Community & Wellbeing Centre Boiler Replacement Capital Project
DecidedCommittee1 paper
Strategy and Resources Committee decided this item on Thursday 29 September 2022. Below is the council's own wording, with the papers it was decided on.
Following consideration, the Committee unanimously resolved to: (1) Authorise additional funding of £55,000 from the Capital Receipts Reserve to deliver replacement boilers and controls at the Community & Wellbeing Centre. (2) Authorise the purchase of the equipment required now to carry out the works.
Word for word from the decision Epsom and Ewell published for this meeting.Source: democracy.epsom-ewell.gov.uk
This report requests authorisation to increase the budget for the Community & Wellbeing Centre boilers replacement project.
Recommendation (s) The Committee is asked to:
(1) Authorise additional funding of £55,000 from the Capital Receipts Reserve to deliver replacement boilers and controls at the Community & Wellbeing Centre.
Reason for recommendation
1.1The project is important for the delivery of the capital programme and support the Council’s Climate Change Action Plan.
1.2Once completed, it will reduce the Council’s carbon footprint, provide revenue savings, upgrade our assets, reduce our maintenance costs and provide business continuity.
Background
2.1Reflecting the current economic environment, EEBC has been experiencing very high levels of pricing for tendered projects. This has prevented some projects from proceeding due to insufficient budget allocation. Strategy and Resources Committee 20 September 2022 2.2 EEBC is not alone with both the public and private sectors experiencing unprecedented national and global inflationary pressures. Factors include a shortage of skilled labour in the building and engineering industries, increased material and transport costs, the energy crisis, Brexit supply issues and the continuing invasion of Ukraine.
2.3The existing capital budget is insufficient to cover the unforeseen scale of these increases and exceeds officer delegation to accommodate minor budget adjustments.
3 Community & Wellbeing Centre – boilers replacement
3.1The works include the replacement of the boilers and water heaters at the Community & Wellbeing centre. This is to reduce the energy consumption and provide a more efficient source of heating and hot water, to support the Council’s Climate Change Action Plan.
3.2The heating and hot water boilers are the inefficient non-condensing type and over 10 years old. The control panel is 20 years old and in need of replacement.
3.3The building is used as a local support hub for the elderly as well as providing specific facilities for those clients unable to cope on their own. The building requires a specific level of heat for comfort and the replacement of the plant will ensure that continuity.
3.4The replacement boilers are estimates to provide a gas saving of 25% and a reduction in electricity running costs by replacing the electric hot water cylinders with gas operated cylinders.
3.5The expected reduction in costs will reduce the Council’s energy expenditure at a time of rapidly rising energy prices.
3.6The project has been tendered twice; the first tender was returned with only one tender received out of a requested four. Officers believed this tender to be high at £134,000 and the decision to re- tender was taken to obtain better value.
3.7Following the second tender exercise, four priced tenders were returned out of the seven selected, with the cost ranging from £105,000 to £160,000.
3.8The project was tendered on 100% price with no quality scoring matrix required. The lowest priced return will be awarded the tender as all suppliers are reputable mechanical and electrical companies.
3.9Officers recommend awarding the contract to the lowest tender for the sum of £105,000. Strategy and Resources Committee 20 September 2022 3.10 The existing budget is £50,000 and therefore, additional funds of £55,000 are requested for the project to proceed.
3.11The duration of the works is estimated to be 8 weeks but as the heating will need to be turned off while the works are undertaken, the project cannot be commenced until the Summer of 2023. This is due to the elderly residents at the centre being particularly vulnerable and need to be kept warm.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Strategy and Resources Committee at Epsom and Ewell and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.