Resolved
Following consideration, the Committee unanimously resolved: (1) To agree to allocate £629,000 funding from the Corporate Projects Reserve to enable the completion of the Epsom and Ewell Local Plan (2022-2040).
Strategy and Resources Committee agreed this item on Tuesday 12 December 2023. Below is the council's own wording, with the papers it was decided on.
Resolved
Following consideration, the Committee unanimously resolved: (1) To agree to allocate £629,000 funding from the Corporate Projects Reserve to enable the completion of the Epsom and Ewell Local Plan (2022-2040).
The report provides an updated financial position regarding progressing the Epsom and Ewell Local Plan (2022-2040) towards submission and subsequent adoption in accordance with the timescales defined in the recently published Local Development Scheme (November 2023).
The Licencing and Planning Policy Committee on the 22 November 2023 agreed to report the estimated shortfall in funding for completing the Local Plan to the Strategy and Resources Committee with a request to secure funding for the £629,000 shortfall.
Recommendation The Committee is asked to:
(1) To agree to allocate £629,000 funding from the Corporate Projects Reserve to enable the completion of the Epsom and Ewell Local Plan (2022-2040).
1.1The purpose of this report is to provide an update to the committee on the Local Plan budget following the public consultation on the draft Epsom and Ewell Local Plan (Regulation 18) that was undertaken between 1 February and 19 March 2023. Strategy and Resources Committee 12 December 2023 1.2 Following the closure of the public consultation an extraordinary Council meeting was held on the 22 March 2023 where the decision was made to pause the Local Plan and to allow specified tasks to be undertaken. On the 24 October 2023 the Local Plan was un-paused at an extraordinary meeting of full Council and subsequently a revised Local Plan timetable (the Local Development Scheme) was approved by the Licencing and Planning Policy Committee on the 22 November 2023.
1.3On the 22 November 2023, the Licencing and Planning Policy Committee agreed to report the estimated shortfall in funding for completing the Local Plan to this committee with a request to secure funding for the £629,000 shortfall.
2.1On the 21 June 2022, the Licencing and Planning Policy Committee (LPPC) considered a report on the Local Plan funding update, which identified a potential shortfall in funding for 2023/24 and 2024/25. The report identified:
That this Committee would be asked to approve two fixed term contract posts, the first of which is a principal policy officer (ending early May 2024) and a planning policy officer post (ending early December 2024).
As of June 2022, a total of £517,830 approved budget remained to complete the Local Plan, and that the estimated costs of progressing the Local Plan to Regulation 19 stage (excluding staffing costs) would consume most of this budget.
2.2The report concluded that the funds would not be adequate to cover the examination in public and in particular the Planning Inspectorate fees, which was a known position prior to the publication of the report. In addition, the report noted that any deviation from the approved timeline (the Local Development Scheme) that was agreed by Licencing and Planning Policy Committee on 26 April 2022 would have cost implications.
Position as of December 2023
2.3Following the decision by Council to pause the Local Plan for a period of seven months, an updated timetable for preparing the Local Plan was approved by the Licencing and Planning Policy Committee on the 22 November 2022. The revised timetable anticipates the submission of the Local Plan in May 2025. Strategy and Resources Committee 12 December 2023 Staffing
2.4The planning policy team remains fully staffed, with four permanent team members (two of which are part time) and two fulltime members on fixed term contracts. As noted in para 2.1 above the two fixed term posts end in 2024 and therefore the capacity of the team to progress the Local Plan will be impacted if the contracts are not extended.
2.5To retain experience, knowledge and capacity in the team, the costs of extending both contracts up until 31 December 2026 would be approximately £252,000.
Expenditure since June 2022
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Local Plan Budget ResourcesReport | 264 KB | DownloadRead as text |
Follow Strategy and Resources Committee at Epsom and Ewell and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 10 Nov 2026 | Exceptional CIL-Related Ex Gratia Payment PolicyFollowing consideration, the committee unanimously resolved tot was resolved: (1) Note the contents of the Government... | Noted | Open |
| 10 Nov 2026 | Response to consultationFollowing consideration, the committee unanimously resolved to: (1) Note the report | Noted | Open |
| 10 Nov 2026 | Conferring the Title of Honorary FreewomanFollowing consideration, the committee agreed with 7 votes for and 1 member not voting to: (1) recommend that the Cou... | Agreed | Open |
| 10 Nov 2026 | Update from the Town Twinning Working GroupFollowing consideration, the committee agreed with 6 votes for, 1 abstention and 1 member not voting to: (1) Note the... | Agreed | Open |
| 10 Nov 2026 | Urgent DecisionFollowing consideration, it was unanimously resolved to: (1) Note the urgent decision taken and the reasons for that ... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.