Resolved
The Committee approved the use of £23,000 from the capital receipts reserve to fund the additional budget, subject to the Environment & Safe Communities Committee supporting the increase in budget at the meeting on 29 January 2019.
Strategy and Resources Committee approved this item on Thursday 31 January 2019. Below is the council's own wording, with the papers it was decided on.
Resolved
The Committee approved the use of £23,000 from the capital receipts reserve to fund the additional budget, subject to the Environment & Safe Communities Committee supporting the increase in budget at the meeting on 29 January 2019.
2.1In September 2017 a capital bid was made to install security fencing on levels 4C and 5 of the Ashley centre car park. Preventing anti-social behaviour, such as things being dropped from top floor of car park and to deter potential attempts from those wishing to self-harm.
2.2The proposal was split as follows: Strategy and Resources Committee 31 January 2019 Fencing £97,240
Stairwell railings £18,000
Stairwell windows £18,000
Fire Protection doors £20,000
Contingency £11,760
Total £165,000
2.3The proposal and bid was agreed and funds were made available at the start of the financial year 2018/19. The works for the fencing and stairwell windows were tendered in July 2018 with return date of 17th August 2018. Out of five contractors invited only two returned with fixed price tenders, one of £168,502 and another of £153,495.
2.4The project was highlighted as most urgent priority due to the serious issues of suicides at the car park, the most recent incidents occurring on 24th September 2017 and 14th June 2018. This highlighted the urgency, with the Police and Ashley Centre shopping management calling for urgent action.
2.5The initial works order was placed on 28/09/18, but after investigations it was deemed that the floor surface of level 4D was not suitable to fix to, as this would damage the waterproofing between the floors and cause leaks into Waitrose shops.
2.6Additional structural investigations were carried out to ascertain a safe fixing mechanism to prevent wind from blowing the railings off the roof. This prevented orders being made for all materials in a single process, splitting the ordering into 2 phases. The two separate deliveries required two cranes to lift materials on to the roof rather than one.
2.7The project commenced on 19 November 2018 and is due for completion by 8 February 2019.
3 Proposals
3.1The budget of £165,000 for the project has been exceeded due to the following issues:
3.1.1 Instructions to proceed most urgently - this required a quick turnaround of computer aided design drawings by consultant which cost an additional £5,390.
3.1.2 To proceed quickly, an initial order for the first phase of fencing was made rather than waiting for structural investigations to be completed, saving 2 weeks in time. An additional crane hire was required at an unbudgeted cost of £3,451. Strategy and Resources Committee 31 January 2019 3.1.3 Fencing extra works – additional areas agreed at pre-start meeting between the Playhouse and car park, where previous issues occurred with youths throwing shopping trollies off of roof. This area was not proposed in original capital bid paperwork and cost £5,655.
3.1.4 Structural investigation as detailed in paragraph 2.6 cost £4,760.
3.1.5 Cost of lightening protection measures not initially included in bid - £4,869.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Ashley Centre car park safety fencingReport | 97 KB | DownloadRead as text |
Follow Strategy and Resources Committee at Epsom and Ewell and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 10 Nov 2026 | Exceptional CIL-Related Ex Gratia Payment PolicyFollowing consideration, the committee unanimously resolved tot was resolved: (1) Note the contents of the Government... | Noted | Open |
| 10 Nov 2026 | Response to consultationFollowing consideration, the committee unanimously resolved to: (1) Note the report | Noted | Open |
| 10 Nov 2026 | Conferring the Title of Honorary FreewomanFollowing consideration, the committee agreed with 7 votes for and 1 member not voting to: (1) recommend that the Cou... | Agreed | Open |
| 10 Nov 2026 | Update from the Town Twinning Working GroupFollowing consideration, the committee agreed with 6 votes for, 1 abstention and 1 member not voting to: (1) Note the... | Agreed | Open |
| 10 Nov 2026 | Urgent DecisionFollowing consideration, it was unanimously resolved to: (1) Note the urgent decision taken and the reasons for that ... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.