Strategy and Resources Committee, Thursday 29 September 2022 at 7.30pm

Community & Wellbeing Centre Boiler Replacement Capital Project

Decided Committee 1 paper

Strategy and Resources Committee decided this item on Thursday 29 September 2022. Below is the council's own wording, with the papers it was decided on.

Item26

Resolved

Following consideration, the Committee unanimously resolved to: (1) Authorise additional funding of £55,000 from the Capital Receipts Reserve to deliver replacement boilers and controls at the Community & Wellbeing Centre. (2) Authorise the purchase of the equipment required now to carry out the works.
Word for word from the decision Epsom and Ewell published for this meeting. Source: democracy.epsom-ewell.gov.uk

Follow this further

Built from Epsom and Ewell's papers

What the report saysPro

Report to Strategy and Resources Committee

Summary

This report requests authorisation to increase the budget for the Community & Wellbeing Centre boilers replacement project.

Recommendation (s) The Committee is asked to:

(1) Authorise additional funding of £55,000 from the Capital Receipts Reserve to deliver replacement boilers and controls at the Community & Wellbeing Centre.

Reason for recommendation

1.1The project is important for the delivery of the capital programme and support the Council’s Climate Change Action Plan.

1.2Once completed, it will reduce the Council’s carbon footprint, provide revenue savings, upgrade our assets, reduce our maintenance costs and provide business continuity.

Background

2.1Reflecting the current economic environment, EEBC has been experiencing very high levels of pricing for tendered projects. This has prevented some projects from proceeding due to insufficient budget allocation. Strategy and Resources Committee 20 September 2022 2.2 EEBC is not alone with both the public and private sectors experiencing unprecedented national and global inflationary pressures. Factors include a shortage of skilled labour in the building and engineering industries, increased material and transport costs, the energy crisis, Brexit supply issues and the continuing invasion of Ukraine.

2.3The existing capital budget is insufficient to cover the unforeseen scale of these increases and exceeds officer delegation to accommodate minor budget adjustments.

3 Community & Wellbeing Centre – boilers replacement

3.1The works include the replacement of the boilers and water heaters at the Community & Wellbeing centre. This is to reduce the energy consumption and provide a more efficient source of heating and hot water, to support the Council’s Climate Change Action Plan.

3.2The heating and hot water boilers are the inefficient non-condensing type and over 10 years old. The control panel is 20 years old and in need of replacement.

3.3The building is used as a local support hub for the elderly as well as providing specific facilities for those clients unable to cope on their own. The building requires a specific level of heat for comfort and the replacement of the plant will ensure that continuity.

3.4The replacement boilers are estimates to provide a gas saving of 25% and a reduction in electricity running costs by replacing the electric hot water cylinders with gas operated cylinders.

3.5The expected reduction in costs will reduce the Council’s energy expenditure at a time of rapidly rising energy prices.

3.6The project has been tendered twice; the first tender was returned with only one tender received out of a requested four. Officers believed this tender to be high at £134,000 and the decision to re- tender was taken to obtain better value.

3.7Following the second tender exercise, four priced tenders were returned out of the seven selected, with the cost ranging from £105,000 to £160,000.

3.8The project was tendered on 100% price with no quality scoring matrix required. The lowest priced return will be awarded the tender as all suppliers are reputable mechanical and electrical companies.

3.9Officers recommend awarding the contract to the lowest tender for the sum of £105,000. Strategy and Resources Committee 20 September 2022 3.10 The existing budget is £50,000 and therefore, additional funds of £55,000 are requested for the project to proceed.

3.11The duration of the works is estimated to be 8 weeks but as the heating will need to be turned off while the works are undertaken, the project cannot be commenced until the Summer of 2023. This is due to the elderly residents at the centre being particularly vulnerable and need to be kept warm.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Community & Wellbeing Centre Boiler Replacement Capital ProjectReport 236 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 18 attended
ND
Councillor Neil Dallen MBEChair, present
HD
Councillor Hannah DaltonVice-Chair, present
KC
Councillor Kate ChinnCommittee Member, present
MC
Councillor Monica ColemanCommittee Member, apologies, sent representative
LF
Councillor Liz FrostCommittee Member, present
DG
Councillor David GullandCommittee Member, present
GJ
Councillor Graham Jones MBECommittee Member, present
CK
Councillor Colin KeaneCommittee Member, absent
EK
Councillor Eber KingtonCommittee Member, present
HR
Councillor Humphrey ReynoldsCommittee Member, present as substitute
AW
Councillor Alan WilliamsonCommittee Member, apologies
JK
Jackie KingOfficer, in attendance

All 18 on the meeting page

On this subject at Epsom and Ewell

Search all
  1. Community & Wellbeing Centre Boiler Replacement Capital ProjectThis decision
  2. Recommendation from the Audit and Scrutiny Committee in respect of the Called-in Decision of the Community and Wellbeing Committee made on 13 January 2026 (item 04) Regarding the Options for the Future of the Bourne Hall MuseumDeferred
  3. Community and Wellbeing Centre, Sefton Road Epsom, Surrey, KT19 9HG - 18/01359/FULApproved

More from Epsom and Ewell Strategy and Resources Committee

All decisions
MeetingDecisionOutcome
10 Nov 2026 Exceptional CIL-Related Ex Gratia Payment PolicyFollowing consideration, the committee unanimously resolved tot was resolved: (1) Note the contents of the Government... Noted Open
10 Nov 2026 Response to consultationFollowing consideration, the committee unanimously resolved to: (1) Note the report Noted Open
10 Nov 2026 Conferring the Title of Honorary FreewomanFollowing consideration, the committee agreed with 7 votes for and 1 member not voting to: (1) recommend that the Cou... Agreed Open
10 Nov 2026 Update from the Town Twinning Working GroupFollowing consideration, the committee agreed with 6 votes for, 1 abstention and 1 member not voting to: (1) Note the... Agreed Open
10 Nov 2026 Urgent DecisionFollowing consideration, it was unanimously resolved to: (1) Note the urgent decision taken and the reasons for that ... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies