Resolved
Agreed to proceed with the silt removal at an extra cost of up to £82,000; (3) Approved the use of S106 from the agreements listed in paragraph 5.3 of the report to fund the works.
Strategy and Resources Committee agreed this item on Thursday 1 February 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
Agreed to proceed with the silt removal at an extra cost of up to £82,000; (3) Approved the use of S106 from the agreements listed in paragraph 5.3 of the report to fund the works.
Strategy and Resources Committee 1 February 2018
Rosebery Park Pond - Silt Removal
Report of the: Head of Property & Regeneration Contact: Tony Foxwell Urgent Decision?(yes/no) Yes If yes, reason urgent decision required: The main contract is underway on site and a decision is required urgently. Annexes/Appendices (attached): None Other available papers (not attached): N/A
Report summary The report highlights issues with the renovation of Rosebery Park Pond and requests authority to use additional funds to remove accumulated silt.
Recommendation (s) That the Committee:
(1) Notes the urgent decision taken under delegated authority, in consultation with the Chairman, to allocate additional funds to the project for the perimeter detail of the pond;
(2) Agrees either: Option 1: to proceed with silt removal at an extra cost of £82,000 or Option 2: to delay works until the following year and seek their inclusion in the Capital Programme;
(3) Should the Committee agree to proceed with Option 1 (silt removal), to approve the use of S106 funds from the agreements listed in paragraph 5.3 of the report to fund the works.
1 Implications for the Council’s Key Priorities, Service Plans and Sustainable Community Strategy
1.1Supporting our community and improving the quality of life for all residents.
2 Extra works to Perimeter detail of Pond
2.1The restoration of the pond in Rosebery Park is underway, after safely removing the fish and relocating them to the Stew ponds. The pond is now empty. Strategy and Resources Committee 1 February 2018 2.2 The works involve reconstructing the defective perimeter detail that had collapsed due to water damage. After commencement of works, inspection revealed the structure to be in worse condition than originally thought.
2.3Prior to preparing specification documentation, when the scope of the works were being looked into, trial holes were made to investigate the perimeter construction. Unfortunately, due to the amount of fish in the pond it was not possible at that stage to drain the pond completely to inspect the entire structure. Design drawings and a specification were compiled from this exercise.
2.4The proposed design was based on a fillet concrete detail with liner dressed down into the pond. As the structure has been completely undermined with water it is no longer bonded to the ground and water is flowing under the lower edge of concrete. The defective concrete and perimeter edge detail has to be removed, a new detail has been designed and agreed by the Structural Engineer and costs submitted by the main contractor.
2.5This element of the works required urgent approval to avoid incurring costs through delay and lack of materials as the main contractor is already on site. It would result in disruption to the works and additional plant, materials and site set up costs of £2,800 per week as the contract is well underway. Officers therefore consulted the Chairman about the decision to allow the works to continue.
2.6The additional costs for alteration to the perimeter detail of the pond are £33,000.
3 Silt Removal
3.1A survey carried out in 31 October 2014 that took measurements and levels of silt within the pond area. The proposed removal of the silt was put into a 10-year maintenance plan to be addressed at some future date.
3.2With the pond empty, the extent of the silt at the base of the pond is of concern and while carrying out the main construction work, the opportunity presents itself to undertake these works as well. This would also have the benefit of minimising the disruption to the local wildlife, particularly as the pond is currently empty of fish.
3.3There are three methods of removing silt from ponds:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Rosebery park pond: silt removalReport | 120 KB | DownloadRead as text |
Follow Strategy and Resources Committee at Epsom and Ewell and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 10 Nov 2026 | Exceptional CIL-Related Ex Gratia Payment PolicyFollowing consideration, the committee unanimously resolved tot was resolved: (1) Note the contents of the Government... | Noted | Open |
| 10 Nov 2026 | Response to consultationFollowing consideration, the committee unanimously resolved to: (1) Note the report | Noted | Open |
| 10 Nov 2026 | Conferring the Title of Honorary FreewomanFollowing consideration, the committee agreed with 7 votes for and 1 member not voting to: (1) recommend that the Cou... | Agreed | Open |
| 10 Nov 2026 | Update from the Town Twinning Working GroupFollowing consideration, the committee agreed with 6 votes for, 1 abstention and 1 member not voting to: (1) Note the... | Agreed | Open |
| 10 Nov 2026 | Urgent DecisionFollowing consideration, it was unanimously resolved to: (1) Note the urgent decision taken and the reasons for that ... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.