Note: This item of business was brought up the Agenda with the consent of the meeting, there being a member of the public in attendance for this particular item. The Committee: (1) Approved an additional budget of £68,000 to cover all the costs in connection with the submission of a planning application for the Wells site; (2) Agreed that the £68,000 be funded from the Corporate Reserve; (3) Agreed to a report being brought back to September 2018 Strategy and Resources Committee with an update on progress.
Word for word from the decision Epsom and Ewell published for this meeting.Source: democracy.epsom-ewell.gov.uk
2.1At its February 2018 meeting, Committee considered the future use of the Wells site and approved the following recommendations:- Strategy and Resources Committee 26 July 2018
The residential redevelopment of The Wells Site, including the provision of a community facility of up to 1,500 sq ft (to be operated and managed by the community) is undertaken by the Council or its wholly owned trading company.
PwC (PricewaterhouseCooper) be engaged to advise on how to achieve the outcome set out in recommendation 1 above at a cost of up to £15,000 to be funded from the Corporate Project Reserve.
The Head of Property and Regeneration, in consultation with the Chief Finance Officer and Chief Legal Officer, be authorised to act on the advice received from PwC.
2.2Should a final business case prove the development’s viability (both financially and otherwise), PwC (Pricewaterhouse Cooper) has indicated that the most efficient structure would be for the Council to undertake the redevelopment itself and, upon completion, transfer any units for rent to a wholly owned trading company.
2.3Approval to appoint the procured professional team and allocate an initial £92,000 budget was a decision taken in consultation with the Committee Chairman. The professional team consists of development consultant, architect, planning consultant and quantify surveyor (cost consultant).
2.4The professional team will produce the development brief i.e. to assess the redevelopment potential of the site and appraise its financial viability.
2.5It is expected the professional team will complete the working up of a draft development brief for the September 2018 meeting. If approved, it will allow officers to move forward with the consultation with residents.
2.6Following consultation, the development brief will be finalised and will form the business case to support redevelopment of the Wells site. The purpose of the business case will be to demonstrate the proposals for development are financially deliverable.
2.7The completed business case will underpin a subsequent Committee Report seeking approval of the final scheme and authority to submit a planning application for final scheme.
3 Proposals
3.1In line with the discussions, the key criteria for the development brief are:-
mixed use scheme comprising residential and a community facility
retention of a public children’s playground
retention of a public Right of Way Strategy and Resources Committee 26 July 2018 provision of sufficient parking
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Strategy and Resources Committee at Epsom and Ewell and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.