Resolved
It was resolved: That the Committee supported the budget increase of £23,000 to the Ashley Centre Car Park safety fencing scheme, subject to the agreement by Strategy and Resources committee to the funding from the capital receipts reserve.
Environment Committee agreed this item on Tuesday 29 January 2019. Below is the council's own wording, with the papers it was decided on.
Resolved
It was resolved: That the Committee supported the budget increase of £23,000 to the Ashley Centre Car Park safety fencing scheme, subject to the agreement by Strategy and Resources committee to the funding from the capital receipts reserve.
2.1In September 2017 a capital bid was made to install security fencing on levels 4C and 5 of the Ashley centre car park. The purpose of this was t prevent anti-social behaviour, such as items being dropped from top floor of car park, and to deter potential attempts from those wishing to self- harm. Environment and Safe Communities Committee 29 January 2019 2.2 The proposal was split as follows:
Fencing £97,240
Stairwell railings £18,000
Stairwell windows £18,000
Fire Protection doors £20,000
Contingency £11,760
Total £165,000
2.3The proposal and bid was agreed and funds were made available at the start of the financial year 2018/19. The works for the fencing and stairwell windows were tendered in July 2018 with return date of 17 August 2018. Out of five contractors invited only two returned with fixed price tenders, one of £168,502 and another of £153,495.
2.4The project was highlighted as a most urgent priority due to the serious issues of suicides at the car park, the most recent incidents occurring on 24 September 2017 and 14 June 2018. This highlighted the urgency, with the Police and Ashley Centre shopping management calling for urgent action.
2.5The initial works order was placed on 28 September 2018, but after investigations it was deemed that the floor surface of level 4D was not suitable to fix to, as this would damage the waterproofing between the floors and could cause leaks into the shops units below.
2.6Additional structural investigations were carried out to ascertain a safe fixing mechanism to prevent wind from blowing the railings off the roof. This prevented orders being made for all materials in a single process, splitting the ordering into 2 phases. The two separate deliveries required two cranes to lift materials on to roof rather than one.
2.7The project commenced on 19 November 2018 and is due for completion by 8 February 2019.
3 Proposals
3.1The budget of £165,000 for the project has been exceeded due to the following issues:
3.2Instructions to proceed most urgently - this required a quick turnaround of computer aided design drawings by a consultant which cost an additional £5,390. Environment and Safe Communities Committee 29 January 2019 3.3 To proceed quickly, an initial order for the first phase of fencing was made rather than waiting for structural investigations to be completed, saving 2 weeks in time. An additional crane hire was required at an unbudgeted cost of £3,451.
3.4Fencing extra works – additional areas between the Playhouse and car park were agreed at a pre-start meeting. Issues had previously occurred with shopping trollies being thrown off the roof. This area was not proposed in original capital bid paperwork and cost £5,655.
3.5Structural investigation as detailed in paragraph 2.6 cost £4,760.
3.6Cost of lightening protection measures not initially included in bid - £4,869.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Ashley centre car park safety fencingReport | 78 KB | DownloadRead as text |
Follow Environment Committee at Epsom and Ewell and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 30 Jun 2026 | Questions and Statements from the PublicThere was one statement from a member of the public in relation to agenda item 6 on the agenda, Library of Things at ... | Decided | Open |
| 30 Jun 2026 | Declarations of InterestCllr Julie Morris declared a personal interest in agenda item 8 – Free Summer Tennis – and would leave the room for t... | Decided | Open |
| 30 Jun 2026 | Minutes of the Previous MeetingThe Committee confirmed as a true record the Minutes of the Committee held on 4 March 2026 and the Chair signed them. | Decided | Open |
| 30 Jun 2026 | Environment & Sustainability Working GroupFollowing Consideration, it was resolved to: (1) Agree the continuation of the Environment and Sustainability Working... | Agreed | Open |
| 30 Jun 2026 | Car Park Working GroupFollowing consideration the Committee agreed to: (1) Agree to the continuation of a Car Parking Working Group (CPWG).... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.