agreed to seek contributions of £103,430 from both ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.