Resolved
Following consideration, it was resolved: That the Committee: (1) Noted the progress to date; (2) Agreed to fund the increased works cost of £150,000 from the Corporate Projects Reserve.
Strategy and Resources Committee noted this item on Tuesday 30 July 2019. Below is the council's own wording, with the papers it was decided on.
Resolved
Following consideration, it was resolved: That the Committee: (1) Noted the progress to date; (2) Agreed to fund the increased works cost of £150,000 from the Corporate Projects Reserve.
2.1At its 17 April 2018 meeting, Committee approved the following recommendations to progress the extension of the Council owned Epsom cemetery between Ashley Road and Downs Road:- Strategy and Resources Committee 30 July 2019 Agree the submission of a planning application for the proposed Cemetery extension.
Approve the appointment of a specialist consultant to prepare the planning application, procure the contractor and oversee completion of the works.
If negotiations fail, to authorise the use of compulsory purchase making powers to acquire the required land.
2.2Following a tender exercise, The Environment Partnership (TEP) were appointed the Council’s specialist consultant. TEP provide independent environment planning and design advice with the benefit of direct experience of cemetery operations.
2.3Following successful negotiations between the Council and landowner, Committee approved the acquisition of the extension land at its 26 July 2018 meeting.
2.4TEP submitted the planning application on 21 September 2018 and planning permission (subject to conditions) was granted on 31 December 2018. The conditions (which include the specific treatment of boundaries and landscaping proposals) are necessary to preserve the setting and character of Epsom Cemetery. The Cemetery has been in existence since c1870, and comprises various Grade II Listed structures including the Chapel, War Memorial, Gate Piers and Cemetery Lodge.
3 Current Position
3.1The contractor tender documentation was sent out on 25 February 2019 to a select number of specialist contractors. This method of procurement (as distinct from an open, full market exercise) is often utilised where projects are specialist in nature. These works are deemed specialist with a relatively small number of contractors with experience of cemetery development.
3.2Tender returns were due 25 March 2019 with an anticipated work commencement date of 23 April 2019 and completion by Christmas 2019.
3.3Based on comparable schemes, TEP were confident the tenders would reflect the £650k approved capital budget.
3.4However, all received tenders exceeded the approved capital budget available with the highest tender almost £330k over budget.
3.5The tender analysis undertaken by TEP revealed specific works items were responsible for the extremely high variances between the contractors. By way of example, the boundary Random Rubble Wall and the general landscaping works (both conditions of the planning permission) returned the highest variances between the contractors. Strategy and Resources Committee 30 July 2019 3.6 It was noted that if the lowest price for each individual item from each contractor were used to cost the full works contract, then the cost of the works would have been below the approved budget. This would suggest that the comparable cost evidence used by TEP to estimate the contract value was undertaken in good faith.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Value Engineering AnalysisAppendix A | 384 KB | Download |
PDF |
Epsom Cemetery ExtensionReport | 78 KB | DownloadRead as text |
Follow Strategy and Resources Committee at Epsom and Ewell and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 10 Nov 2026 | Exceptional CIL-Related Ex Gratia Payment PolicyFollowing consideration, the committee unanimously resolved tot was resolved: (1) Note the contents of the Government... | Noted | Open |
| 10 Nov 2026 | Response to consultationFollowing consideration, the committee unanimously resolved to: (1) Note the report | Noted | Open |
| 10 Nov 2026 | Conferring the Title of Honorary FreewomanFollowing consideration, the committee agreed with 7 votes for and 1 member not voting to: (1) recommend that the Cou... | Agreed | Open |
| 10 Nov 2026 | Update from the Town Twinning Working GroupFollowing consideration, the committee agreed with 6 votes for, 1 abstention and 1 member not voting to: (1) Note the... | Agreed | Open |
| 10 Nov 2026 | Urgent DecisionFollowing consideration, it was unanimously resolved to: (1) Note the urgent decision taken and the reasons for that ... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.