Strategy and Resources Committee, Tuesday 23 July 2024 at 7.30pm

Procurement of Harrier Centre roof replacement

Noted Committee 1 paper

Strategy and Resources Committee noted this item on Tuesday 23 July 2024. Below is the council's own wording, with the papers it was decided on.

Item13

Resolved

Following consideration, the Committee unanimously resolved to: (1) note the findings of the report and endorse the learning points from it (as set out in para 4.1 of the report).
Word for word from the decision Epsom and Ewell published for this meeting. Source: democracy.epsom-ewell.gov.uk

Follow this further

Built from Epsom and Ewell's papers

What the report saysPro

Report to Strategy and Resources Committee

Summary

To present the findings of a review into the procurement of the Harrier Centre Roof replacement, commissioned as requested by the Strategy and Resources committee meeting on the 21st September 2023.

Recommendation (s) The Committee is asked to:

(1) Note the findings of the report and endorse the learning points from it (as set out in para 4.1 of this report).

Reason for recommendation

1.1The committee is asked to note the outcome of the review following the procurement of the Harrier Centre roof replacement and support the recommended items for improvement.

Background

2.1A report seeking funding to pay for the works at the Harrier Centre was brought to the Strategy and Resources Committee on the 21st September 2023. The report sought further funding for the roof replacement project as a result of substantially increased costs from the initial estimate following a procurement exercise. Permission was sought from the committee to fund the works at the new, increased costs.

2.2Approval was given for the works at the meeting and the works have progressed through to successful completion. Strategy and Resources Committee 23 July 2024 2.3 During the meeting members of the committee raised concerns about the fact that the costs had increased since the work was first scoped. There was also concern expressed about the closeness of the final bid figures between different suppliers.

2.4The explanation for this was given to the committee reflecting that the material costs had increased over time since the original estimate. The closeness of the figures was explained by the fact that the roofing material itself was coming from one supplier and as a result of that fixed cost the only variable cost was installation costs from the various suppliers, whose margins would only differ slightly.

2.5Although the committee approved the funding it was requested that a review should take place of the procurement process to see if any lessons could be learned. That review was commissioned through our (external) internal auditors (a company called Southern Internal Audit Partnership – SIAP - who provide internal audit services for a number of local authorities in the South East of England).

2.6A summary of the key findings by SIAP are set out below.

3 Key findings from SIAP following their review of the Harrier Centre Roof procurement.

1.1At the Strategy and Resources Committee 21 September 2023 an additional funding of £105k to previously approved funding of £150k, was requested for the project.

Scope of review

2.1To review the procurement process to ascertain the reasons for the price increase and reasons why the bids were close in value.

2.2This included:

• Seek to determine if due process was followed throughout the procurement process including how the potential suppliers were identified and any due diligence undertaken around these suppliers.

• Seek to provide insight as to why prices increased from the original proposal.

3. Key findings

The procurement process

3.1Contract Standing Orders require all procurements at threshold 2 and 3 to be processed via the Council’s eSourcing platform In-Tend. This requirement was fulfilled. Strategy and Resources Committee 23 July 2024 3.2. The Council’s Procurement Strategy March 2022, section 9.3 sets out that local SMEs should be encouraged to bid for contract opportunities, subject to the normal tendering requirements. This was adopted in full in the March Request For Quotation (RFQ) and in part in the October RFQ.

3.3For the October RFQ no evidence, including a Companies House check, was identified that indicates collusion between the suppliers. All suppliers completed the statement of non-collusion as required.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Procurement of Harrier Centre roof replacementReport 244 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 17 attended
ND
Councillor Neil Dallen MBEChair, present
HD
Councillor Hannah DaltonVice-Chair, present
KC
Councillor Kate ChinnCommittee Member, present
AC
Councillor Alex ColeyCommittee Member, present
AK
Councillor Alison KellyCommittee Member, present
RL
Councillor Robert LeachCommittee Member, present
LM
Councillor Lucie McIntyreCommittee Member, present
PN
Councillor Phil NealeCommittee Member, present
SM
Councillor Steven McCormickCouncillor in Attendance, in attendance
JK
Jackie KingOfficer, in attendance
AB
Andrew BircherOfficer, in attendance
BB
Brendan BradleyOfficer, in attendance

All 17 on the meeting page

More from Epsom and Ewell Strategy and Resources Committee

All decisions
MeetingDecisionOutcome
10 Nov 2026 Exceptional CIL-Related Ex Gratia Payment PolicyFollowing consideration, the committee unanimously resolved tot was resolved: (1) Note the contents of the Government... Noted Open
10 Nov 2026 Response to consultationFollowing consideration, the committee unanimously resolved to: (1) Note the report Noted Open
10 Nov 2026 Conferring the Title of Honorary FreewomanFollowing consideration, the committee agreed with 7 votes for and 1 member not voting to: (1) recommend that the Cou... Agreed Open
10 Nov 2026 Update from the Town Twinning Working GroupFollowing consideration, the committee agreed with 6 votes for, 1 abstention and 1 member not voting to: (1) Note the... Agreed Open
10 Nov 2026 Urgent DecisionFollowing consideration, it was unanimously resolved to: (1) Note the urgent decision taken and the reasons for that ... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies